Quiz 3: Project Management Process Groups

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

Key outcomes of the executing process group are formal acceptance of the work and creation of closing documents.

False

Which project would be compatible with the use of the agile approach?

Projects that have more flexible scheduling

The level of activity and length of each process group varies for every project.

True

A(n) _____ is the person who ensures that the team is productive, facilitates the daily Scrum, enables close cooperation across all roles and functions, and removes barriers that prevent the team from being effective.

ScrumMaster

A(n) _____ is a set period of time, normally two to four weeks, during which specific work must be completed and made ready for review when using Scrum methods.

sprint

A(n) _____ is a document that includes stakeholders' roles, names, organizations, and contact information.

stakeholder register

A milestone list is an output associated with the Project Scope Management knowledge area.

False

Agile methods are used when deliverables have a low degree of change.

False

An organization's project management plan expresses the vision, mission, goals, objectives, and strategies of the organization.

False

Initiating processes are not required to end a project.

False

In Scrum, a(n) _____ is a useful object created by people.

Artifact

Which activity is a part of the Scrum planning process?

Creating sprint backlog

Which is an example of a pre-initiation task?

Developing a business case for a project

Which processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements?

Executing

Which project management process group(s) includes activities from every single knowledge area?

Initiating

The project cost management knowledge area maps to which process group through the activities of estimating costs and budget determination?

Planning

A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint.

True

In the Scrum method, team members work as a self-directed group coached by the ScrumMaster.

True

_____ are short descriptions written by customers of what they need a Scrum system to do for them.

User stories

What process group does the project integration management knowledge area map to through the activities of developing project charters?

initiating


Set pelajaran terkait

Psychology: Lifespan Development - Middle Adulthood | Chapter 8

View Set

Renewable and Nonrenewable Energy Sources

View Set

chapter 6 - rock identification study guide

View Set

FIN Chapter 4 - Financial Services: Savings Plans & Payment Accounts

View Set

INMUNOGLOBULINAS y otras BIOMOLÉCULAS - INMUNOLOGÍA

View Set

Laws and Rules OHIO Life & Health Insurance XCEL

View Set

ITSC 1307 Linux Competency 1 Review Quiz Material

View Set