b

A(n) ___________ normally does not have any cost or duration. a) baseline b) milestone c) critical task d) activity

a

A(n) ____ path for a project is the series of activities that determine the earliest time by which the project can be completed. a) critical b) incidental c) vital d) integral

d

A(n) ________ is a distinct, scheduled portion of work performed during the course of a project. a.all answers are correctb.tasksc.work packaged.activity

b

The critical path is the shortest path through the network diagram. a) true b) false

a

There is usually no cost or duration associated with a milestone. a) true b) false

a

Most project management software shows the precedence diagramming method. a) true b) false

a

A ______ is a time-phased budget that project managers use to measure and monitor cost performance a) cost baseline b) bottom-up c) project budget d) critical task

b

A __________ is a time-phased budget that project managers use to measure and monitor cost performance. a) cost estimate b) cost baseline c) life-cycle budget d) project budget

s

A cost baseline is a(n) ____ budget that project managers use to measure and monitor cost performance. a.incrementalb.basicc.incidentald.time-phased

a

Activity ____ provide schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity. a.attributesb.propertiesc.characteristicsd.features

a

Critical chain scheduling considers limited resources when creating a project schedule and includes _________ to protect the project completion date. a) buffers b) multitasking c) reserves d) outsourcing

a

Critical chain scheduling considers limited resources when creating a project schedule. a) true b) false

b

In an AOA network diagram, a(n) ____ occurs when two or more nodes precede a single node. a.joinb.mergec.intersectiond.union

b

Project teams rarely estimate completion dates for milestones early in the scheduling process. a) True b) False

a

The _________ rule is that all work required for a deliverable is included in its sub-deliverables when defining activities. a.WBS 100%b.goldenc.roll-upd.hierarchy

b

The ____________ method is a network diagramming technique used to predict total project duration. a.Gantt chartb.critical pathc.PERTd.crashing

d

Using a(n) _________ approach to developing cost estimates requires a good deal of expert judgment and is generally less costly than others are, but it can also be less accurate. a.expert judgmentb.parametricc.bottom-upd.analogous

a

What activity was on the critical path for building Disney's Animal Kingdom theme park? a.growing grassb.building the tree of lifec.acquiring animalsd.obtaining funding

b

What is the PERT weighted average based on an optimistic estimate of six days, a most likely estimate of eight days, and a pessimistic time of sixteen days? a.sixb.ninec.eightd.ten

a

What is the first step in planning a project schedule? a) creating a schedule management plan b) developing an activity list c) determining activity sequencing d) assigning resources to the project

a

What is the formula for determining a PERT weighted average? a) (optimistic time + 4 x most likely time + pessimistic time)/6 b)(optimistic time + 6 x most likely time + pessimistic time)/4 c) (optimistic time + 4 x most likely time + pessimistic time)/4 d) (optimistic time + 6 x most likely time + pessimistic time)/6

c

What is the most common type of dependency between activities? a.start-to-finishb.finish-to-finishc.finish-to-startd.start-to-start

d

Which cost estimating technique would you be using if you estimate the cost of materials based on the number of square feet? a) analogous b) bottom-up c) top-down d) parametric modeling

b

Which number should be shortest when creating a three-point estimate? a.most likely timeb.optimistic timec.the critical pathd.pessimistic time

d

____ estimates involve estimating individual activities and summing them to get a project total. a) Temporary b) Provisional c) Ad hoc d) Bottom-up

c

_______ dependencies involve relationships between project and non-project activities a) Internal b) Miscellaneous c) External d) Ancillary


Related study sets

Chapter 30: Basic Pediatric Nursing Care (Foundations)

View Set

Chapter 10: Monopolistic Competition and Oligopoly

View Set

Scientific Method, Theory, Hypothesis

View Set

EAQ Ch 58 Care of Patients with Liver Problems

View Set

Necessary And Sufficient Condition Indicator Words

View Set

Introduction to Communication Concepts

View Set

STA15_03_Lesson9_10_U32_Place an order_Check an order

View Set

logic & critical thinking HW 3a-e

View Set

Health Science Ethics - GMS 6871-005 - Chapter 7 - Liability and Health Care: Legal Aspects of Health Care

View Set

CHAPTER 16: UNDERSTANDING MONEY AND THE ROLE OF BANKING (721E85-2)

View Set

LEGAL, ETHICAL & MORAL ISSUES OF HEALTH CARE

View Set

Chapter 25 Pregnancy- Related Complications

View Set