The arrows in a network diagram represent missed milestones in a project.

False

Estimates should become more accurate as time progresses.

True

It is important for project managers to understand that every cost estimate is unique.

True

What does the process of controlling costs primarily involve?

managing changes to the project budget

Which type of dependencies are inherent in the nature of work being performed on a project?

mandatory

The formulas for variances and indexes start with EV, the earned value.

True

After defining project activities, the next step in project schedule management is developing the schedule.

False

In a Gantt chart, thick black bars represent milestones achieved in a project.

False

Supporting details for an estimate include the ground rules and assumptions used in creating the estimate.

True

The critical path on a project can change as the project progresses.

True

If cost variance is a positive number, it means that performing the work costs more than planned.

False

If the cost performance index (CPI) is less than 100 percent, the project is under budget.

False

Milestones are easy to achieve and are always achieved through one main activity.

False

A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.

True

Which is a similarity between scope control and schedule control?

Both are portions of the integrated change control process under project integration management.

27. If the cost performance index (CPI) is less than 100 percent, the project is under budget.

False

A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.

False

One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.

False

Which technique involves doing activities in parallel that one would normally do in sequence?

Fast tracking

Which provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format?

Gantt charts

Which is true of the schedule performance index (SPI)?

It can be used to estimate the projected time to complete the project.

Which is true of a finish-to-finish dependency?

It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.

Which is true of earned value?

It is an estimate of the value of the physical work actually completed.

Which network diagramming technique uses boxes to represent activities?

PDM

What is an accurate difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM)?

PERT uses different duration estimates whereas CPM uses one specific duration estimate.

Which law states that work expands to fill the time allowed?

Parkinson's Law

Which is most likely to be a reason for inaccuracies in information technology cost estimates?

People lack estimating experience.

Which statement is true of contingency reserves?

They allow for future situations that can be partially planned for.

Which statement is true of analogous estimates?

They are most reliable when previous projects are similar in fact with current projects.

Which statement is true of bottom-up estimates?

They are time-intensive and expensive to develop.

Which statement is true of tangible costs?

They can be easily measured.

Which is true of dummy activities?

They have long durations.

A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates.

True

A cost management plan can include organizational procedures links, control thresholds, and process descriptions.

True

A dependency pertains to the sequencing of project activities or tasks.

True

Which is a similarity between the crashing and fast tracking?

both can shorten the time needed to finish a project

What type of estimate is a cost estimation tool that involves estimating individual work items or activities and summing them to get a project total?

bottom-up

Which is an output of schedule control?

change requests

The main goal of which process is to produce a cost baseline for measuring project performance and project funding requirements?

cost budgeting

Which is an output of the process of controlling costs?

cost forecasts

Which technique is used for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?

crashing

Which technique involves network diagramming and is used primarily to predict total project duration?

critical path analysis

Which type of estimate should be used if the cost estimate for a project is used a basis for contract awards and performance reporting?

definitive

In project schedule management, the ultimate goal of which process is to provide a basis for monitoring project progress for the time dimension of the project?

developing a schedule

Variances are calculated by subtracting the actual cost from which value?

earned value

Which statement best defines cost variance?

earned value minus the actual cost

Which statement best defines schedule variance?

earned value minus the planned value

After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?

estimate the duration of activities.

What is the purpose of a cost performance index (CPI)?

estimate the projected cost of completing the project

Which dependencies involve relationships between project and non-project activities?

external

How does critical chain scheduling protect tasks on the critical chain from being delayed?

feeding buffers

Which dependencies do AOA network diagrams use?

finish-to-start

What term is used for the amount of time an activity can be delayed without delaying the early start date of any immediately following activities?

free slack

What is the latest possible time an activity might begin without delaying the project finish date?

late start date

The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.

longest; shortest

The additional percentage or dollar amount by which actual costs exceed estimates is known as a(n) _____.

overrun

Which type of estimating uses project characteristics in a mathematical model to estimate project costs?

parametric

What is another term used for budget?

planned value

Where would a draft schedule for a project most likely be found?

project charter

Which is one of the main outputs of estimating activity resources process?

project documents update

How are profits best defined?

revenues minus expenditures

During which relationship is the "from" activity unable start until the "to" activity is started?

start-to-start

Good Earth, a company manufacturing packaged food products, sets up its stores in Baltonia. However, a year later, the company closes the store down due to high operating costs. In such a scenario, the money spent in paying for the rent of the store in Baltonia would be an example of which costs?

sunk

What term is used for the amount of time an activity can be delayed from its early start without delaying the planned project finish date?

total slack

Which is an input of the process of controlling costs?

work performance data

A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for a project.

False

Critical chain scheduling assumes that resources multitask and maximizes multitasking.

False

In a critical path analysis, the shortest path is what drives the completion date for the project.

False

In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.

False

Intangible costs can be easily measured in monetary terms.

False

The project management plan and project funding requirements are inputs of the process of controlling costs.

True

Overrun is the additional percentage amount by which estimates exceed actual costs.

False

Start-to-finish relationships are the most frequently used dependencies between activities.

False

A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.

False

Analogous estimates are called activity-based costing.

False

Analogous estimates are the most accurate technique to estimate costs.

False

The main disadvantage of crashing is that it lengthens the time needed to finish a project.

False

The primary output of the planning cost management process is a change request.

False

The final process in project schedule management is developing the schedule.

False

When deciding what projects to invest in or continue, one should include sunk costs.

False

Project managers must conduct cash flow analysis to determine net present value.

True

Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.

True

Contingency reserves are also known as unknown unknowns.

False

The technique of fast tracking can result in lengthening the project schedule.

True

To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.

True

A merge occurs when one node precedes multiple nodes.

False

A negative schedule variance means that it took less time than planned to perform the work.

False

Which statement best describes the difference between an activity list and an activity attribute?

An activity attribute provides more schedule-related information about each activity than an activity list.

A backward pass through the network diagram determines the early start and early finish dates for each activity.

False

A budgetary estimate is the most accurate of the three types of estimates.

False

Which method is used for determining the estimated annual costs and benefits for a project?

Cash flow analysis

Soles is a footwear company which has recently set up its store in Ambrosia. To manufacture its products, Soles incurs a range of different costs. Which would be an example of an indirect cost?

Electricity used to run its factories

Which costs are difficult to measure in monetary terms?

Intangible costs

Which statement is true of a order of magnitude estimate?

It provides an estimate of what a project will cost.

Which reserves allow for future situations that are unpredictable?

Management reserves

Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project?

analogous estimates

What is a rough order of magnitude estimate also referred to as?

ballpark

What type of estimate is a cost estimation tool used to allocate money into an organization's budget?

budgetary

In an AOA network diagram, what occurs when two or more activities follow a single node?

bursts

In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities?

estimating activity durations

In project schedule management, which process primarily involves checking and managing changes to the project schedule?

controlling the schedule

Which process results in a cost baseline as a main output?

cost budgeting

Work performance information and cost forecasts are main outputs of which process?

cost control

In project schedule management, the main goal of which process is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work?

defining activities

In project schedule management, which process generates the main outputs of an activity list, activity attributes, and a milestone list?

defining activities

Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?

defining activities

What type of estimate is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs?

definitive

Which process involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance?

determining the budget

In project schedule management, what is the next step after defining project activities?

determining their dependencies

In project schedule management, which process involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?

developing the schedule

Newtech Inc. hires John for the position of a software programmer to work on their new project. Salary paid to John by Newtech Inc. would be an example of which type of costs?

direct

Which dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options?

discretionary

Which process involves developing an approximation of the costs of resources needed to complete a project?

estimating costs

What term is used for analogous estimates?

top-down

Which process helps develop an accurate projection of a project's financial expenses and benefits?

life cycle costing

Which term is used for a significant event on a project that normally has no duration?

milestone

Which statement is true regarding indirect costs?

not directly related to the products or services of a project.

What is the first step in project cost management?

plan how costs will be managed

What is the first process involved in project schedule management?

planning schedule management

In project schedule management, which is an output of controlling the schedule?

project management plan update

Project schedules grow out of basic documents such as the project charter.

True

A schedule performance index of one means that the project is on schedule.

True

An activity is an element of work that has an expected duration, cost, and resource requirements.

True

Budgetary estimates are made even before a project is officially started.

True

Definitive estimates are made one year or less prior to project completion.

True

Determining the budget involves allocating the project cost estimate to individual work items over time.

True

IT project managers must be able to present and discuss project information both in financial and technical terms.

True

If an important supplier goes out of business, management reserves can be set aside to cover the resulting costs.

True

In a bottom-up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates.

True

It is important for the activity list and activity attributes to be in agreement with the work breakdown structure.

True

Knowing the amount of float allows project managers to know whether a project schedule is flexible.

True

Network diagrams are the preferred technique for showing activity sequencing.

True

One of the reasons why project cost estimates are inaccurate is because human beings are biased toward underestimation.

True

Parametric models are reliable when the models are flexible in terms of the project's size.

True

In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?

sequencing activities

In project schedule management, the next step after sequencing activities is to define these activities.

False

In project schedule management, the primary output of defining activities is a schedule management plan.

False

It is important for project managers to focus on indirect costs because they can be easily controlled.

False

Which document is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?

project charter

What type of management includes the processes required to ensure that a project team completes a project within an approved budget?

project cost management