After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?

Determine their dependencies

In project schedule management, which process involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?

Developing the schedule

Which dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options?

Discretionary

A backward pass through the network diagram determines the early start and early finish dates for each activity.

False

In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.

False

In project schedule management, the next step after sequencing activities is to define these activities.

False

In project schedule management, the primary output of defining activities is a schedule management plan.

False

Milestones are easy to achieve and are always achieved through one main activity.

False

One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.

False

Start-to-finish relationships are the most frequently used dependencies between activities.

False

The arrows in a network diagram represent missed milestones in a project.

False

The main disadvantage of crashing is that it lengthens the time needed to finish a project.

False

Which technique involves doing activities in parallel that one would normally do in sequence?

Fast tracking

How does critical chain scheduling protect tasks on the critical chain from being delayed?

Feeding buffers

What is the latest possible time an activity might begin without delaying the project finish date?

Late start date

The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.

Longest; shortest

What is an accurate difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM)?

PERT uses different duration estimates whereas CPM uses one specific duration estimate.

What is the first process involved in project schedule management?

Planning schedule management

Which document is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?

Project charter

Which is true of dummy activities?

They show logical relationships between activities.

A dependency pertains to the sequencing of project activities or tasks.

True

Network diagrams are the preferred technique for showing activity sequencing.

True

To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.

True

In project schedule management, what is the next step after defining project activities?

determining their dependencies

In project schedule management, the ultimate goal of which process is to provide a basis for monitoring project progress for the time dimension of the project?

developing a schedule

In project schedule management, which is an output of controlling the schedule?

project management plan update

In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?

sequencing activities

During which relationship is the "from" activity unable start until the "to" activity is started?

start -to-start

Which statement best describes the difference between an activity list and an activity attribute?

An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is not.

Which is a similarity between scope control and schedule control?

Both are portions of the integrated change control process under project integration management.

In an AOA network diagram, what occurs when two or more activities follow a single node?

Bursts

Which technique is used for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?

Crashing

Which technique involves network diagramming and is used primarily to predict total project duration?

Critical path analysis

What term is used for the amount of time an activity can be delayed without delaying the early start date of any immediately following activities?

Free slack

Which provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format?

Gnatt charts

Which is a similarity between the crashing and fast tracking?

both can shorten the time needed to finish a project


Related study sets

70-410 Test Bank, Lesson 10, Configuring IPv4 and IPv6 Addressing

View Set

Foundations -- Module 15: Health, Wellness, and Disparities

View Set

Covenants of General Warranty Deed

View Set

A Taste Of Honey - Key Quotes: Jo and Jimmie

View Set

Module 4: Skeletal Muscle Structure, Function, and Control

View Set

Quiz: Administering Oral Medications

View Set

Private Pilot Study Unit 3: Airports, Air Traffic Control, and Airspace

View Set