Chapter 10 Project Scheduling: Lagging, Crashing, and Activity Networks

Ace your homework & exams now with Quizwiz!

A) Resource 1

17) Use the Gantt chart and activity list to determine which resource is used the least. Activity Resources Activity Resources R 5 M 1 H 1 K 4 G 5 J 3 F 2 P 1 B 2 S 2 T 4 W 3 A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5

D) Resource 5

18) Use the Gantt chart and activity list to determine which resource is used the most. Activity Resources Activity Resources R 5 M 1 H 1 K 4 G 5 J 3 F 2 P 1 B 2 S 2 T 4 W 3 A) Resource 1 B) Resource 2 C) Resource 4 D) Resource 5

A) Finish to start relationship.

1) The most common type of logical sequencing between tasks is referred to as the: A) Finish to start relationship. B) Finish to finish relationship. C) Start to start relationship. D) Start to finish relationship.

B) Resource 3

10) Use the Gantt chart and the activity list to determine which resource is used the least. Activity Resources Activity Resources A 1 F 2 B 1 G 3 C 4 H 4 D 2 J 3 E 2 K 5 A) Resource 1 B) Resource 3 C) Resource 4 D) Resource 2

C) Resource 1

11) Use the Gantt chart and the activity list to determine which resource is used the most. Activity Resources Activity Resources A 1 F 2 B 3 G 3 C 4 H 4 D 2 J 5 E 2 K 1 A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2

D) Resource 2

12) Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. Activity Resources Activity Resources A 1 F 2 B 3 G 3 C 4 H 4 D 2 J 5 E 2 K 1 A) Resource 4 B) Resource 3 C) Resource 1 D) Resource 2

A) Resource 2

13) Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. Activity Resources Activity Resources A 5 F 2 B 6 G 3 C 7 H 4 D 1 J 5 E 2 K 1 A) Resource 2 B) Resource 3 C) Resource 1 D) Resource 4

B) Between 10 and 20

14) Use the Gantt chart and activity list to determine when resource 3 is free. Activity Resources Activity Resources R 3 M 1 H 1 K 5 G 4 J 3 F 2 P 1 B 2 S 2 T 4 W 3 A) Between 0 and 10 B) Between 10 and 20 C) Between 20 and 30 D) Between 30 and 40

C) Resource 2

15) Use the Gantt chart and activity list to determine which resource has the greatest continual use. Activity Resources Activity Resources R 3 M 1 H 1 K 5 G 4 J 3 F 2 P 1 B 2 S 2 T 4 W 3 A) Resource 3 B) Resource 1 C) Resource 2 D) Resource 4

D) Resource 5

16) Use the Gantt chart and activity list to determine which resource has the greatest continual use. Activity Resources Activity Resources R 5 M 1 H 1 K 5 G 5 J 3 F 2 P 1 B 2 S 2 T 4 W 3 A) Resource 4 B) Resource 2 C) Resource 3 D) Resource 5

C) Resource 1

19) Use the Gantt chart and activity list to determine which resource is used the most. Activity Resources Activity Resources R 3, 5 M 1, 2 H 1 K 4 G 2,5 J 3 F 4, 1 P 1 B 2 S 3, 4 T 4 W 3 A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 5

B) On the line adjoining the two activity nodes.

2) A finish to start lag delay is usually shown: A) As an added value in the predecessor's activity time. B) On the line adjoining the two activity nodes. C) As an added value in the predecessors early start time. D) As a subtracted value in the follower's early finish time.

D) Resource 3

20) Use the Gantt chart and activity list to determine which resource is used the least. Activity Resources Activity Resources R 3, 5 M 1, 2 H 1 K 4 G 2, 5 J 3 F 4, 1 P 1 B 2 S 3, 4 T 4 W 3 A) Resource 4 B) Resource 2 C) Resource 1 D) Resource 3

A) Resource 2

21) Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. Activity Resources Activity Resources R 3, 5 M 1, 2 H 1 K 4 G 2, 5 J 3 F 4, 1 P 1 B 2 S 3, 4 T 4 W 3 A) Resource 2 B) Resource 4 C) Resource 1 D) Resource 3

C) Permits scheduling resources well before they are needed.

22) A basic Gantt chart: A) Clearly displays early and late start and finish times for all activities. B) Cannot be used to track the project's progress. C) Permits scheduling resources well before they are needed. D) Shows dummy activities to preserve network logic.

D) Crashing.

23) The process of accelerating a project is referred to as: A) Streamlining. B) Expediting. C) Rushing. D) Crashing.

A) The project has slipped behind schedule.

24) One reason for crashing a project is: A) The project has slipped behind schedule. B) That the initial schedule may be too pessimistic. C) Market needs change and the project is not in demand any more. D) There are no repercussions for delivering the project late.

B) Increase the bureaucratic oversight.

25) Which of these approaches will NOT accelerate the completion of a project? A) Improve the productivity of existing project resources. B) Increase the bureaucratic oversight. C) Improve the working method. D) Increase the quantity of personnel and equipment.

D) Increase project resources.

27) The most common method for shortening activity durations involves the decision to: A) Eliminate bureaucracy. B) Alter the technology used in the activity. C) Assign more senior personnel to the activity. D) Increase project resources.

A) Activity A

29) Given the cost information in the table, what is the cheapest activity to crash on a per week basis? Activity | Normal Time |Normal Cost | Crash Time| Crash Cost A 8 $1,000 5 $6,000 B 6 2,000 4 6,000 C 9 2,500 6 8,000 D 12 4,000 8 10,000 A) Activity A B) Activity B C) Activity C D) Activity D

C) The early finish time for B increases to 31.

3) Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4-day lag between activities C and B? A) The early finish for A increases to 31. B) The early start time for A increases to 24. C) The early finish time for B increases to 31. D) The early start time for D falls to 23.

C) $6,790

30) Use the information in the table (all times are in days) to determine the lowest cost minimum completion time if the base cost for each activity finished in normal time is $1,000. Activity Normal Time Minimum Time Crash Cost ($/day) Predecessor A 10 6 $70 -- B 6 3 $40 -- C 2 2 -- B D 4 2 $60 C E 6 4 $80 A F 8 5 $90 D, E A) $7,120 B) $6,910 C) $6,790 D) $6,830

A) $6,280

31) Use the information in the table (all times are in days) to determine the lowest total cost for a 20-day project if the base cost for each activity finished in normal time is $1,000. Activity Normal Time Minimum Time Crash Cost ($/day) Predecessor A 10 6 $70 -- B 6 3 $40 -- C 2 2 -- B D 4 2 $60 C E 6 4 $80 A F 8 5 $90 D, E A) $6,280 B) $6,390 C) $6,530 D) $6,740

D) $460

32) Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is $1,000. Activity Normal Time Minimum Time Crash Cost ($/day) Predecessor A 10 6 $70 -- B 6 3 $40 -- C 2 2 -- B D 4 2 $60 C E 6 4 $80 A F 8 5 $90 D, E A) $400 B) $420 C) $440 D) $460

B) 37 weeks

39) A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the duration of the least expensive project possible? Activity Normal time Crash time Normal Cost Crash Cost Predecessor A 8 5 $1,000 2,000 B 6 4 1,500 2,000 A C 8 5 1,800 2,300 A D 12 9 1,000 1,800 B E 14 11 950 1,450 B F 9 7 1,500 1,900 C, D G 7 5 2,300 2,800 E, F A) 38 weeks B) 37 weeks C) 36 weeks D) 35 weeks

D) Day 29

4) What is the early start time for activity C if it has the start to start relationship shown? A) Day 20 B) Day 25 C) Day 27 D) Day 29

B) $12,450

40) A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the cost of the least expensive project possible? Activity Normal time Crash time Normal Cost Crash Cost Predecessor A 8 5 $1,000 2,000 B 6 4 1,500 2,000 A C 8 5 1,800 2,300 A D 12 9 1,000 1,800 B E 14 11 950 1,450 B F 9 7 1,500 1,900 C, D G 7 5 2,300 2,800 E, F A) $11,450 B) $12,450 C) $13,450. D) $14,450

C) $12,250

41) A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 33 weeks? Activity Normal time Crash time Normal Cost Crash Cost Predecessor A 8 5 $1,000 2,000 B 6 4 1,500 2,000 A C 8 5 1,800 2,300 A D 12 9 1,000 1,800 B E 14 11 950 1,450 B F 9 7 1,500 1,900 C, D G 7 5 2,300 2,800 E, F A) $11,250 B) $11,500 C) $12,250 D) $12,500

A) $14,250

42) A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than 30 weeks, there is a penalty of $300. What is the highest total cost for completing this project? Activity Normal time Crash time Normal Cost Crash Cost Predecessor A 8 5 $1,000 2,000 B 6 4 1,500 2,000 A C 8 5 1,800 2,300 A D 12 9 1,000 1,800 B E 14 11 950 1,450 B F 9 7 1,500 1,900 C, D G 7 5 2,300 2,800 E, F A) $14,250 B) $13,950 C) $13,550 D) $13,150

A) Cannot have more arrows than nodes.

43) An activity on an arrow network: A) Cannot have more arrows than nodes. B) Cannot have more nodes than arrows. C) Has one more node than arrows. D) Has one more arrow than nodes.

B) One dummy activity.

44) The AOA network described by this table needs: Activity Predecessor A -- B -- C A, B D B E C, D A) Zero dummy activities. B) One dummy activity. C) Two dummy activities. D) Three dummy activities.

C) Two dummy activities.

45) The AOA network described by this table needs: Activity Predecessor A -- B -- C A D A, B E C F C, D A) Zero dummy activities. B) One dummy activity. C) Two dummy activities. D) Three dummy activities.

D) Early finish time

46) What information is NOT included in the nodes for an AOA network? A) Label B) Early start time C) Late finish time D) Early finish time

A) Slack on the critical path.

47) Dummy activities have a duration equal to the: A) Slack on the critical path. B) Length of the predecessor. C) Length of the successor. D) Lag needed to preserve network logic.

B) 15.

48) The critical path of this network is: A) 14. B) 15. C) 12. D) 13.

C) 16.

49) The fastest completion time for this project is: A) 14. B) 15. C) 16. D) 17.

A) a < d

5) Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown. Which statement is BEST? A) a < d B) a < c C) b < c D) d < a

D) 18

50) What is the late finish for activity D in the network shown in the diagram? A) 15 B) 16 C) 17 D) 18

D) Can have all of the features described in A-C above.

53) An AOA network: A) Cannot show a merge activity. B) Cannot show a burst activity. C) Cannot have consecutive merge and burst activities. D) Can have all of the features described in A-C above.

A) If the project is complex.

54) AOA networks have an advantage over AON networks: A) If the project is complex. B) Because they are easier to read for novices. C) When it comes to software packages for project management. D) When the task of network labeling is considered.

B) Because they don't need dummy activities.

55) AON networks have an advantage over AOA networks: A) If the project under study is complex. B) Because they don't need dummy activities. C) In the construction industry because they are the norm. D) When it is critical to highlight milestones.

B) Simplify network logic and reduce it to the most meaningful relationships.

56) The BEST approach to network representation of a large and hugely complex project is to: A) Represent all activities and relationships. B) Simplify network logic and reduce it to the most meaningful relationships. C) Use AOA. D) Use AON.

D) Planning monthly production.

58) Networks would NOT be well suited for: A) Planning a construction project. B) Planning a wedding. C) Planning a software upgrade. D) Planning monthly production.

A) It is imperative that the network is a mutually accessible document.

59) When involved in a project involving many subcontractors: A) It is imperative that the network is a mutually accessible document. B) One subcontractor's network diagram should never be shown to another for ethical reasons. C) PERT/CPM should not be used. D) It is illegal to reveal one subcontractor's plan to another.

D) Between 45 and 60

8) Use the Gantt chart and the activity list to determine when resource 5 is free. Activity Resources Activity Resources A 1 F 1 B 5 G 2 C 4 H 5 D 3 J 3 E 2 K 4 A) Between 0 and 15 B) Between 15 and 30 C) Between 30 and 45 D) Between 45 and 60

A) Between 0 and 15

9) Use the Gantt chart and the activity list to determine when resource 2 is free. Activity Resources Activity Resources A 1 F 1 B 5 G 2 C 4 H 5 D 3 J 3 E 2 K 2 A) Between 0 and 15 B) Between 15 and 30 C) Between 30 and 45 D) Between 45 and 60

D) $262,000

38) A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project as quickly as possible? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $22,000 B A 12 $18,000 9 $32,000 C A 15 $22,000 9 $62,000 D B 3 $9,000 2 $18,000 E C 9 $15,000 5 $35,000 F E 7 $5,000 5 $8,000 G D 8 $13,000 6 $23,000 H A 12 $20,000 8 $32,000 J H 6 $45,000 4 $56,000 A) $244,000 B) $255,600 C) $258,333 D) $262,000

C) The top tier summary network does not give top management the basis for understanding the actual development of the project.

57) A complex project that is managed using a top-down, bottom-up approach to network diagrams means that: A) Management's top-down portion of the network contains the greatest detail. B) Top management does not have a basis for understanding the actual development of the project. C) The top tier summary network does not give top management the basis for understanding the actual development of the project. D) The bottom level information cannot be understood by those performing the actual work.

C) The slope of the line is negative because it costs more to finish an activity more quickly.

26) If an activity's cost is plotted against its duration on axes with zeros at the origin: A) The slope of the line is positive because it costs more to finish an activity more quickly. B) The slope of the line is negative because a shorter activity costs less than a longer one. C) The slope of the line is negative because it costs more to finish an activity more quickly. D) The slope of the line is positive because a longer activity costs more than a shorter one.

C) $25,000 per week

28) An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000. Due to slippage on the critical path you need to reduce this activity by three weeks. If the subcontractor informs you that the activity can be completed in 16 weeks for $200,000, what is the slope for the activity? A) $5,000 per week B) $33,333 per week C) $25,000 per week D) $12,500 per week

C) $1,780

33) It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity. Use this information to determine the lowest cost for this project. All times given are in days. Activity Normal Time Minimum Time Crash Cost ($/day) Predecessor A 10 6 $70 -- B 6 3 $40 -- C 2 2 -- B D 4 2 $60 C E 6 4 $80 A F 8 5 $90 D, E A) $1,720 B) $1,750 C) $1,780 D) $1,810

A) $172,000

34) A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 40 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $22,000 B A 12 $18,000 9 $32,000 C A 15 $22,000 9 $62,000 D B 3 $9,000 2 $18,000 E C 9 $15,000 5 $35,000 F E 7 $5,000 5 $8,000 G D 8 $13,000 6 $23,000 H A 12 $20,000 8 $32,000 J H 6 $45,000 4 $56,000 A) $172,000 B) $218,000 C) $192,000 D) $159,000

B) $197,500

35) A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 35 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $22,000 B A 12 $18,000 9 $32,000 C A 15 $22,000 9 $62,000 D B 3 $9,000 2 $18,000 E C 9 $15,000 5 $35,000 F E 7 $5,000 5 $8,000 G D 8 $13,000 6 $23,000 H A 12 $20,000 8 $32,000 J H 6 $45,000 4 $56,000 A) $211,500 B) $197,500 C) $203,500 D) $194,500

B) $184,000

36) A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $22,000 B A 12 $18,000 9 $32,000 C A 15 $22,000 9 $62,000 D B 3 $9,000 2 $18,000 E C 9 $15,000 5 $35,000 F E 7 $5,000 5 $8,000 G D 8 $13,000 6 $23,000 H A 12 $20,000 8 $32,000 J H 6 $45,000 4 $56,000 A) $172,000 B) $184,000 C) $187,000 D) $192,500

A) 34 weeks

37) A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 25 weeks. What is the lowest total cost duration for completing this project? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $22,000 B A 12 $18,000 9 $32,000 C A 15 $22,000 9 $62,000 D B 3 $9,000 2 $18,000 E C 9 $15,000 5 $35,000 F E 7 $5,000 5 $8,000 G D 8 $13,000 6 $23,000 H A 12 $20,000 8 $32,000 J H 6 $45,000 4 $56,000 A) 34 weeks B) 36 weeks C) 40 weeks D) 43 weeks

B) B and D

51) Which of the activities in the diagram have slack? A) C and D B) B and D C) C and E D) B and E

C) 38

52) What is the duration of the project shown in the network? A) 36 B) 37 C) 38 D) 39

B) Activity b probably has activity a as a predecessor.

6) Which statement about this Gantt chart is BEST? A) Activity a has a duration that could be as short as 1 day and as long as 10. B) Activity b probably has activity a as a predecessor. C) No progress has been made on activity c. D) Activity d is the longest activity.

B) There is a tendency to overestimate activity lengths.

60) Research has shown that, in general: A) There is a tendency to underestimate activity lengths. B) There is a tendency to overestimate activity lengths. C) The activity lengths are estimated correctly. D) The activity lengths are estimated correctly but the networks are drawn incorrectly.

C) 0 minutes

7) Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis. How much slack is available in The Great Hair Washing project? A) 10 minutes B) 15 minutes C) 0 minutes D) 5 minutes


Related study sets

Traditions & Culture of IU - Unit 2 EXAM !

View Set

Biology CK-12: Mendel's First Experiment

View Set

Consumer Behavior MK-320 MIDTERM 3/3

View Set