Chapter 5: Project Schedule
what are the 4 types of task dependencies? (def)
-mandatory -discretionary -external -internal
Network diagram
A depiction of project activities and the interrelationships between these activities.
Activity list
A list of all the activities required to complete the work of the project that also includes an identifier code and the WBS code it's associated with. Activities are broken down from the work package level of the WBS.
Finish-to-finish (FF)
A project task relationship in which the finish of the successor task is dependent on the finish of the predecessor task.
Finish-to-start (FS)
A project task relationship in which the successor task cannot begin until the predecessor task has completed.
Start-to-start (SS)
A project task relationship where the start of the successor task depends on the start of the predecessor task.
Fast-tracking
A schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time. Fast-tracking reduces schedule duration.
Start-to-finish (SF)
A task relationship where the finish of the successor task is dependent on the start of its predecessor.
External dependency
A type of dependency where a relationship between a project task and a factor outside the project, such as weather conditions, drives the scheduling of that task.
Mandatory dependency
A type of dependency where the relationship between two tasks is created by the type of work the project requires.
Analogous estimating
An estimating technique that uses the actual duration of a similar, completed activity to determine the duration of the current activity; top-down; least accurate
Activity duration
Assessing the number of work periods needed to complete the project activities. Work periods are usually expressed in hours or days. Large projects might express duration in weeks or months.
CPM
Critical path method; A schedule development method that determines a single early and late start date, early and late finish date, and the float for each activity on the project.
what is the most commonly used logical relationship?
FS
what is a float?
It's the amount of time an activity can be delayed without delaying the project completion date.
what are two common forms to display project schedules?
PERT charts Gnatt charts
PDM
Precedence diagramming method; A network diagramming method that places activities on nodes, which connect to dependent activities using arrows. Also known as activity on node.
PERT
Program evaluation and review technique; Calculates the expected value, or weighted average, of critical path tasks to determine project duration by using three estimates: most likely, pessimistic, and optimistic. The PERT calculation is (optimistic + pessimistic + (4 × most likely)) / 6.
Float time
The amount of time the early start of a task may be delayed without delaying the finish date of the project. Also known as slack time.
Logical relationships
The dependency relationships that may exist between tasks. Finish-to-start is the most common logical relationship.
Schedule baseline
The final, approved project schedule that is used during project execution to monitor project progress.
Critical path (CP)
The longest path through the project. Activities with zero float are considered critical path tasks.
Dependencies
The relationship between project activities.
Dependency relationships
The type of dependency between two activities and the specific relationship between the activities.
Duration compression
The use of techniques such as fast-tracking or crashing to shorten the planned duration of a project or to resolve schedule slippage.
You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What is this telling you?
There is a finish-to-start dependency relationship between Activity A and Activity B.
Crashing
This is a schedule compression technique that adds resources to the project to reduce the time it takes to complete the project.
What is analogous estimating also referred to as?
Top-down estimating
governance gates (3)
approval points in the project; client sign-off, management approval, legislative approval
Gnatt chart
bar graph showing production managers what projects are being worked on and what stage they are in at any given time; displays tasks using horizontal bars across a timeline
discretionary dependencies
defined by the project management team; usually process or procedure driven and requires approvals and sign-offs
What are the crashing and fast tracking techniques used for?
duration compression
You are a project manager for a major movie studio. You need to schedule a shoot in Denver during ski season. This is an example of what type of dependency?
external dependency
PERT chart
production schedule specifying the sequence of activities, time requirements, and critical path for performing the steps in a project; graphical rep of the project's timeline
You have added a checkpoint in the project schedule to determine whether the work is accurate. What is this called?
quality gate
parametric estimating
quantitatively based estimate tat multiples the quantity of work by the rate of work; need to know the productivity rate of resource
Internal dependencies
relationship btwn tasks are confined within the project; under the control of the PT
What has been established as a result of the sponsor, customer, and key stakeholders signing off on the project schedule?
schedule baseline
quality gates
similar to milestones; used to determine qualilty checks at strategic points
duration compression
technique used during planning stage to shorten planned duration of project; helps resolve schedule slippage