курсера

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

Вопрос 10 What project management tool typically organizes tasks into columns with labels such as to do, in progress, and done? 1 / 1 балл Kanban board Gantt chart RACI chart Work breakdown structure (WBS)

Kanban board

Вопрос 4 As a project manager, the project is your number one priority. However, you have team members with competing priorities from other projects. You want to influence them to make your project their priority. To do this, you bridge the high-level goals of the project and the day-to-day perspective of the team. You collaborate to find an outcome that works for everyone. What interpersonal skill did you mainly use in this scenario? 1 / 1 балл Build trust Practice patience Negotiate effectively Ask the right questions

Negotiate effectively

Imagine you're a project manager creating a critical path. Your stakeholders request the earliest and latest start dates for each task. What is a strategy to make this time estimate? 1 / 1 балл Develop a RACI chart. Use the forward pass or backward pass method. Review the project goals. Create a list of dependencies.

Use the forward pass or backward pass method.

Which of the following should you include in a project plan that are essential for project success? Select all that apply. a Specifically who are completing what tasks b All project tasks c Links to tasks in previously successful projects d A timeline of when the team will complete the tasks

a b d

Вопрос 8 What two steps can a project manager take to overcome the planning fallacy? 1 / 1 балл a Meet with teammates to uncover potential risks. b Increase the project's budget. c Consider all risks and carefully examine them. d Expand the project's scope.

a c

Which of the following strategies follow project plan best practices? Select all that apply. a Ask yourself if the information in your plan is clear enough for stakeholders to understand b Ask your team members daily if they are able to meet the deadlines they have for their tasks c Ask your team members to identify risks that will most likely occur and create plans to prevent or mitigate those risks d Ask team members questions about their work to gain deeper insights into their tasks for the project

a c d

What tools can a project manager use to account for issues that may cause a project delay? Select all that apply. a Task buffer b Sub-tasks c Project buffer d Gantt chart

a,c

Вопрос 7 As a project manager, you realize that with the current timeline, it's unlikely you will meet the project deadline. Which of the following strategies could help you meet the deadline? Select all that apply. 0.75 / 1 балл a Revise the project schedule without stakeholder approval. b Request more resources, such as an additional team member. c Eliminate any unnecessary tasks. d Identify tasks that can be done in parallel.

c d

Which of the following are relevant project documents you should link to in your project plan? Select all that apply. a Daily review emails and messages between the stakeholders, project manager, and project team b The organization chart that depicts everyone who works in the company with their contact information c The project charter that defines the project and outlines project goal details d RACI charts that define roles and responsibilities for individuals on a team

c, d

Вопрос 3 Fill in the blank: To determine the _____ of a project, list the milestones you must reach in order to meet the project goal on schedule. capacity planning details critical path dependencies float time

critical path


Set pelajaran terkait

Business Law - Module 5 - TORT LAW - Negligence

View Set

Final exam Anatomy of the Reproductive System and Fluid,Electrolyte and Acid Base Balance

View Set