The organization or person designated as the quality assurance authority performs the role usually assumed by what office?
Contracting Office
X (True or False) The Quality Control (QC) manager is responsible for managing and coordinating the project design, the three phases of control, and project documentation.
False
Naval Construction Force (NCF) units reviewing plans and specifications should identify project design conflicts between which of the following items?
Equipment needed and available resources
(True or False) A Quality Deficiency Report (QDR) may provide the basis for disciplinary action.
False
Quality Control (QC) manager managers should receive status logs from what individuals?
Project Managers
The Quality Assurance (QA) representative's primary point of contact for quality, workmanship, or general construction issues is what individual?
Quality Control Manager
Field Adjustment Requests (FARs) for project changes that exceed 50 man-days of additional effort or $500 in additional cost should be approved by the appropriate Naval Construction Regiment office prior to submission to what individual?
Resident Officer in Charge of Construction
A Quality Deficiency Report (QDR) for workmanship defects found on a construction project serves what purpose?
To report hidden quality defects found during a follow-up inspection
(True or False) The Quality Assurance (QA) representative has the responsibility to approve the Quality Control (QC) plan.
True
(True or False) The Quality Assurance Report (QAR) form is an optional report used at the discretion of quality assurance representatives and does not supersede engineering field division guidance given to Quality Control (QC) managers or project superintendents.
True
(True or False) The Quality Control (QC) manager may also perform duties as the project superintendent.
True
(True or False) The engineering unit's operations officer, in consultation with The project manager and quality control manager, should be aware of the unit's policy on personnel behavior, schedules, and expectations for turnover.
True
(True or False) The quality assurance representative is prohibited from stopping work for safety purposes only.
True
(True or False) The quality assurance representative should prepare a Quality Assurance Report (QAR) when there is a lost time mishap on a construction contract.
True