Student Review Ch 5 - 8

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

An activity has a duration of 10 days. Its early start is 4 and its late start is 6. This activity has ____ days of total slack

2.

*Which of the following represents an activity on an activity-on-node (AON) project network

A node

*A key distinction between a risk response and a contingency plan is

A risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired.

*Refining estimates may be necessary for a number of reasons. For example, a manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project and meet the needs of the customer is an example of

Changes in project scope.

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first

Check to see which activities are on the critical path.

*Which of the following is NOT one of the basic rules to follow when developing project networks

Conditional statements are allowed but looping statements are not allowed.

The top-down method of estimating when the pooled experience of senior and/or middle managers are used to estimate the total project duration and cost is the ____ method

Consensus.

*Companies are using which of the following for improving the estimating process for future projects

Creating historical databases of previous projects.

*An activity that has more than one dependency arrow flowing into it is termed a(n)

Critical path.

What is the relationship between organizational culture and estimating

Cultural norms affect the accuracy of estimates.

*If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a

Dangler path.

*Which of the following is NOT one of the more common problems associated with scheduling multiproject resources

Decline in project quality.

*All resource leveling techniques involve

Delaying noncritical activities.

*Based on the following, which event should you be most concerned about

Design flaw.

Which of the following is provided by both the project network and the work breakdown structure

Activity duration.

Typical kinds of costs found in a project include all of the following EXCEPT

All of these are examples of costs found in a project.

Change management systems are designed to accomplish all of the following EXCEPT

All of these are examples of what change management systems are designed to accomplish.

*Which of the following is NOT included in a Failure Mode and Effects Analysis

All of these are included.

Which of the following groups should NOT be a part of the risk identification process?

All of these groups can be included in the risk identification process.

These are all guidelines a project manager should consider when assigning project work EXCEPT

Always assign the best people to the most difficult tasks.

*Rose is working on estimates for a project that is very similar to a previous project, in that it has many of the same features and those features have similar costs. Each feature or deliverable will represent the same percentage of the total cost as it did for the previous project. Rose is using the ____ method of top-down estimating

Apportion.

Which of the following top-down methods is used when projects closely follow past projects in regard to features and costs of those features, and result in costs being assigned by percentages to major segments of the project

Apportion.

In a project network, ____ indicate activity dependency and project flow

Arrows.

After your team has successfully identified potential risks that could affect the project, what is the next step

Assess identified risks.

Tools such as a risk assessment form and a risk severity matrix are used to

Assess risks.

*Adopting proven technology instead of experimental technology in order to eliminate technical failure would be an example of which risk response

Avoiding.

Which of the following is NOT true in regard to the level of detail estimates should contain

Detailed estimates are crucial to project success; therefore, an effort should be made to make estimates as detailed as possible for all projects.

____ is a measure of how easy it would be to notice that a risk event was going to occur in time to take mitigating action, that is, how much warning you would have

Detection difficulty.

*The salary of the project manager would be an example of what type of cost found in a project

Direct project overhead.

Which of the following correctly calculates the early finish for an activity

ES + DUR.

Which of the following correctly calculates the late start for an activity

ES - SL.

The backward pass in project network calculations determines all of the following EXCEPT

Earliest time an activity can finish.

The forward pass in project network calculations determines all of the following EXCEPT

Earliest time an activity can finish.

A special truck that George needs on his project has been scheduled on another project. This is an example of what type of resource constraint?

Equipment.

Which of the following is NOT involved in risk control

Establishing contingency funds.

Which of the following is NOT one of the recommended guidelines for developing useful work package estimates?

Estimates should include a normal level of contingency.

The process of forecasting or approximating the time and cost of completing project deliverable is called

Estimating.

*As long as everyone in a project adds a little padding to reduce risk, the project duration and cost estimates will be more accurate

False.

*If a project is internal to the company and relatively small, the bottom-up approach to estimating time and costs for the project is the best choice

False.

*If the project has a duration of 13 days, the project should be completed 13 days from the day it starts

False.

*Performance bonds, warranties, and guarantees are financial instruments used to share risk.

False.

*Project managers should always assign the best people to the most difficult tasks

False.

*Resource leveling or smoothing is only used on projects which are resource constrained

False.

*Risk management is a reactive approach that is designed to ensure that surprises are reduced and that negative consequences associated with undesirable events are minimized

False.

*Sequential activities hold just as much potential for resource conflicts as parallel activities.

False.

*Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity

False.

*Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation

False.

*The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project

False.

*The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints

False.

*The first step in the risk management process is risk assessment

False.

*When considering risk value, the lower the value, the higher the level of risk

False.

A lack of readily available engineers is a technical constraint

False.

A merge activity is one that merges with other activities into a succeeding activity

False.

A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. We can assume that everything is going as planned and that we are under budget

False.

Adopting proven technology instead of experimental technology is an example of mitigating a risk

False.

After averaging out the underestimates and overestimates, a long-duration project is more likely to be on target than a short-term, small project

False.

An activity can include only one work package

False.

Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens

False.

Estimating the total cost of a house by multiplying the total square feet by cost per square foot is an example of the apportion method of estimating costs

False.

Estimating the total cost of a project by multiplying each major function by a complexity factor is an example of the apportion method of estimating costs

False.

If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint

False.

If time and costs are important to a project the top-down approach to estimating time and costs for the project is the best choice

False.

If, during risk response development, you successfully identify how you will respond to a risk, contingency planning is unnecessary

False.

Project estimates should be broken down into as much detail, and with as much accuracy, as possible

False.

Responses to all identifiable risks should be a top priority for the project manager

False.

Risk events that occur in the early stages of a project will have a greater cost impact than those that occur in later stages

False.

The WBS identifies dependencies, the sequencing of activities, and the timing of activities

False.

The backward pass determines project duration

False.

The consensus method of estimating costs is a bottom-up technique.

False.

The forward pass through a project network determines the critical path

False.

The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints

False.

The process of forecasting or approximating the time and cost of completing project deliverable is called planning

False.

The project being delayed is an example of a major risk that should be assessed

False.

The project management structure chosen to manage the project will have little impact on the quality of estimates

False.

The risk identification process should be limited to just the core project team.

False.

The salary of the project manager and her administrative assistant is classified as direct labor costs

False.

When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities

False.

When developing a response to a risk by scheduling outdoor work in the summer, investing in up-front safety training, or choosing high-quality materials, these are examples of retaining a risk

False.

When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack

False.

Work package estimates should include allowances for contingencies

False.

*If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists

Finish to Finish.

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag

Finish to Start.

The ____ lag is the most typical type of lag that is encountered in developing networks

Finish-to-start.

All of the following are types of resource constraints EXCEPT

Information.

Which of the following does NOT help describe a bottom-up estimating approach

They are made by someone who uses experience and/or information from someone else to determine overall project cost and duration.

*Which of the following is true about hammock activities

They are used to identify the use of fixed resources or costs over a segment of a project.

Refining estimates may be necessary for a number of reasons. For example, design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are good examples of

Things going wrong on a project.

Which of the following is a good condition for top-down estimating

Internal, small project.

All of the following are benefits of scheduling resources before project implementation EXCEPT

It ensures low network sensitivity.

Why is it necessary to have a time-phased budget baseline

It shows how much work was accomplished for the money spent.

Which of the following will correctly calculate the total slack in an activity

LF - ES.

*Which of the following would best represent direct project costs

Labor, materials and equipment.

Learning curves are more likely to be applied in situations where most of the costs are

Labor.

The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called

Laddering.

When an activity with a long duration is broken into smaller segments so that the following activities can begin sooner it is called ____

Laddering.

A(n) ____ is the minimum amount of time a dependent activity must be delayed to begin or end

Lag.

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as

Lag.

*Laura is forecasting the time and cost of developing an intranet for a new customer. Her department has completed six such intranets for customers during the last two years. Although the proposed system is about the same size as the others, she estimates that it will take about 10 percent less time and money. Which of the following methods is she using

Learning curve.

Which of the following is NOT one of the bottom-up approaches to estimating project time and cost

Learning curve.

*In a resource-constrained project, the first priority in assigning resources is usually given to activities with the

Least slack.

Risks are evaluated in terms of

Likelihood and impact.

The significance of a risk is assessed in terms of the ____ and the impact of the event

Likelihood.

The critical path in a project network is the

Longest path through the network.

Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of

Looping.

A network has only one critical path and the slack for noncritical activities is high. This network would appear to have a ____ level of sensitivity

Low.

In a resource-constrained project the third priority in assigning resources is usually given to activities with the

Lowest identification number.

Which of the following is identified to cover major unforeseen risks and, hence, are applied to the total project

Management reserves.

*Gene is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint

Materials.

*Splitting an activity can result in all of the following EXCEPT

More people working on the same activity.

Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization. She should first identify activities with the

Most slack.

Refining estimates may be necessary for a number of reasons. For example, resource shortages, in the form of people, equipment, or materials, can extend original estimates. This is a good example of

Normal conditions not applying.

When translated into a project network, a work package will become

One or more activities.

*____ focuses on how to respond to events that have a positive impact on a project

Opportunity management.

The estimating factor that considers the prevailing belief in some firms that detailed estimating takes too much time and is not worth the effort is an example of the ____ factor

Organization Culture.

When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

Outsourcing.

A project cost baseline is also called ____

PV (Plan Value)

*Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation

Padding estimates.

The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood of meeting the estimates is known as the ____ factor

Padding estimates.

Activities which can take place at the same time are termed

Parallel activity.

A good starting point for developing time and cost estimates is

Past experience.

A sequence of connected, dependent activities is termed a(n)

Path.

*A shortage of programmers to write software is an example of a(n) _____ type of resource constraint

People.

Rachel is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time. There are only 3 available for her to use. This is an example of what type of constraint

People.

Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint

People.

The estimating factor that considers the skill level of participants doing the estimating is known as the ____ factor

People.

Which of the following would be the best method for projects where the final product is not known and the uncertainty is very large

Phase estimating.

Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it

Physical.

Trying to renovate a ship compartment that is too small for more than one person is an example of a(n) _____ resource constraint

Physical.

The estimating factor that considers the decreasing accuracy of estimates as one forecasts activities that are further into the future is known as _____

Planning Horizon.

Richard is collecting estimates for a house that he will have the funding to build in 12 months. Which of the following factors does Richard need to consider in regard to the quality of these estimates

Planning horizon.

___ activities must be completed immediately before a particular activity

Predecessor.

*Which of the following is NOT one of the factors that need to be considered to improve quality of estimates for project times and costs

Profit.

Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognizing

Project duration.

*Arrows on an activity-on-node (AON) project network represent

Project flow and dependency.

Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach

Range estimating.

*Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. Which of the following methods is he using

Ratio.

Resource leveling or smoothing can have all the following results on a project EXCEPT

Reduced resource need over the life of the project.

*If resources are not adequate to meet peak demands, the resulting reschedule is termed

Resource-constrained scheduling.

In reviewing the status of her project with top management, Shirley was told that there are only two programmers that she can use for her project. Her project is classified as _______ constrained

Resource.

*The risk associated with the unlikelihood that one of the key members will be struck by lightning would most likely be handled by which of the following

Retaining.

Organizations use ____ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk

Risk breakdown structures.

*The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as

Risk management.

A list of questions that address traditional areas of uncertainty on a project is termed a

Risk profile.

Which of the following is NOT one of the steps in the risk management process

Risk tracking.

*An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a

Risk.

An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is known as a ____

Risk.

Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation

Scope creep.

The likelihood the original critical path(s) will change once the project is initiated is referred to as

Sensitivity.

______ reflects the likelihood the original critical path(s) will change once the project is initiated.

Sensitivity.

The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk

Severity matrix.

The chances of a risk event occurring as a project proceeds through its life cycle tend to

Slowly drop.

The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

Slowly rise.

In a resource-constrained project the second priority in assigning resources is usually given to activities with the

Smallest duration.

*Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource

Smoothing.

The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as

Template method.

*Which of the following methods is NOT considered a top-down approach to estimating project time and cost

Template.

Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will he decide which activity should be scheduled first

The activity with the least slack.

*In a resource-constrained project, which of the following is most likely to be changed

The completion date.

When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select

The smallest LS of all its immediate successor activities to establish the LF.

*Most of the scheduling methods available today require the project manager to classify the project as either _____ constrained or ______ constrained

Time, resource.

*When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints

Time.

In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ -constrained project

Time.

Regina's boss has told her that her project is very important. If the critical path is delayed, she will be given whatever she needs to get it back on schedule. Her project is classified as ______ constrained

Time.

When classifying projects, ________ constrained means that project duration is fixed and resources are flexible

Time.

Reasons why estimating time and cost are important include all of the following EXCEPT

To help establish a project selection process.

*In practice, estimating processes are frequently classified as

Top down/bottom up.

The preferred method for situations involving strategic decision making, projects with a high degree of uncertainty, and projects with an unstable scope is the ____ approach to estimating project time and costs

Top-Down.

Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on back-order and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of

Total Slack.

*The amount of time an activity can be delayed and yet not delay the project is termed

Total slack.

____ slack must be coordinated with all participants in the activities that follow in the chain

Total.

A fixed price contract is an example of

Transferring risk.

Purchasing an accident insurance policy would be an example of responding to a risk by ____ it

Transferring.

*A risk is an uncertain event that, if it occurs, can have a positive or negative effect on project objectives

True.

*Estimates that are typically based on estimates of elements found in the work breakdown structure are called bottom-up estimates

True.

*General and administrative costs are usually allocated as a percent of the total of a direct cost which includes labor, materials, or equipment

True.

*If a network has more than one critical path but noncritical activities have very little slack, the network is considered to have a high level of sensitivity

True.

*In developing a project network, neither looping nor conditional statements are permitted

True.

*It is possible for a project network to have more than one critical path

True.

*Past experience is almost always used primarily in the initial phases of estimating

True.

A risk profile is a list of questions that have been developed and refined from previous, similar projects

True.

All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements

True.

All task time estimates need consistent time units

True.

An activity cannot begin until ALL preceding connected activities have been completed

True.

An activity is an element of the project that always requires time

True.

Budget reserves are set up to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project

True.

Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them)

True.

Change management systems involve reporting, controlling, and recording changes to the project baseline

True.

Contingency funding is made up of budget reserves and management reserves

True.

Cost, time, and budget estimates are the lifeline for control; they serve as the standard for comparison of the actual and the planned throughout the life of the project

True.

Different activities along the same path can have different total slack

True.

Estimates are supposed to be based on normal conditions. While this is a good starting point, it rarely holds true in real life

True.

Experience suggests that when there are multiple starts, a common start node should be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending

True.

Fixed-price contracts are an example of transferring risk from an owner to a contractor

True.

Gantt charts are popular because they represent an easy-to-understand, clear picture on a time-scaled horizon

True.

Having too few programmers and too many engineers is an example of a people resource constraint

True.

If resources are truly limited and activity time estimates are accurate, the resource-constrained schedule will materialize as the project is implemented, not the time-constrained schedule

True.

In a resource-constrained project, the completion date is most likely to change.

True.

It is acceptable for arrows to cross one another in a network diagram

True.

Lags can be used to constrain the start and finish of an activity

True.

One common mistake that is made early on in the risk identification process is to focus on consequences and not on the events that could produce consequences

True.

One guideline to follow when estimating time, cost and resources is to use several people to make the estimate for a task

True.

Only activities that occur at the end of a chain of activities can have free slack

True.

Organization culture can significantly influence project time and cost estimates

True.

Phase estimating is used when a project cannot be rigorously defined because of the uncertainty of design or the final product

True.

Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules

True.

Resource dependency takes priority over technological dependency but it does not violate it

True.

Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints

True.

The backward pass through a project network determines slack or how long an activity can be delayed without impacting the completion date of the project

True.

The ideal approach to estimating project time and costs is to use both the top-down and the bottom-up approach.

True.

The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint

True.

The probability that a risk event will occur is higher during the initial stages of a project

True.

To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix

True.

Too many parallel activities for one individual is an example of a resource constraint

True.

Top-down estimates usually are derived from someone who uses experience and/or information to determine the project duration and total cost

True.

Using free slack does not delay any following activities and requires no coordination with managers of other activities

True.

When resource constraints are added to technical constraints the original project network may change as well as the completion date

True.

While a "can do" attitude is essential during implementation, project managers have to encourage critical thinking when it comes to risk identification

True.

Without a time-phased budget a good project schedule and cost control are impossible

True.

*Which of the following describes the consensus method

Uses pooled experience of senior and/or middle managers to estimate the total project duration and cost.

*The approach to estimating project time and cost that begins with an overall estimate for the project and then refines estimates for various stages of the project as it is implemented is known as ____

phase estimating.

The estimating approach that is best to use on projects where there is an unusual amount of uncertainty surrounding the project and when it is impractical to estimate times and costs for the entire project is known as _____

phase estimating.

All leveling techniques delay noncritical activities by using ________ to reduce peak demand

positive slack.

*Activities that must occur immediately before a given activity are called ____ activities

predecessor.

Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. He is using the _____ method of top-down estimating

ratio.

In scheduling resource-constrained projects, _____ are typically used rather than optimum mathematical solutions

realistic or rules up-down.

After resource leveling or smoothing one goal is that the amount of resources needed over the life of the project will be

reduce.

Beth has two engineers assigned to her project and does not have access to more even if the result means extending the completion date on her project. She is managing a(n) ________ -constrained project

resource.

Having one person responsible for performing several activities, all due at the same time, is an example of a(n) _____ constraint

resource.

When classifying projects, ________ constrained means that a specific resource is fixed and the duration of the project is flexible

resource.

Flooding would be devastating to the project; however, it is very unlikely. The project manager is most likely to ____ this risk

retain.

When considering risk response development, assuming the risk because the chance of such an event is slim is known as ____ the risk

retaining.

*The first step in the risk management process is ____

risk anticipation.

*The ____ form identifies each risk event, the likelihood of it occurring, the potential impact, when it may occur, and the degree of difficulty in detecting it

risk assessment.

*A list of questions that address traditional areas of uncertainty on a project is known as a

risk profile.

The ____ matrix is divided into red, yellow, and green zones representing major, moderate, and minor risks

risk severity.

According to the Failure Mode and Effects Analysis (FMEA), Impact x Probability x Detection = ____

risk value.

Since resource leveling or smoothing delays noncritical activities, a common result is an increase in network _____

sensitivity.

*Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called resource ____

smoothing or laddering.

*Start-up and shutdown costs are major considerations when using the ______ scheduling technique

splitting or multitasking.

When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is called ____

splitting or multitasking.

Activities that must immediately follow a given activity are called ____ activities

successor.

A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints

technical or logic.

*Resource dependency takes priority over the technological dependency but does not violate _____ dependencies

technical.

The bottom-up method of estimating where work package time and costs for past projects are used as a starting point for a new project and adjustments are made based on differences in the new project is known as the ____ method

template.

Without a ____ budget a good project schedule and cost control are impossible

time phase.

*When someone uses experience and/or information from others to determine the project duration and total cost, ____ estimating is being used

top-down.

*When considering risk response development, passing risk to another party instead of changing it is known as ____ the risk

transferring.

Performance bonds, warranties, and insurance are examples of ____ a risk

transferring.

The event or point in time when a contingency plan will be implemented is called a ____

trigger.

The activity time estimates used to build a project network are derived from _____

work packages.

Accounting would be an example of which of the following costs typically found in a project

General and administrative overhead.

A(n) _____ activity is frequently used to identify the use of fixed resources or costs over a segment of the project

Hammock.

Refining estimates may be necessary for a number of reasons. For example, people working on prototype development needing time to interact with the design engineers after the design is completed is a good example of

Hidden interaction costs.

Which of the following does NOT help describe a project network

Highlights major deliverable and identifies their completion dates.

*The initial step in the risk management process is to

Identify the risks.

Which of the following is NOT one of the potential responses to a specific risk event

Ignoring.

An element in the project that consumes time is a(n)_____

activity.

Choosing to move a concert indoors to eliminate the threat of bad weather is an example of ____ a risk.

avoiding.

When considering risk response development, changing the plan to eliminate the risk or condition is known as ____ the risk

avoiding.

A(n) _____ calculates how late an activity can start and finish

backward path.

The ____ calculates the critical path and determines how long an activity can be delayed without delaying the project

backward path.

*When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverable and the project itself, ____ estimating is being used

bottom-up.

The preferred method for situations where the cost and time estimates are important, in a fixed contract situation, and when the customer wants a lot of detail is the ____ approach to estimating project time and costs

bottom-up.

____ reserves are identified for specific work packages and are distributed by the project manager and the team members.

budget.

A(n) ____ activity has more than one successor activity

burst.

____ systems involve reporting, controlling, and recording changes to the project baseline

change management.

*A ____ is an alternative that will be used if a possible foreseen risk event becomes a reality

contingency plan.

The delaying of any activity on the ____ will delay the completion of the project by the same amount

critical path.

The longest path through a project network is called the _____

critical path.

A way to improve estimates on future projects is to collect and archive data on past project estimates and actual. Creating a ____ for estimating is a way to achieve this goal

database.

The likelihood of a risk event occurring ____ as a project goes through its life cycle

decreases.

The measurement of how easy it would be to detect that the event was going to occur in time to take mitigating action is known as

detection difficulty.

The salary of the project manager and temporary rental space for the project team would be classified as ____ costs

direct overhead.

Project costs such as labor and materials are typically classified as _____ costs

direct.

If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint

equipment.

When a project is classified as resource-constrained and a resource constraint exists, the project duration is typically ____

extended.

A(n) ____ calculates project duration

forward path.

The ____ calculates the earliest times that activities can start or finish

forward path.

*____ can never be negative and applies only to the last activity in a single chain of activities

free slack.

The top-down method for estimating project time and cost that uses weighted variables based on major parameters and is frequently used in the development of software is known as the ____ method

function point.

Costs that are not directly related to a specific project, such as advertising, accounting, and senior management's salary, are classified as ____ costs

general and administrative overhead.

Costs that are associated with time devoted to the coordination in meetings and briefings as well as time necessary to resolve disconnects between tasks are known as _____ costs

interaction.

The top-down method of estimating project time and costs that is useful for projects requiring the same task, group of tasks, or product repeated several times, especially if it is labor intensive, is the ____

learning curve.

When scheduling activities in a resource-constrained project, typically the activity scheduled first has the ______ amount of slack

lease.

____ reserves are controlled by the project manager and the owner of the project and are used to cover major unforeseen risks to the entire project

management.

The shortage of computer chips to produce a circuit board is an example of a(n) ______ type of resource constraint

materials.

An activity that has more than one predecessor is a ____ activity

merge.

*When considering risk response development, reducing the likelihood that an event will occur and/or reducing the impact that an adverse event would have on a project is known as ____ the risk

mitigating.

Testing a new project on a smaller isolated area prior to installing it for the entire organization is an example of ____ a risk

mitigating.

*In a project network, recycling through a set of activities or ____ is not permitted

moving.

In reality resource allocation generally occurs in a(n) ______ environment where the demands of one project have to be reconciled with the needs of other projects

multiproject.

Estimates should be made based on _____ conditions, efficient methods, and a normal level of resources

normal.

Many companies are ______ project work to contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects

outsourcing.

Activities that can occur while an activity is taking place are called ____ activities

parallel or concurrent.

Activities that can take place at the same time if the manager wishes them to are called ____ activities.

parallel.

*Information to develop a project network is collected from the

Work breakdown structure.

On a project network, the activity times are derived from the

Work packages.

Project budgets are developed by time-phasing which of the following

Work packages.

Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves

Budget.

*A(n) _________ activity has more than one dependency arrow flowing from it

Burst.

___ activities are to be completed immediately following a particular activity

Burst.

One common mistake made early in the risk identification process is to

Focus on consequences and not on the events that could produce consequences.

Which of the following can be used without coordinating with managers of succeeding activities

Free slack.

Sean is forecasting the time and cost of developing a customized software program by looking at the number of inputs, outputs, inquiries, files, and interfaces. Which of the following methods is he using

Function point.

System documentation cannot end until three days after testing has started. This is an example of which kind of lag

Start to Finish.

Concurrent engineering, which has dramatically reduced the development time for new products, relies on what kind of lag

Start to Start lags.

*Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point

Technical dependencies between activities are known.

Risks that can result in a system or process that will not work are known as

Technical risks.

When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by ______ constraints

Technical.

Which of the following activities might you consider adding a time buffer to

You might consider adding a time buffer to any of these activities.

A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true

We can't be sure how the project is going.

A Risk Response Matrix contains all of the following EXCEPT

When the risk will occur.

Which of the following is a good condition for bottom-up estimating

When there is a fixed price contract.

The risk assessment form contains all of the following EXCEPT

Who will detect the occurrence of the risk event.

The information necessary to conduct a bottom-up estimate of project time and costs starts with the ____

Work Package.


Set pelajaran terkait

Module 2 - DNA replication & Chromosome structure

View Set

Lesson 2: Managing Users and Groups - CompTIA Linux Plus

View Set

Computer Programming - Assignment (ALA)Assignment

View Set

Marriage and Family: Chapter 1 Quiz

View Set