A(n) ___________ normally does not have any cost or duration. a) baseline b) milestone c) critical task d) activity

a

A(n) ____ path for a project is the series of activities that determine the earliest time by which the project can be completed. a) critical b) incidental c) vital d) integral

d

A(n) ________ is a distinct, scheduled portion of work performed during the course of a project. a.all answers are correctb.tasksc.work packaged.activity

b

The critical path is the shortest path through the network diagram. a) true b) false

a

There is usually no cost or duration associated with a milestone. a) true b) false

a

Most project management software shows the precedence diagramming method. a) true b) false

a

A ______ is a time-phased budget that project managers use to measure and monitor cost performance a) cost baseline b) bottom-up c) project budget d) critical task

b

A __________ is a time-phased budget that project managers use to measure and monitor cost performance. a) cost estimate b) cost baseline c) life-cycle budget d) project budget

s

A cost baseline is a(n) ____ budget that project managers use to measure and monitor cost performance. a.incrementalb.basicc.incidentald.time-phased

a

Activity ____ provide schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity. a.attributesb.propertiesc.characteristicsd.features

a

Critical chain scheduling considers limited resources when creating a project schedule and includes _________ to protect the project completion date. a) buffers b) multitasking c) reserves d) outsourcing

a

Critical chain scheduling considers limited resources when creating a project schedule. a) true b) false

b

In an AOA network diagram, a(n) ____ occurs when two or more nodes precede a single node. a.joinb.mergec.intersectiond.union

b

Project teams rarely estimate completion dates for milestones early in the scheduling process. a) True b) False

a

The _________ rule is that all work required for a deliverable is included in its sub-deliverables when defining activities. a.WBS 100%b.goldenc.roll-upd.hierarchy

b

The ____________ method is a network diagramming technique used to predict total project duration. a.Gantt chartb.critical pathc.PERTd.crashing

d

Using a(n) _________ approach to developing cost estimates requires a good deal of expert judgment and is generally less costly than others are, but it can also be less accurate. a.expert judgmentb.parametricc.bottom-upd.analogous

a

What activity was on the critical path for building Disney's Animal Kingdom theme park? a.growing grassb.building the tree of lifec.acquiring animalsd.obtaining funding

b

What is the PERT weighted average based on an optimistic estimate of six days, a most likely estimate of eight days, and a pessimistic time of sixteen days? a.sixb.ninec.eightd.ten

a

What is the first step in planning a project schedule? a) creating a schedule management plan b) developing an activity list c) determining activity sequencing d) assigning resources to the project

a

What is the formula for determining a PERT weighted average? a) (optimistic time + 4 x most likely time + pessimistic time)/6 b)(optimistic time + 6 x most likely time + pessimistic time)/4 c) (optimistic time + 4 x most likely time + pessimistic time)/4 d) (optimistic time + 6 x most likely time + pessimistic time)/6

c

What is the most common type of dependency between activities? a.start-to-finishb.finish-to-finishc.finish-to-startd.start-to-start

d

Which cost estimating technique would you be using if you estimate the cost of materials based on the number of square feet? a) analogous b) bottom-up c) top-down d) parametric modeling

b

Which number should be shortest when creating a three-point estimate? a.most likely timeb.optimistic timec.the critical pathd.pessimistic time

d

____ estimates involve estimating individual activities and summing them to get a project total. a) Temporary b) Provisional c) Ad hoc d) Bottom-up

c

_______ dependencies involve relationships between project and non-project activities a) Internal b) Miscellaneous c) External d) Ancillary


Related study sets

Chapter 30: Basic Pediatric Nursing Care (Foundations)

View Set

Chapter 10: Monopolistic Competition and Oligopoly

View Set

Scientific Method, Theory, Hypothesis

View Set

EAQ Ch 58 Care of Patients with Liver Problems

View Set

Introduction to Communication Concepts

View Set

STA15_03_Lesson9_10_U32_Place an order_Check an order

View Set

logic & critical thinking HW 3a-e

View Set

Health Science Ethics - GMS 6871-005 - Chapter 7 - Liability and Health Care: Legal Aspects of Health Care

View Set

CHAPTER 16: UNDERSTANDING MONEY AND THE ROLE OF BANKING (721E85-2)

View Set

LEGAL, ETHICAL & MORAL ISSUES OF HEALTH CARE

View Set

Chapter 25 Pregnancy- Related Complications

View Set

World Geography A: Unit 5 - Exam

View Set