OP2

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

What type of products have low profit margins, long product life, and predictable demand? Functional Stable Evolving Innovative

Functional

What type of products include staples that people buy in a wide range of retail outlets? Unique Innovative Functional Common

Functional

Which of the following is not an organizationally driven reason to outsource?

Generate access to new markets

Inventory turn

Cost of goods sold/Average inventory

Work-center layouts allocate dissimilar machines into cells to work on products that have dissimilar processing requirements.

F

Two common measures to evaluate supply chain efficiency are the consumer price index and the beta flow system.

FALSE

The long-term relationship between inventory, throughput, and flow time is mathematically related using

Little's law

What term refers to the management functions that support the complete cycle of material flow?

Logistics

The bill-of-material file is also known as

Product structure file and Product tree

Rank the production process layouts from lowest- to highest-volume (top to bottom).

Project Workcenter Manufacturing cell Assembly line

In which production system does the product remain in one place while resources (such as workers or equipment) travel to the product when needed? Multiple choice question. Assembly line Project layout Cellular layout

Project layout

Efficiency formula

T (sum of time) / NaC (# workstations x cycle time)

Push ordering is an example of: -channel alignment -demand forecast updating -order batching -forward buying

order batching

the ultimate goal of any MRP lot sizing approach is to balance the setup or _______________ costs and the ______________costs associated with meeting the net requirements generated by the MRP planning process.

order, holding

The file created by retracing a material requirement upward in the product structure to identify each parent item that created the demand is called a _____ record.

peg

Which of the following would be located on the MPS plan? Multiple select question. vehicle engine purchased for a production line. pens ordered from an office supply company. pen caps ordered by a pen manufacturer from a supplier. a new vehicle purchased from an automotive dealer.

pens ordered from an office supply company. a new vehicle purchased from an automotive dealer.

The __________-_______ matrix shows when different production process types are used in relation to product volume and standardization.

product process

Which of the following is a sourcing term to describe how common an item is and/or how many substitutes may be available?

specificity

Workcenters are often structured to___________ the movement of material.

optimize

days of supply

the inverse of inventory turns scaled to days

Using complex lot-sizing techniques, larger lot sizes can cause an increase in __________, complicating plant logistics. inventory setup costs supplier costs demand

inventory

Customer order decoupling point

inventory is positioned to allow entities in the supply chain to operate independently

The bullwhip effect can be reduced by __________- efforts among members of the supply chain.

synchronizing

Which of the following products would use a project layout? Multiple choice question. Bridge Automobile Mass produced toy Laptop

Bridge

_____________ is used to avoid expensive shut downs by operating 24 hours a day. Multiple choice question. Assembly line Workcenter Project layout

Continuous process

What term is used to describe a practice where a customer makes a large purchase in response to a promotion or price cut? Forward buying Hedging Buying to forecast Risky buying

Forward buying

What term is used to describe a practice where a customer makes a large purchase in response to a promotion or price cut?

forward buying

what type of products include staples that people buy in a wide range of retail outlets? -common -unique -functional -innovative

functional

Strategic sourcing is focused on the ________ needs of a business.

immediate

Strategic sourcing is focused on the ________ needs of a business. forecasted future immediate historical

immediate

Are the inventory turnover and weeks of supply measures related to one another?

yes they are mathematically inverses

cross docking is used in consolidation warehouses and targets for local delivery in area t/f

true

innovative products have higher stockout costs than functional products? t/f

true

Workcenters are often focused on

one type of operation

Which of the following is an innovative product?

personal computer

project

remain in a fixed location, equipment is moved to the product

When the supplier takes full responsibility to manage items for the customer, the supplier is performing outsourcing activities. helpful activities. vendor managed inventory. strategic sourcing.

vendor managed inventory.

When purchasing items that are highly specified and a long contract is desirable, which sourcing process should be used

vendor management theory

Which of the following is one of the dimensions depicted on a product-process matrix? Multiple choice question. Service Time Cost volume

volume

According to the logistics-system design matrix, which of the following modes of transporting products has the highest capacity and a very low cost? -highway -water -hand delivery -rail

water

Which of the following are parts of the material requirements planning system?

- master production schedule -bill of materials -inventory records

organization of product processes

- project - workcenter (jobshop) - manufacturing cell - assembly line - continuous process

which case outsourcing manufacturing is appropriate? 1. the design in manufacturing of products are closely connected and require mutual adaptation 2. the products are modularized designed and assembled together using standard modules

-2 only

Which of the following statements about inventory measures is TRUE?

-Days-of-supply measures how long (on average) a firm's inventory can support sales. -Inventory turn compares cost of goods sold to average inventory.

which initiative cannot effectively counteract the bullwhip effect -periodic ordering -everyday low price -consumer direct -Vendor management inventory

-periodic ordering

Using the assembly-line balancing procedure, which of the following is the required cycle time if the production time in minutes per day is 1440 and the required output per day in units is 2000? - 1.388 - 500 - 0.72 - Cannot be determined from the information above - 250

0.72

Which types of inventory are included in the average aggregate inventory value? 1. Raw material 2. Work-in-process 3. Finished goods 4. Distribution

1 2 3 4

The master scheduler must consider

1. Never lose sight of the aggregate plan 2. Be involved with customer order promising 3. Trade-off manufacturing, engineering and marketing conflicts

Last year, Ace Electronics had Cost of Goods Sold of $2,500,000. The average inventory value last year was $250,000. What was the inventory turnover for Ace Electronics last year? 10 8 4 6

10

There are ______ dimensions depicted on a product-process matrix.

2

Most retailers estimate that annual inventory carrying costs equals _____ of what is paid for the product.

25

Most retailers estimate that annual inventory carrying costs equals _____ of what is paid for the product

25%

Most retailers estimate that annual inventory carrying costs equals _____ of what is paid for the product. 25% 10% 2% 50%

25%

250 people/hour 15 min average time in a store how many customers in the store at any given time?

250 ppl/hour x (15/60 mins) - 62.5 customers

Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes? - 8 - 5 - None of these - 6 - 3

3 (4 + 6 + 7 + 2 + 6 + 5) / 10 = 3.

Using the assembly-line balancing procedure, which of the following is the required cycle time in minutes per unit if the daily production time is 480 minutes and the required daily output is 50 units? - 480 - 0.104 - Cannot be determined from the information above - 50 - 9.6

9.6 daily production time (480) / daily output (50)

Which of the following is an example of a product made with a project layout?

A house

If a company has an MRP program that can reflect the exact status of each item in real time, this program is called?

A net change MRP system

An MRP system is

A system-driven logic that allows a company to tie the production functions together from a material planning and control view

Which is the most challenging kind of supply chain to manage according to Hau Lee? A.)Agile supply chain B.)Efficient supply chain C.)Risk-hedging supply chain D.)Erratic supply chain E.)Responsive supply chain

A.) Agile supply chain

The inventory turnover ratio used in measuring supply-chain efficiency is found by the ratio of which of the following? A.) Cost of goods sold/Average aggregate inventory value B.) Fixed costs/Variable costs C.)Sales costs/Marketing costs D.)Cost of goods sold/Cost to sell goods E.)Operations flow costs/Suppliers flow costs

A.) Cost of goods sold/Average aggregate inventory value

Which of the following activities should not be outsourced? Multiple select question. Activities that have lots back-and-forth exchange of information Complex computer software Specialized research and development Immature technology Highly standardized and well understood processes

Activities that have lots back-and-forth exchange of information Complex computer software Specialized research and development Immature technology

From the highest level planning at the top to the lowest level planning at the bottom, rank the following. Aggregate planning Master production schedule Material requirements planning

Aggregate planning Master production schedule Material requirements planning

Which type of supply chain strategy is aimed at being responsive and flexible to customer needs and hedges against pooled inventory and other capacity resources? Responsive supply chains Efficient supply chains Risk-hedging supply chains Agile supply chains

Agile supply chains

Select all the transportation methods listed below that are considered fast Rail-car Container Ship Airplane Barge Pipeline

Airplane Pipeline

MRP would provide the highest benefit to assembly processes such as

Appliances, Motors, and Trucks

MRP systems seek to achieve which of the following? A. Minimize lot sizes B. Determine the number of dependent demand items needed C. Relieve capacity bottlenecks D. Provide a yardstick for future improvements E. Improve on JIT methods

B. Determine the number of dependent demand items needed

Which of the following is considered a secondary report in an MRP system? A. Planned order schedule B. Exceptions reports C. Inventory record D. Firm orders from known customers E. Engineering change reports

B. Exceptions reports

A bill-of-material also goes by the acronym ______.

BOM

Which of the following are some ideas for firms to implement green sourcing programs? Multiple select question. Creating recycling partnerships with suppliers Waste reduction programs that employees can help use Increasing the number of air conditioners in an improperly insulated building Reducing the use of electricity throughout facilities

Creating recycling partnerships with suppliers Waste reduction programs that employees can help use Reducing the use of electricity throughout facilities

develop the sourcing strategy

Cultivate quantitative and qualitative criteria to evaluate the sourcing process

Which of the following are sources of demand for products in a material requirements planning system?

Customer orders from sales personnel. Inter-department transactions.

One of the main purposes of a MRP system is which of the following? A. Track inventory levels B. Create productive capacity C. Decrease layers of management D. Develop schedules specifying when each component should be ordered or produced. E. Upgrade manufacturing's professionalism

D. Develop schedules specifying when each component should be ordered or produced.

Which of the following is a dynamic lot-sizing technique that adds ordering and inventory carrying cost for each trial lot size and divides by the number of units in each lot size, picking the lot size with the lowest unit cost? A. Economic order quantity B. Lot-for-lot C. Least total cost D. Least unit cost E. Inventory item averaging

D. Least unit cost

Last year a firm had an average inventory of $1,500,000 and the cost of goods sold was $3,750,000. What was the days-of-supply last year?

Days-of-Supply = Averageinventory/ Costofgoodssold ×365=$1,500,000/$3,750,000×365= 146

What is a legitimate reason for inventory?

Decoupling Risk

A(n) _____ _____ _____ system is a computer system that integrates application programs from the functional areas of a firm.

E R P

Grocery stores would traditionally use which type of supply chain?

Efficient supply chain

Which of the following is not considered a major work flow structure? - Work Center - Project - Fabrication - Assembly line - Continuous Flow

Fabrication

A firm's core competency should always be considered a candidate for outsourcing to improve performance.

False

An improvement-driven reason for outsourcing is that it can increase product and service value, customer satisfaction, and shareholder value

False

Capability Sourcing refers to outsourcing the functions that they do best to trusted key partners.

False

In a MTO manufacturing process, the product volumes are usually high and the customization is also high.

False

The Factor Rating Method is a calculation of where to place a distribution center given the distances and volumes between sources and destinations.

False

The total cost of ownership (TCO) is an estimate of the cost of an item that includes all the costs related to the procurement and use of an item, but does not include any of the costs related to disposing of the item after it is no longer useful.

False

True of False: Finished goods purchased by individuals external to the organization are considered dependent demand items.

False

True or false: A firm should consider its core competency as an activity that should be outsourced.

False

True or false: Finished goods purchased by individuals external to the organization are considered dependent demand items.

False

True or false: Sourcing activities remain the same regardless of what is being purchased.

False

Using a modular bill-of-materials will complex the scheduling and control and also makes it difficult to forecast the use of different modules.

False

The MRP program performs its analysis from the bottom up of the product structure trees, imploding requirements level by level.

False The MRP program performs its analysis from the top of the product structure downward, calculating requirements level by level.

What is NOT a lot sizing technique used in MRP systems?

Fixed time costs

What term is used to describe a practice where a customer makes a large purchase in response to a promotion or price cut?

Forward buying

A bill-of-materials that uses differences in alignment to indicate the order of assembly of components is using which type of structure? Uneven structure Duplicate structure Component structure Indented structure

Indented structure

What type of products have a life cycle of just a few months? Innovative Cyclical Functional Seasonal

Innovative

During which step of the green sourcing process does the actual procurement process begin?

Institutionalize the sourcing strategy

During which step of the green sourcing process does the actual procurement process begin? Implement sourcing strategy Engage sourcing agent Institutionalize the sourcing strategy Develop the sourcing strategy

Institutionalize the sourcing strategy

What are the sources of demand for products in a material requirements planning system?

Inter-department transactions, customer orders from sales personnel, and orders for specific components needed in repair

Which of the following are sources of demand for products in a material requirements planning system? Multiple select question. Inter-department transactions. Customer orders that have been canceled. Customer orders from sales personnel. The master production schedule.

Inter-department transactions. Customer orders from sales personnel.

An EOQ lot sizing technique will try to minimize the sum of which of the following costs given a fairly constant demand

Inventory holding and setup

Engage internal sourcing agents

Involving individuals and groups to help set realistic green goals

______________ are the part quantities issued in the planned order receipt and planned order release sections of an MRP schedule. Lot sizes Least total cost Demand numbers Economic order quantity

Lot sizes

Setting planned orders to match the net requirements exactly is what type of lot sizing technique? EOQ Least total costs Least unit costs Lot-for-lot

Lot-for-lot

Which of the following is true about MRP? Multiple select question. MRP is not used for dependent demand items. MRP is used to determine the number of parts, components, and other materials needed to produce a product. MRP is the highest level of planning in most organizations. MRP is an acronym for Material Requirements Planning.

MRP is used to determine the number of parts, components, and other materials needed to produce a product. MRP is an acronym for Material Requirements Planning.

Which of these acronyms are part of Ch 6 Manufacturing Processes (check all that apply) MTO ETO WIP RBI BEP

MTO ETO WIP BEP

The issue of balancing the level of finished inventory against the level of service to the customer occurs in which type of firm?

Make-to-stock

Which layout format groups machines to work on products that have similar processing requirements?

Manufacturing cell

The step in the planning process down from the master production schedule is called

Material Requirements Planning

Which are characteristics of a continuous process line? Multiple select question. May operate 24 hours a day. Product is moved from one workstation to the next workstation in a sequence of events. Highly automated machinery is used. Shutdowns can be expensive.

May operate 24 hours a day. Highly automated machinery is used. Shutdowns can be expensive.

An item that can be produced and stocked as a subassembly often uses a ______ bit-of-materials for planning

Modular

After finding gross requirements, the next step in the MRP explosion process references inventory on hand and scheduled orders to calculate _____ requirements

Net

A ___ requirement is the amount needed when the projected available balance plus the scheduled receipts in a period are not sufficient to cover the ____ requirements

Net, gross

_____________ techniques are typically used to manage production processes that follow a project layout structure. Multiple choice question. Bulk inventory Project management Made-to-stock Lean manufacturing

Project management

What is an example of a Set Up Cost?

Reconfig Machines Driving to the farm every time you want some eggs

Which type of supplier relationship should be used when there is a standardized interface between adjacent tasks?

Required coordinated

Which of the following is a sourcing term to describe how common an item is and/or how many substitutes may be available? Bullwhip effect Specificity Uniqueness Outsourcing

Specificity

Which type of supply process has a mature manufacturing and technology base? Functional Innovative Evolving Stable

Stable

The file containing the complete product description, parts listing, quantity needed and product build sequence is called? The peg record The bill-of-material The inventory log The MPS

The bill-of-material

The next level in the planning process down from an aggregate plan is called?

The master production schedule

The next level in the planning process down from an aggregate plan is called? Supply coordination Materials requirements planning Demand forecasting The master production schedule

The master production schedule

According to Little's Law, which of the following can be used to estimate work-in-process inventory? - Process velocity/Flow time - Value added time/Process velocity - Process time/Cycle time - Throughput rate times Flow time - Set up time/Throughput rate

Throughput rate times Flow time

______ _______ are a company's attempt to provide a controlled window of opportunity to make changes to the master production schedule

Time fences

are a company's attempt to provide a controlled window of opportunity to make changes to the master production schedule.

Time fences

inventory measures

Total average value of inventory Inventory turns Days of supply

True or False: A least total cost lot sizing technique is a dynamic approach that continually looks for an optimal lot size where carrying costs and ordering costs are close to equal

True

True or false: A least total cost lot sizing technique is a dynamic approach that continually looks for an optimal lot size where carrying costs and ordering costs are close to equal.

True

True or false: Innovative products have higher profit margins than functional products.

True

True or false: The average aggregate inventory value is valued at cost.

True

True or false: Weeks of supply is the preferred measure of supply chain efficiency when distribution inventory is dominant.

True

Which of the following is not a reason why a firm may choose to outsource an activity?

Turn variable costs into fixed costs

Which of the following is not a type of time fence described in the text? Variable Frozen Slushy Liquid

Variable

When purchasing items that are highly specified and a long contract is desirable, which sourcing process should be used?

Vendor managed inventory

When purchasing items that are highly specified and a long contract is desirable, which sourcing process should be used? Electronic catalog Reverse auction Spot purchase Vendor managed inventory

Vendor managed inventory

engineer to order

Work with the customer to design and then make the product

manufacturing process flow design

a method to evaluate the specific processes that material follow as they move through the plant -focus should be on the identification of activities that can be minimized or eliminated

Least unit cost provides _________ as an advantage when taking variable ordering costs and setup costs into account. a shorter computation a simple return on investment a quick reference a more complete analysis

a more complete analysis

Outside of determining parts, components, and materials, MRP provides independent demand for products being produced. a schedule for when each of these should be produced or ordered. a forecast for the next 6 months. the total plan for all capital investments needed.

a schedule for when each of these should be produced or ordered.

breakeven analysis

a standard approach to choosing among alternative processes or equipment-seeks to determine the point in units produced where a company will start making a profit on the process =FC/($/unit-VC/unit)

Problem 6-17 Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These are to be combined into workstations to create an assembly line. The assembly line operates 13 hours per day. The output requirement is 1,800 units per day. (TASK) (b/4) (TIME) A — 20 G C 13 B A 7 H D 8 C A 14 I E 7 D B 16 J F, G 9 E B 15 K H, I 6 F C 14 L J, K 4 a. What is the workstation cycle time? b. balance the line using the longest task time based on the 1,800-unit forecast, stating which tasks would be done in each workstation. c. What is the efficiency of your line balance? (Round your answer to 1 decimal place.) d. After production was started, Marketing realized that they understated demand and must increase output to 1,900 units. There are two options: reduce cycle time or work overtime. Please identify the following:

a. 26 seconds per unit b. c. 85.3 d. reduce cycle time to 25 (13 x 3600)/1900 = 25 overtime 43 minutes ((1900-1800) x 26 sec) = 2600 sec / 60 sec = 43 minutes

Workcenters with large amounts of interdepartmental traffic are often placed Multiple choice question. adjacent to each other. in areas where few machines are located. far away from each other. near exits.

adjacent to each other.

MRP systems tend to work best in companies where products are made in _____ using the same productive equipment.

batches

MRP systems tend to work best in companies where products are made in_____________, using the same productive equipment.

batches

Which of the following terms describes the phenomenon of variability magnification as one moves upstream in the supply chain from customer to producer

bullwhip effect

manufacturing cell

dedicated area where a group of similar products are produced

assembly chart

defines how parts fit together, their order of assembly, and overall flow pattern ex: putting IKEA furniture together diagram + step by step instruction

process flowchart

denotes what happens to the product as it progresses through the production facility -helps determine cost of making the product

A manufacturing cell is generally made up of ___________ machines. Multiple choice question. similar identical dissimilar

dissimilar

Inventory turn is calculated by

dividing cost of goods sold by average inventory value.

Grocery stores would traditionally use which type of supply chain?

efficient supply chain

Level 0 items during the explosion process are typically referred to as _____ items, or gross requirements.

end

The master production schedule is used to plan raw materials. end items. supply parts. rework.

end items.

When the manufacturing process and underlying technology are still under development and rapidly changing, it is known as a(n) ___________ supply process.

evolving

When the manufacturing process and underlying technology are still under development and rapidly changing, it is known as a(n) ___________ supply process. innovative functional stable evolving

evolving

True or false: Sourcing activities remain the same regardless of what is being purchased.

false

The _____ _____ _____ method is a dynamic approach that adds ordering and inventory carrying costs for each trial lot size, divides the costs by the number of units, and chooses the lot size with the lowest unit cost.

least unit cost

One of the limitations with least total coast (LTC) is the influence by the size of the manufacturing site. length of the planning horizon. number of parts ordered. selection of suppliers.

length of the planning horizon.

What term refers to the management functions that support the complete cycle of material flow?

logistics

throughput rate

long term average rate of flow through process

are the part quantities issued in the planned order receipt and planned order release sections of an MRP schedule. Economic order quantity

lot sizes

A generic pizza box that can be used by multiple pizza shops is an example of a product with ____________ specificity

low

A generic pizza box that can be used by multiple pizza shops is an example of a product with ____________ specificity.

low

A generic pizza box that can be used by multiple pizza shops is an example of a product with ____________ specificity. generic low high medium

low

spot purchases have _ specificity and _ transaction costs

low and low

Spot purchases have ________ specificity and ________ transaction costs.

low; low

make to order

make a customer's order from raw material

When a company groups dissimilar machines to work on products that have similar processing requirements, it's using a(n) ___________ layout

manufacturing cell

inventory

material held by arm for future use

An item that can be produced and stocked as a subassembly often uses a _____ bill-of-materials for planning.

modular

If inventory turn is known, days-of-supply is calculated by

multiplying the inverse of inventory turn by 365 days.

In an assemble-to-order system, the total number of unique combinations possible is calculated by

multiplying the number of options for each choice together.

how production processes are organized

project workcenter (job shop) manufacturing cell assembly line continuous process

Some benefits of an ERP system are Multiple select question. quality management can develop inspection points for products during manufacturing. manufacturing knows about orders as soon as they are entered. human resources knows how many employees to schedule. sales can track all the details of an order.

quality management can develop inspection points for products during manufacturing. manufacturing knows about orders as soon as they are entered. sales can track all the details of an order.

A solicitation for a detailed proposal from a vendor is called a _______________ for _______________.

request proposal

A solicitation for a detailed proposal from a vendor is called a ________for _________

request proposal

A solicitation for a detailed proposal from a vendor is called a ___________ for ___________

request for proposal

Little's Law provides a convenient way to calculate WIP inventory with this equation: Inventory = Throughput time x Flow time. What is Flow Time? WIP Inventoy average rate that items come out of the process time for a single unit to go end-to-end Cycle time

time for a single unit to go end-to-end

flow time

time for one unit to get through a process

An estimate of all expenses incurred while procuring and using an item is the _______________ cost of ownership.

total

An estimate of all costs related to the procurement and use of an item is the

total cost of ownership

A production process map is built by

tracking the flow of material through the system.

Coke's bottling facility which mixed drink ingredients, adds water, and fills up cans and bottles with the drink should be located closer to markets t/f

true

True or false: Innovative products have higher profit margins than functional products.

true

Which of the following is NOT true about a workcenter layout? Multiple choice question. A workcenter layout can produce a wide variety of products. A workcenter layout is commonly used for systems with high production volumes. A workcenter layout is also called a job shop. In a workcenter layout, machines with similar functions are grouped together.

A workcenter layout is commonly used for systems with high production volumes.

Which common layout format refers to the progressive build of a product? Multiple choice question. Assembly line Workcenter Manufacturing cell Project layout

Assembly line

Which of the following terms describes the phenomenon of variability magnification as one moves upstream in the supply chain from customer to producer? Continuous replenishment Normal demand Outsourcing Bullwhip effect

Bullwhip effect

inventory turn

COGS / avg. inventory value

Which of the following is one of the strategic characteristics to consider when deciding how supplier relationships should be structured on the continuum between vertical integration (do not outsource) to arm's length relationships (outsource)? A.) Cost B.) Location C.) Investment D.) Coordination E.) Control

D.) Coordination

The time needed to respond to a customer's order is called the customer response time.

F

MRP stands for Manufacturing Requirements Planning.

False Material Requirements Planning (MRP)

Which of the following is not an organizationally driven reason to outsource? Increase product and service value Generate access to new markets Improve effectiveness Increase flexibility

Generate access to new markets

What is part of an MRP record?

Gross Requirements, Net Requirements, & Planned Order Receipts

A bill-of-materials that uses differences in alignment to indicate the order of assembly of components is using which type of structure?

Indented Structure

The ______ ____ ____ lot sizing technique is a dynamic approach that adds ordering and inventory carrying costs for each trial lot size, divides the costs by the number of units, and chooses the lot size with the lowest unit cost

Least unit cost

Which sourcing process is used for complex items where there are a number of potential vendors? Electronic catalog Request for proposal Spot purchase Strategic alliance

Request for proposal

Which of the following is/are issues a master scheduler must consider? Multiple select question. Trade-off manufacturing, engineering and marketing conflicts. Be involved with customer order promising. The firms financing plans. Never lose sight of the aggregate plan. Adjust the raw material supply schedule as needed.

Trade-off manufacturing, engineering and marketing conflicts. Be involved with customer order promising. Never lose sight of the aggregate plan.

MRP require a very accurate BOM to successfully plan material requirements.

True

lean manufacturing

a means of achieving high levels of customer service with minimal inventory investment

Which type of supply chain strategy is aimed at being responsive and flexible to customer needs and hedges against pooled inventory and other capacity resources?

agile supply chains

assembly drawing

an exploded view of the product showing its component parts

which describes the phenomenon of variability magnification as one moves from customer to producer? -continuous replenishment -outsourcing -bullwhip effect -normal demand

bullwhip effect

The point in the supply chain where inventory is positioned to allow the preceding processes to operate independently is the

customer order decoupling point.

A material requirements planning system interfaces with the master production schedule, bill-of-materials file and __________. product demand. inventory records file. forecasted sales. customer purchase order.

inventory records file.

The ratio of cost of good sold to average inventory value is known as

inventory turnover

A process that places all identical parts at the same level in the bills-of-materials simplifies computations. This process is known as

low level coding

After finding gross requirements, the next step in the MRP explosion process references inventory on hand and scheduled orders to calculate _____ requirements.

net

The ultimate goal of any MRP lot sizing approach is to balance the setup or _____ costs and the _____ costs associated with meeting the net requirements generated by the MRP planning process.

order holding

The bill-of-material (BOM) file is also known as a Multiple select question. product structure file. product recipe. assembly instruction. product tree.

product structure file. product tree.

A framework depicting when the different production process types are typically used depending on volume and standardization is known as the

product-process matrix.

Standardization on the product-process matrix refers to Multiple choice question. variations in the product. raw materials shared between processes. the amount of product being produced. the volume the process is designed to produce.

variations in the product.

When the supplier takes full responsibility to manage items for the customer, the supplier is performing

vendor managed inventory.

customer order decoupling point

where inventory is positioned to allow entities in the supply chain to operate independently

Every 2 minutes a bus departs from AVIS. Flow time is 20 minutes. How many buses are in the system at a time?

(1 bus / 2 minutes) x 20 minutes = 10 buses

You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. Which of the following is the correct value for the resulting line's efficiency? - 0.833 - None of these - 0.973 - 0.500 - 0.990

0.833 Using equation 6.5, [25 / (6 x 5)] = 0.833.

The total cost of ownership includes: 1. Procurement costs 2. Disposal costs 3. Engineering design costs

1 and 2

Which types of inventory are included in the average aggregate inventory value? 1. Raw material 2. Work-in-process 3. Finished goods 4. Distribution 1, 2, 3, and 4 1, 2, and 3 Only 3 and 4 Only raw materials

1, 2, 3, and 4

Which of the following is the net requirement using an MRP program if the gross requirement is 1,250 and the inventory on hand is 50? 1,200 1,300 1,150 2,450 None of the above

1,250 - 50 = 1,200. Net requirements are the amounts that are needed week by week in the future over and above what is currently on hand or committed to through an order already released and scheduled.

List the highest level planning to the lowest level of planning:

1. Aggregate Planning 2. Master Production Schedule 3. Material Requirements Planning

Green Sourcing steps

1. Assess the opportunity 2. Engage sourcing agents 3. Assess the supply base 4. Develop the sourcing strategy 5. Implement sourcing strategy 6. Institutionalizing the sourcing strategy

Which of the following is the planned-order release using an MRP program if the gross requirement is 670 and the inventory on hand is 600? 670 600 530 70 None of the above

670 600 530 correct 70 None of the above Using net requirements, the program calculates when orders should be received to meet these requirements. This can be a simple process of just scheduling orders to arrive according to the exact net requirements or a more complicated process where requirements are combined for multiple periods. This schedule of when orders should arrive is referred to as "planned-order receipts." Since there is typically a lead time associated with each order, the next step is to find a schedule for when orders are actually released. Offsetting the "planned-order receipts" by the required lead time does this. This schedule is referred to as the "planned-order release." 670 - 600 = 70.

If a company has an MRP program that can reflect the exact status of each item in real time, this program is called? A peg record An inventory transaction file A net change MRP system A bill-of-material system

A net change MRP system

Which of the following statements best characterizes an MRP system? A system-driven logic that allows a company to tie the production functions together from a material planning and control view. An independent demand system that helps a company to prioritize customer orders based on profit potential. A system that specifies the best transportation mode for inbound materials. A system-driven approach to determine which suppliers are likely meet delivery due dates.

A system-driven logic that allows a company to tie the production functions together from a material planning and control view.

Which of the following is an input file necessary to run an MRP system? A. Bill of materials (BOM) file B. Quality management report C. Exception reports D. Planned-order schedules E. Purchasing contracts

A. Bill of materials (BOM) file

Which of the following industry types will not benefit greatly from the application of MRP? A. Fabricate-to-order B. Assemble-to-stock C. Assemble-to-order D. Manufacture-to-order E. None of the above

A. Fabricate-to-order

A product tree can do which of the following? A. Help to compute component usage B. Reduce product scrap C. Reduce labor overtime D. Reduce regular time labor E. Locate raw material supplies

A. Help to compute component usage

Which of the following is considered a primary report in an MRP system? A. Planned order schedule B. Peg report C. Planning report D. Inventory accuracy report E. Aggregate production plan report

A. Planned order schedule

A BOM file is also called which of the following? A. Product tree B. Stocking plan C. Inventory usage record D. Production parts plan E. Time bucket schedule

A. Product tree

Which of the following is most closely related to the reason a firm might implement MRP? A. So they can order the right parts B. So they can order parts sufficient for immediate use C. So they can insure that parts to arrive prior to when they are needed D. To assure appropriate quality levels E. To keep process costs between the LCL and the UCL

A. So they can order the right parts

Which is not true about a Bill of Material (BOM) There is more than one way to create a BOM The BOM has multiple levels Item is coded at the lowest level at which it occurs All of the above are true statements

All of the above are true statements

Which layout moves product from workstation to workstation at a controlled rate? Multiple choice question. Continuous process Assembly line U-shaped layout Retail layout

Assembly line

Which of the following basic types of process structures is one which equipment or work processes are arranged according to the progressive steps by which the product is made? - Manufacturing cell - Assembly line - Project - Workcenter - Continuous process

Assembly line

Which the following describes the layout for items produced through a fixed sequence of workstations? Multiple choice question. Project Workcenter Assembly line Manufacturing cell

Assembly line

What is the first step in the process for green sourcing? Engage sourcing agents Assess the opportunity Assess the supply base Develop the sourcing strategy

Assess the opportunity

If a company has more units in the master production schedule than firm customer orders, the residual is called? Liquid inventory Available to promise Ready to ship Customer overstock

Available to promise

If a company has more units in the master production schedule than the firm customer orders then it is called

Available to promise

Days-of-Supply

Average Inventory/Cost of goods sold x 365

Under the lot-for-lot (L4L) lot sizing technique as used in MRP, we would expect which of the following? A. A consistent lag of supply behind demand B. Minimized carrying costs C. Minimized set-up costs D. A just in time management philosophy E. Minimized quality problems

B. Minimized carrying costs

Which of the following is an input to the master production schedule (MPS)? A. Inventory records file B. The aggregate plan C. The bill of materials D. The exception report E. Planned order schedules

B. The aggregate plan

In an MRP program, the program accesses the status segment of an inventory record according to specific periods called which of the following? A. Cubed time units B. Time buckets C. BOM units D. Time modules E. Time lines

B. Time buckets

Which of the following is one of the main purposes of a MRP system? A. Educate personnel in basic work rules B. To determine the amount of materials needed to produce each end item. C. Stimulate the work force D. Decrease labor requirements E. Increase inventory accuracy

B. To determine the amount of materials needed to produce each end item.

Which of the following is/are issues a master scheduler must consider?

Be involved with customer order promising. Trade-off manufacturing, engineering and marketing conflicts. Never lose sight of the aggregate plan.

Which of the following is an input to the master production schedule? Bill of materials (BOM) file Inventory records file Exception reports Planned-order schedules None of the above

Bill of materials (BOM) file Inventory records file Exception reports Planned-order schedules correct None of the above

work station cycle time formula

C = total production time/ total units needed per day

Which of the following industry types have high expected benefits from the application of MRP? A. Fabricate-to-order B. Hospitals C. Assemble-to-order D. Aircraft manufacturers E. Oil refineries

C. Assemble-to-order

Which of the following industry types have high expected benefits from the application of MRP? A. Fabricate-to-stock B. Fabricate-to-order C. Assemble-to-stock D. Continuous process E. Service and repair parts

C. Assemble-to-stock

Which of the following is an input file necessary to run an MRP system? A. Exception report B. Computer-aided-design files C. Inventory records file D. Personnel files E. Planned order schedule

C. Inventory records file

Which of the following is a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup (or ordering) costs for various lot sizes and then selects the lot in which these are most nearly equal? A. Economic Order Quantity B. Lot for lot C. Least total cost D. Least unit cost E. ABC analysis

C. Least total cost

Which of the following can be used for lot sizing in an MRP system? A. Low-level coding B. Time bucket size C. Least unit cost D. Inventory record file E. Peg inventory

C. Least unit cost

We would expect to see which of the following in an MRP system's inventory status file? A. End items produced B. Late/early delivery records C. Scrap parts D. Labor efficiency E. Computer errors

C. Scrap parts

When considering outsourcing, what should firms be sure to avoid? A.)Losing control of non-core activities which don't distinguish the firm B.) Allowing outsourcing to develop into a substitute for innovation C.) Giving the outsourcing partner opportunities to become a strong competitor D.) Allowing employees transferred to the outsourcing partner to rejoin the firm E.) Adverse corporate tax implications of asset transfers to the outsourcing partner

C.) Giving the outsourcing partner opportunities to become a strong competitor

Which of the following is not a major characteristic to be considered when structuring an outsourcing relationship?

Collaboration

assemble to order

Combine a number of preassembled modules to meet a customer's specifications

Which process layout is best used for manufacturing liquids?

Continuous

What type of activities are key to the business but do not confer a competitive advantage? Core Integral Strategic Outsourced

Core

Which of the following resources would a firm not outsource?

Core competencies

Which of the following resources would a firm not outsource? Human resources department IT department Manufacturing facility to produce a component Core competencies

Core competencies

What term describes the annual cost for a company to produce the good or services provided to customers? Weeks of supply Cost of goods sold Cost of production Average aggregate inventory value

Cost of goods sold

The location for a manufacturing operation is often ____ focused, while the location for services operations is often ___ focused.

Cost, Revenue/Profit/Customer

Which of the following is considered a primary report in an MRP system? A. Planning reports B. Performance reports C. Exception reports D. Planned order schedules E. Cycle counting reports

D. Planned order schedules

Which of the following is NOT a step in the process of developing a manufacturing cell? Multiple choice question. Determine which machines perform the same process. Physically regroup machines into cells. Group parts into families that follow a common sequence of steps. Identify dominant flow patterns for each f

Determine which machines perform the same process.

One of the main purposes of a MRP system is which of the following? Track inventory levels Create productive capacity Decrease layers of management Develop schedules specifying when each component should be ordered or produced. Upgrade manufacturing's professionalism

Develop schedules specifying when each component should be ordered or produced. MRP is a logical, easily understandable approach to the problem of determining the number of parts, components, and materials needed to produce each end item. MRP also provides the schedule specifying when each of these items should be ordered or produced.

Which of the following is not a production activity report generated by MRP? A. Exception report B. Planning report C. Performance control report D. Planned-order schedules E. Bill of materials report

E. Bill of materials report

Which of the following is an input to the master production schedule? A. Prototype products from product development B. Aggregate component schedule C. Peg reports D. Exception reports E. Forecasts of random demand from customers

E. Forecasts of random demand from customers

Which of the following is a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup (or ordering) costs for various lot sizes and then selects the lot size in which these are most nearly equal? A. Kanban B. Just-in-time system C. MRP D. Least unit cost E. Least total cost

E. Least total cost

In a typical inventory status record which of the following would you not expect to see? A. Scrap allowance B. Order quantity C. Gross requirements D. Planned-order releases E. Lost items

E. Lost items

Which of the following files allows us to retrace a material requirement upward in the product structure through each level, identifying each parent item that created the demand? A. Planning bill of materials file B. Modular bill of materials file C. Super bill of materials file D. Exception report file E. Peg record file

E. Peg record file

Which of the following is not a lot sizing technique used in MRP systems? A. Lot-for-lot (L4L) B. Economic order quantity (EOQ) C. Least total cost (LTC) D. Least unit cost (LUC) E. Warehouse loading factor (WLF)

E. Warehouse loading factor (WLF)

Which is the correct equation used to calculate economic order quantity (EOQ)? EOQ= √(2HS/D) EOQ= √(2DS/H) EOQ= √(2DH/S) EOQ= √(DS/H)

EOQ= √(2DS/H)

Grocery stores would traditionally use which type of supply chain? Responsive supply chain Agile supply chain Efficient supply chain Risk-hedging supply chain

Efficient supply chain

The placement of which of the following is not determined by production process organization decisions? - Emergency exits - Machines - Workstations - Departments - `Workgroups

Emergency exits

The master production schedule is used to plan

End Items

Match the green-sourcing step with the correct action associated. Engage internal sourcing agents Assess the supply base Develop the sourcing strategy Implement sourcing strategy Cultivate quantitative and qualitative criteria to evaluate the sourcing process Engaging new and existing vendors Select vendors and products for each business requirement Involving individuals and groups to help set realistic green goals

Engage internal sourcing agents: Involving individuals and groups to help set realistic green goals Assess the supply base: Engaging new and existing vendors Develop the sourcing strategy: Cultivate quantitative and qualitative criteria to evaluate the sourcing process Implement sourcing strategy: Select vendors and products for each business requirement

assess the supply base

Engaging new and existing vendors

In which of the following industry types would MRP provide high benefits? Multiple select question. Engineer-to-order Make-to-order Assemble-to-stock Assemble-to-order

Engineer-to-order Assemble-to-stock Assemble-to-order

An _______ ______ ______ system is a computer system that integrate application programs from the functional areas of a firm

Enterprise resource planning

A continuous process indicates production of discrete parts moving from workstation to workstation at a controlled rate.

F

A make-to-order firm will work with the customer to design the product and then make it from purchased materials, parts, and components.

F

A project layout is characterized by a relatively low number of production units in comparison with process and product layout formats.

F

Break-even analysis can only be used in production equipment decision making when dealing solely with fixed costs, not variable costs.

F

Process selection refers to the strategic decision of choosing the volume of output to produce in a manufacturing facility depending upon the way that facility produces.

F

The closer the customer is to the customer order decoupling point, the longer it takes the customer to receive the product.

F

The essential issue in satisfying customers in the make-to-stock environment is to balance the cost of the finished item against the willingness of the consumer to pay for it.

F

Firms producing functional products are forced to introduce a steady stream of innovations in order to survive.

FALSE

Which of the following is not a lot sizing technique used in MRP systems? Fixed time costs Economic order quantity Lot-for-lot Least total costs

Fixed time costs

Time fences are described as

Frozen, Slushy, or Liquid

Which of the following is/are a part of an MRP record? Multiple select question. Scheduled repairs Raw material receipts Gross requirements Net requirements Planned order receipts

Gross requirements Net requirements Planned order receipts

A major drawback with lot-for-lot sizing is? Low investment costs High capital investments High setup costs Low setup costs

High setup costs

Little's law relates inventory, throughput rate, and flow time as

INVENTORY: throughout rate x flow time

Which of the following activities should not be outsourced?

Immature technology Complex computer software Specialized research and development Activities that have lots back-and-forth exchange of information

Which of the following is an organizationally-driven reason for outsourcing? A.) Improve effectiveness by focusing on what the firm does best B.) Turn fixed costs into variable costs C.) Reduce costs through lowered cost structure and increased flexibility D.) Improve risk management Improve credibility and image by associating with superior providers E.) Improve effectiveness by focusing on what the firm does best

Improve effectiveness by focusing on what the firm does best

Identify the true statements about assembly-line and continuous process layouts. Multiple select question. In a continuous process, a product moves continuously through the process. In an assembly line, the stations are completely independent of each other. Often, the item being produced in a continuous process is a liquid or chemical that actually flows through the system. In an assembly line, a product goes through a progressive set of steps

In a continuous process, a product moves continuously through the process. Often, the item being produced in a continuous process is a liquid or chemical that actually flows through the system. In an assembly line, a product goes through a progressive set of steps.

Which is true in regards to a request for proposal and a reverse auction?

In a reverse auction, the buyer establishes a request, sellers then place bids for the amount they are willing to accept.

Which is true in regards to a request for proposal and a reverse auction? Both allow the seller to have the majority of control in deciding on the price of goods or services. A reverse auction allows the buyer to inform the seller the price they are willing to pay for services. Both allow the buyer to have the majority of control in deciding on the price of goods or services. In a reverse auction, the buyer establishes a request, sellers then place bids for the amount they are willing to accept.

In a reverse auction, the buyer establishes a request, sellers then place bids for the amount they are willing to accept.

A material requirements planning system interfaces with the master production schedule, bill-of-materials file and ________ _______ ____

Inventory records file

When changes occur because of stock receipts and disbursements, scrap losses, wrong parts and canceled orders, the real-time file capturing these changes is called the:

Inventory transactions file

Last year a firm had an average inventory of $1,500,000 and the cost of goods sold was $3,750,000. What was the inventory turn last year?

Inventory turn = CostofgoodssoldAverageinventory=$3,750,000/$1,500,000=2.5

The inventory records file contains an _____ ______ data segment that contains a detailed description of the item, lead time information, safety stock levels and other records

Item master

If an end item is ________ or _________, the master production schedule may include major sub-assemblies and/or complex components

Large or Expensive

the part quantities issued in the planned order receipt and planned order release sections of an MRP schedule.

Least total cost

What term refers to the management functions that support the complete cycle of material flow? Logistics Supply chain Purchasing Transportation

Logistics

Which of the following is not a broad cost category in total cost of ownership? Logistics Ownership Post-ownership Acquisition

Logistics

MRP systems seek to achieve which of the following? Minimize lot sizes Determine the number of dependent demand items needed Relieve capacity bottlenecks Provide a yardstick for future improvements Improve on JIT methods

Minimize lot sizes correct Determine the number of dependent demand items needed Relieve capacity bottlenecks Provide a yardstick for future improvements Improve on JIT methods MRP is a logical, easily understandable approach to the problem of determining the number of parts, components, and materials needed to produce each end item. MRP also provides the schedule specifying when each of these items should be ordered or produced. MRP is based on dependent demand. Dependent demand is caused by the demand for a higher-level item.

number of work stations needed formula

Nt = sum of task time (t) / cycle time

When safety stock is needed, what is reduced by the safety stock? Projected available balance Forecast for last period On-hand balance Demand from sales

On-hand balance

The total cost of ownership includes: 1. Procurement costs 2. Disposal costs 3. Engineering design costs Only 1 and 2 Only 2 and 3 Only 1 and 3 1, 2, and 3

Only 1 and 2

Which of the following is considered in green sourcing? 1. Using recyclable materials 2. Waste reduction 3. Increase usage Only 1 and 3 1, 2, and 3 Only 1 and 2 Only 2 and 3

Only 1 and 2

Which costs are not part of the Total Cost of Ownership framework? Taxes Opportunity Costs Energy Costs Finance Costs Disposal Costs

Opportunity Costs

Lot sizes are the part quantities issued in the planned order receipt and planned _____ _______ sections of an MRP schedule

Order Release

What term describes moving some of a firm's activities and decisions to outside providers? Production In-sourcing Benchmarking Outsourcing

Outsourcing

Which cost of ownership includes maintenance and ergonomic factors? Post-ownership Ownership These are not part of TCO Acquisition

Ownership

The file created by retracing a material requirement upward in the product structure to identify each parent item that created the demand is called a _____ record

Peg

Which of the following is an innovative product? Personal computer Pens Cereal Diapers

Personal computer

Which of the following files allows us to retrace a material requirement upward in the product structure through each level, identifying each parent item that created the demand? Planning bill of materials file Modular bill of materials file Super bill of materials file Exception report file Peg record file

Planning bill of materials file Modular bill of materials file Super bill of materials file Exception report file correct Peg record file The MRP program allows the creation of a peg record file either separately or as part of the inventory record file. Pegging requirements allows us to retrace a material requirement upward in the product structure through each level, identifying each parent item that created the demand.

Projected balance, the amount of inventory expected at the end of a period, is calculated using which equation? Projected available balance = sum of on-hand inventory + gross requirements - scheduled receipts + planned orders Projected available balance = sum of on-hand inventory + gross requirements - scheduled receipts - planned orders Projected available balance = sum of on-hand inventory + gross requirements + scheduled receipts - planned orders Projected available balance = sum of on-hand inventory - gross requirements + scheduled receipts + planned orders

Projected available balance = sum of on-hand inventory - gross requirements + scheduled receipts + planned orders

The Bullwhip Effect can be prevented if companies all along the value stream: Always buy in bulk at reduced prices Replenish stock with smaller volumes more frequently Coordinate and communicate orders and demand forecasts Avoid placing orders

Replenish stock with smaller volumes more frequently. Coordinate and communicate orders and demand forecasts.

Which type of supplier relationship should be used when there is a standardized interface between adjacent tasks? Required coordinated Intellectual property Vertical integration Strategic control

Required coordinated

A product with high demand uncertainty and low supply uncertainty would utilize which type of supply chain? Agile Efficient Responsive Risk-hedging

Responsive

The first step in the MRP explosion process is? Retrieve the gross requirements for end items from the master schedule. Place part orders for net requirements. Calculate the lead times for all products that have been schedule on the master schedule. Identify the inventory on hand for all parts.

Retrieve the gross requirements for end items from the master schedule.

In a typical inventory status record which of the following would you not expect to see? Scrap allowance Order quantity Gross requirements Planned-order releases Lost items

Scrap allowance Order quantity Gross requirements Planned-order releases correct Lost items The inventory status file is kept up to date by posting inventory transactions as they occur. These changes occur because of stock receipts and disbursements, scrap losses, wrong parts, canceled orders, and so forth.

Implementing sourcing strategy

Select vendors and products for each business requirement

make to stock

Serve customers "on demand" from finished goods inventory

An EOQ lot sizing technique will try to balance the sum of which of the following costs given a fairly constant demand? Multiple select question. Marketing Transportation Setup Holding costs

Setup Holding costs

Logistics involves which of the following management functions? Multiple select question. Shipping of final goods Purchase of production materials Planning of employee work hours Distribution of finished product Planning of work-in-process

Shipping of final goods Purchase of production materials Distribution of finished product Planning of work-in-process

Logistics involves which of the following management functions?

Shipping of final goods Purchase of production materials Planning of work-in-process Distribution of finished product

Which of the following is not a common constraint regarding vendor managed inventory?

Shipping terms

Which of the following is not a common constraint regarding vendor managed inventory? Required service level Maximum inventory level Billing transaction process Shipping terms

Shipping terms

Shorter cycle time and better risk management are ___________ reasons to outsource

Shorter cycle time and better risk management

Which type of time fence allows for changes to a specific product so long as parts are available?

Slushy

Which type of time fence allows for changes to a specific product so long as parts are available? Slushy Frozen Scheduled Liquid

Slushy

Which of the following activities should not be outsourced?

Specialized research and development Immature technology Complex computer software Activities that have lots back-and-forth exchange of information

Which of the following is a sourcing term to describe how common an item is and/or how many substitutes may be available?

Specificity

When balancing an assembly line, which of the following is not a way to reduce the longest task time below the required workstation cycle time? - Split the task between two workstations - Use a more skilled worker - Speed up the assembly line transfer mechanism - Upgrade the equipment - Assign a roaming helper to support the line

Speed up the assembly line transfer mechanism

Which type of activities are a key source of competitive advantage?

Strategic

Which type of activities are a key source of competitive advantage? Outsourced Noncritical Internal Strategic

Strategic

What term describes the development and management of supplier relationships?

Strategic sourcing

What term describes the development and management of supplier relationships? Bullwhip effect Strategic sourcing Spot purchasing Vendor managed inventory

Strategic sourcing

Total average value of inventory

Sum of raw material, work-in-process, and finished goods inventory

A company producing widgets only needs Part A for 40% of the widgets built. This company is likely using what type of bill-of material?

Super

A company producing widgets only needs Part A for 40% of the widgets built. This company is likely using what type of bill-of-material? Partial bill-of-material Modular bill-of-material Deluxe bill-of-material Super bill-of-material

Super bill-of-material

What is NOT a part of the material requirements planning system?

Supplier Delivery Schedule

Which of the following is NOT a part of the material requirements planning system? Master production schedule Supplier delivery schedule Bill-of-materials Inventory records

Supplier delivery schedule

A general-purpose machine is less capable than a special-purpose machine in certain tasks but can perform a broader variety of tasks.

T

A high-level map or diagram of a supply chain process can be useful to understand how material flows and where inventory is held.

T

A project layout is characterized by a high degree of task ordering.

T

An example of an assemble-to-order firm is Dell Computer.

T

Assemble-to-order means moving the customer order decoupling point from finished goods to components.

T

Break-even analysis can be used to help decide whether to perform a task with a special-purpose machine or with a general-purpose machine.

T

Engineer-to-order firms will work with the customer to design the product and then make it from purchased materials, parts, and components.

T

One difference between an assembly line process flow and a continuous process flow is that on the assembly line the flow is discrete rather than continuous.

T

One methodology used to evaluate equipment investment decisions where the investment entails an initial investment, fixed costs, and variable costs is break-even analysis.

T

One trade-off illustrated by the product-process matrix is between flexibility and cost.

T

Process selection refers to the strategic decision of selecting which kind of production processes to use to produce a product or provide a service.

T

The closer the customer is to the customer order decoupling point, the more quickly the customer receives the product.

T

The essential issue in satisfying customers in the make-to-stock environment is to balance the level of finished inventory against the level of service to the customer.

T

The focus in the make-to-stock environment is on providing finished goods where and when the customers want them.

T

The product-process matrix shows the relationship between process structures and product volume and variety characteristics.

T

The term "assembly line" refers to progressive assembly linked by some material handling device.

T

The volume requirements for the product are one determinant of the choice of which process structure to select.

T

The total cost of ownership (TCO) can be categorized into three areas: acquisition costs, ownership costs, and post-ownership costs.

TRUE

A BOM file is often called a product structure file or product tree because it shows how a product is put together.

True

A process that places all identical parts at the same level in the bills-of-materials simplifies computations. This process is known as low level coding.

True

Inventory turn values that are considered good differ by industry and the type of products being handled

True

Logistics is a term that refers to the management functions that support the complete cycle of material flow, from the purchase and internal control of production materials; to the planning and control of work-in-process; to the purchasing, shipping, and distribution of the finished product.

True

The Master Production Schedule (MPS) is a disaggregation of the aggregate plan that looks ahead a set number of weeks and is often fixed or "frozen" in the short term.

True

Which two product characteristics help determine the appropriate manufacturing process Volume demanded (high or low) Specifications (detailed or simple) Customization (unique or standard) Value of Finished Goods

Volume demanded (high or low) Customization (unique or standard)

Which of the following is a basic type of process structure? - Process matrix - Manual assembly - Process flow diagram - Product matrix - Workcenter

Workcenter

Are the inventory turnover and weeks of supply measures related to one another? Yes, they can be added together for a true result. Yes, one is a multiple of the other. No, they are not related. Yes, they are mathematically inverses.

Yes, they are mathematically inverses.

manufacturing cell

a dedicated area where products that are similar in processing requirements are produced -formed by allocating dissimilar machines to cells that are designed to work on similar products

An _____ arranges processes according to the sequence of steps by which the product is manufactured.

assembly line

continuous process

assembly line only the flow is continuous such as with liquids

continuous process

assembly line only the flow is continuous such as with liquids. ex: oil refining

What is the first step in the process for green sourcing?

assess the opportunity

If a company has more units in the master production schedule than firm customer orders, the residual is called?

available to promise

An assembly line is to operate eight hours per day with a desired output of 300 units per day. The following table contains information on this product's task times and precedence relationships: TASK TIME b/4 A 50 — B 40 A C 45 A D 25 A E 60 B, C F 35 C, D G 25 E, F H 50 G b. What is the required workstation cycle time to meet the desired output rate? (Round your answer to the nearest whole number.) c. Balance this line using the longest task time. (Leave no cells blank - be certain to enter "0" wherever required.) d. What is the efficiency of your line balance, assuming it is running at the cycle time determined in part b? (Round your answer to 1 decimal place.)

b. Workstation cycle time 96 correct seconds per unit c. Work Station Task Idle Time I A-C 1 II B-D 31 III E-F 1 IV G-H 21 d. Efficiency 85.9 %

Lumpiness, or the tendency for uneven production, further down the creation sequence is cause by items being withdrawn from inventory in single items. not possible with an ERP system in place. caused by items being withdrawn from inventory in lots.

caused by items being withdrawn from inventory in lots.

Which of the following is not a major characteristic to be considered when structuring an outsourcing relationship?

collaboration

assemble to order

combine a number of preassembled modules to meet a customer's specifications ex: Dell computers, subway sandwich - decoupling point: components -enables flexibility in combining components -define a customers order in terms of alternative components because these are carried in inventory

The term sourcing implies a more ________ process suitable for products that are strategically purchased.

complex

The term sourcing implies a more ________ process suitable for products that are strategically purchased. modest simple complex tactical

complex

One program for automatically resupplying customers on a regular basis is _______________ _______________.

continuous replenishment

One program for automatically resupplying customers on a regular basis is __________ _________

continuous replenishment

One program for automatically resupplying customers on a regular basis is ___________

continuous replenishment

what types of activities are key to the business but do not confer a competitive advantage? -core -outsourced -integral -strategic

core activities

Which of the following is an input file necessary to run an MRP system? Bill of materials (BOM) file Quality management report Exception reports Planned-order schedules Purchasing contracts

correct Bill of materials (BOM) file Quality management report Exception reports Planned-order schedules Purchasing contracts

The economic order quantity (EOQ) lot sizing technique produces or acquires exactly the amount of product that is needed each time period with none carried over into future periods.

correct False EOQ assumes that parts are used continuously during the period. The lot sizes generated by EOQ do not always cover the entire number of periods. For example, the EOQ might provide the requirements for 4.6 periods (when another EOQ would be needed).

Low level coding in MRP indicates the exact status of each item managed by the system in "real time."

correct False Low-level coding (is where) each item is placed at the lowest level at which it appears in the structure hierarchy.

In a net change MRP program, a change in one item will result in a completely new inventory plan and schedule for every item in the master production schedule.

correct False Net change systems are "activity" driven and requirements and schedules are updated whenever a transaction is processed that has an impact on the item. Net change enables the system to reflect in "real time" the exact status of each item managed by the system.

"Projected available balance" is a term referring to unsold finished goods inventory.

correct False Projected available balance is the amount of inventory (not just unsold finished goods) that is expected as of the end of a period.

An input to the material requirements planning (MRP) system is an exception report.

correct False This BOM file is one of the three main inputs to the MRP program. (The other two are the master schedule and the inventory records file.)

A product tree can do which of the following? Help to compute component usage Reduce product scrap Reduce labor overtime Reduce regular time labor Locate raw material supplies

correct Help to compute component usage Reduce product scrap Reduce labor overtime Reduce regular time labor Locate raw material supplies The BOM file is often called the product structure file or product tree because it shows how a product is put together. It contains the information to identify each item and the quantity used per unit of the item of which it is a part.

A BOM file is also called which of the following?

correct Product tree Stocking plan Inventory usage record Production parts plan Time bucket schedule The BOM file is often called the product structure file or product tree because it shows how a product is put together.

A master production schedule is an input to a material requirements planning (MRP) system.

correct True Generally, the master schedule deals with end items and is a major input to the MRP process.

A lot-for-lot (L4L) lot sizing technique does not take into account setup costs or capacity limitations.

correct True Lot-for-lot (L4L) is the most common technique. It: • Sets planned orders to exactly match the net requirements. • Produces exactly what is needed each week with none carried over into future periods. • Minimizes carrying cost. • Does not take into account setup costs or capacity limitations.

MRP is a logical, easily understandable approach to the problem of determining the number of parts, components, and materials needed to produce each end item.

correct True MRP is a logical, easily understandable approach to the problem of determining the number of parts, components, and materials needed to produce each end item.

MRP is based on dependent demand

correct True MRP is based on dependent demand. Dependent demand is caused by the demand for a higher-level item. Tires, wheels, and engines are dependent demand items based on the demand for automobiles, for example.

MRP provides the schedule specifying when each part and component of an end item should be ordered or produced.

correct True MRP provides the schedule specifying when each of these items should be ordered or produced.

Time fences are periods of time having some specified level of opportunity for the customer to make changes.

correct True Management defines time fences as periods of time having some specified level of opportunity for the customer to make changes.

Net change MRP systems are "activity" driven.

correct True Net change systems are "activity" driven and requirements and schedules are updated whenever a transaction is processed that has an impact on the item. Net change enables the system to reflect in "real time" the exact status of each item managed by the system.

The master production schedule states the number of items to be produced during specific time periods.

correct True The master production schedule states the number of items to be produced during specific time periods.

The deeper one looks into the product creation sequence, the more the requirements of dependent demand items tend to become more "lumpy."

correct True The requirements of dependent demand items tend to become more and more lumpy as we go farther down into the product creation sequence.

The three main inputs to an MRP system are the bill of materials, the master schedule and the inventory records file.

correct True This BOM file is one of the three main inputs to the MRP program. (The other two are the master schedule and the inventory records file.)

Computing the quantity of each component that goes into a finished product can be done by expanding (or exploding) each item in a product structure file and summing at all levels.

correct True To compute the amount of each item needed at the lower levels, each item would need to be expanded ("exploded") and summed. A more efficient procedure is to store parts data in simple single-level lists. That is, each item and component is listed showing only its parent and the number of units needed per unit of its parent.

What term describes the annual cost for a company to produce the good or services provided to customers?

cost of goods sold

costs of goods sold is also known as

cost of revenue

Cost of goods sold is also referred to as the cost of revenue. cost of inventory. cost of expenses. cost of doing business.

cost of revenue.

which is an approach used in consolidation warehouses, where, rather than making larger shipments, large shipments are broken down into mixed shipments for local delivery in an area? -third party logistics -cross docking -location services -hub and spoke systems

cross docking

creating assortment is one of the economic benefits provided by warehouses t/f

false

Improved return on assets and generation of cash are ___________ reasons to outsource

financial

little law

flow of items through production process inventory = throughput rate x flow rate

what is used to describe a practice where a customer purchases excess parts in advance? -hedging -risky buying -forward buying -buying to forecast

forward buying

Staple products that customers buy in a wide range of retail outlets are known as __________ products.

functional

Staple products that customers buy in a wide range of retail outlets are known as _______________ products.

functional

What type of products have low profit margins, long product life, and predictable demand?

functional

What type of products include staples that people buy in a wide range of retail outlets?

functional

Shorter cycle time and better risk management are driven reasons to outsource.

improvement

Which of the following is NOT a major economic benefit provided by warehouses?

increased flow time

Green sourcing is not only for developing new technologies, but also for

increasing the use of recyclable materials.

which is not a cause of the bullwhip effect -rationing and shortage gaming -order batching -information sharing -demand forecasting updating

information sharing

What type of products have a life cycle of just a few months?

innovative

Weeks of supply is a measure of how many weeks' worth of __________ is in the system at a particular point in time

inventory

Weeks of supply is a measure of how many weeks' worth of __________ is in the system at a particular point in time.

inventory

A material requirements planning system interfaces with the master production schedule, bill-of-materials file and __________

inventory records file.

When changes occur because of stock receipts and disbursements, scrap losses, wrong parts and canceled orders, the real-time file capturing these changes is called the peg record file. bill-of-material file. inventory transactions file. inventory backlog file.

inventory transactions file.

The ratio of cost of good sold to average inventory value is known as asset turnover. employee turnover. inventory turnover. receivables turnover.

inventory turnover.

The inventory records file contains information such as Multiple select question. item description. list of authorized suppliers. lead time. planned order releases. safety stock.

item description. lead time. planned order releases. safety stock.

The master production schedule typically deals with end items, but can be broken down to __________ if the item is large or expensive. inexpensive components work-in-process major subassemblies single use

major subassemblies

make to order

make the customer's product from raw materials, parts, and components ex: cars or boeing's process for making aircraft

Firms whose product is built directly from raw materials and components in response to a customer are known as

make-to-order.

Which sourcing process is used for complex items where there are a number of potential vendors?

request for proposal

which sourcing process demands high transaction costs? -electronic catalog -request for proposal -spot purchase -vendor managed inventory

request for proposal

A product with high demand uncertainty and low supply uncertainty would utilize which type of supply chain?

responsive

a product with high demand uncertainty and low supply uncertainty would utilize which type of supply chain? -responsive -agile -risk hedging -efficient

responsive

make to stock

serve customers from finished goods inventory ex: things sold in retail like televisions, clothing, packaged food -essential issue in satisfying customers is to balance level of inventory against level of customer service -use lean manufacturing to achieve higher service levels for a given inventory investment -decoupling point is FG inventory

The EOQ is the Quantity where the ___ costs equal the ___ costs.

set-up order

Workcenter (job shop)

similar equipment or functions are grouped together

workcenter (job shop)

similar equipment or functions are grouped together -most common is to arrange the centers in a way that optimizes the movement of material -sometimes referred to as a department and is focused on a particular type of operation

Which type of time fence allows for changes to a specific product so long as parts are available

slushy

Production process

source, make, deliver

which is a sourcing term to describe how monnon an item is / how many substitutes may be available -outsourcing -specificity -bullwhip effect -uniqueness

specificity

operation and route sheet

specifies operations and process routing -helps determine cost of making the product

Which type of supply process has a mature manufacturing and technology base?

stable

which type of supply process is one where the manufacturing and technology base are mature? -functional -stable -evolving -innovative

stable

which is not a benefit provided by cross docking -reduced demand -reduced flow time -increased inventory turnover -stockpiling to accommodate seasonal demand

stockpiling to accomodate seasonal demand -- tranditional warehouses

What term describes the development and management of supplier relationships?

strategic sourcing

A company producing widgets only needs Part A for 40% of the widgets built. This company is likely using what type of bill-of-material?

super

The bullwhip effect can be reduced by _______________ efforts among members of the supply chain.

synchronizing

In a project layout, a high degree of __________ is common. Multiple choice question. process cell formation workcenter design assembly line work task ordering

task ordering

If ordering costs and setup costs remain constant then _________ is the easiest method for lot sizing. the lowest total cost method any method the least unit cost method the lot-for-lot method

the lowest total cost method

project

the product remains in a fixed location -manufacturing equipment is moved to the product -high degree of task ordering -layout may be developed by arranging materials according to their assembly priority

THis is not true about the bullwhip effect

the size of orders increases as the order moves from retailers to wholesalers to manufacturers to suppliers

Total average value of inventory

the sum of the value (at cost) of the raw material, work-in process, and finished goods inventory

lead time

the time needed to respond to a customer order

time between plane takeoffs can be at least 3 minutes. after take off, run time is 45 seconds. planes wait an average of 4 minutes and 15 seconds. on average there are 15 planes taking of per hours. How many planes are on the runway at once?

throughput rate: 15 planes/hour flow time: 4 min 15 sec + 45 sec -> 5 minutes inventory: 15 planes/hour x (5 min/60) = 1.25 planes

_____ _____ are a company's attempt to provide a controlled window of opportunity to make changes to the master production schedule.

time fences

At any point in time, an MRP system can access the status segment of the inventory record according to specific time periods commonly known as

time buckets

At any point in time, an MRP system can access the status segment of the inventory record according to specific time periods commonly known as low-level coding system. product part matrix. bill-of-material. time buckets.

time buckets.

An estimate of all costs related to the procurerment and use of an item is the

total cost of ownership

An estimate of all costs related to the procurerment and use of an item is the total purchase price. total cost of ownership. final cost. landed cost.

total cost of ownership.

True or false: The average aggregate inventory value is valued at cost

true

which is not a reason why a firm may choose to outsource an activity? -turn variable costs into fixed costs -improve risk management -shorten cycle time -improve quality

turn variable costs into fixed costs --> turn fixed costs into variable costs

Which of the following is not a reason why a firm may choose to outsource an activity?

turn variable into fixed costs

The re-order point is measured in terms of

units quantity

production process mapping

useful to understand how material flow and inventory is held

assembly line

work processes are arranged according to the progressive steps by which the product is made

engineer to order

work with the customer to design and make the product ex: buildings built to specification -customer order decoupling point could be in either raw materials at the manufacturing site or the supplier inventory

In a_____ layout, machines are grouped according to type or function and parts travel to the appropriate location for processing.

workcenter


Set pelajaran terkait

Florida Laws and Rules Pertinent to Insurance

View Set

chapter 3 the American free enterprise system test

View Set