CNST 201 FINAL

Ace your homework & exams now with Quizwiz!

Most contracts require a warranty period of _____ year (s) from substantial completion.

1

Most contracts require a warranty period of______years from substantial completion.

1 year

What does Comprehensive General Liability insurance protect the General Contractor from?

3rd party lawsuits

Which AIA document outline the agreement between Owner and Contractor?

A101

Which AIA document outlines the process for handling disputes?

A201

Which AIA document outlines the rights and responsibilities of owner, contractor, and architect? Known as the General Conditions.

A201

Which of the following is a submittal?

All of the above

All warranties need to: (select those that apply)

All of them

The general contractor needs to organize a responsive warranty service that: (select all that apply)

All of them

The job specifications state that the contractor warrants or guarantees that: (select all that apply)

All of them

What does the acronym AIA stand for?

American Institute for Architecture

Which of the following is not modified by a change order?

Building Codes

What type of Lien does the following statement represent? Accompanies each request for payment, releases lien rights for the amount of the payment.

Conditional lien waiver

What type of Payment Request does the following statements represent? Request made on actual expenses, Invoices and payroll reports are submitted with request, fee and lump sum are billed based on schedule of values and percent complete, owner may audit

Cost - plus and Guaranty maximum price

Which of the following guarantee is NOT a bond a surety would provide to the obligee?

Duration bond

Which of the following parties is NOT a party in a surety arrangement?

Executor

90% of the items on a Punch List must be corrected before the project is considered complete.

FALSE

Certificate of Occupancy is issued by the architect and indicates the project can be used for its intended purpose but there might be minor deficiencies

FALSE

Construction Change Directives are preferred over Construction Change Orders because they allow the contractor to determine the cost, scope, and time associated with a change after the change is make. Both parties are bound by the Change Directive.

FALSE

Historically too much emphasis has been put on overall value of the project not the price.

FALSE

If some aspect of the work is inadvertently omitted, the subcontractor is still responsible for Ensuring that the GENERAL CONTRACT requirements are achieved.

FALSE

If the project is occupied by the owner prior to substantial completion, the warranty period will still start upon final completion.

FALSE

In order to receive the best price from a subcontractor a general contractor should bid shop or share the quotation from the lowest bedder to the other subcontractors in hope they will lower their price.

FALSE

Liens are highly encouraged in construction.

FALSE

Most Change orders are due to poor design and owner-directed scope changes.

FALSE

The less documents that are received back from an owner or architect with an approval signature and stamp on them, the better off the subcontractors and suppliers are.

FALSE

Type of Lien release provided at job close out, also releases retention.

Final Lien Release

Which of the following is not a close-out process?

Notice to proceed

Another name for Wrap-up insurance is?

Owner-controlled Insurance program

The practice of disclosing the details of one subcontractors proposal or quotation to another subcontractor to gain a price advantage is known as?

bid shopping

What type of Lien does the following statement represent?

conditional lien wavier

A worker can forgo a workers' compensation claim and bring suit against the company under what law?

law of negligence

Select the two coverage types of Comprehensive General Liability Insurance.

occurrence-based Claim-based

How many different AIA documents are available?

over 200

Who is the Obligee in a surety agreement for the primary contract on a project?

owner

When an owner holds back a portion of the monthly payment to assure the contractor and subcontractors stay focused on completing the project; this is called

retainage

An agreed upon breakdown of the contract cost that is usually required to be submitted after the execution of the contract, and after subcontractors have been bought out is called?

schedule of values

Which of the following is NOT an advantage in subcontracting work?

scheduling

The Maximum amount of bonds the surety will issue at a given point in time is?

the difference between the principals bonding capacity and the total of the contractor's ongoing work.

A Lien is a legal right to secure payment for work performed and materials provided in the improvement of land.

TRUE

Adverse weather may be grounds for initiating a change order.

TRUE

Certificate of occupancy can take up to one year to receive.

TRUE

If a contractor fails to pay a subcontractor, a last recourse for the subcontractor is to file a lien against the owner of the project.

TRUE

Submittal requirements for a project are contained in the specifications of the contract.

TRUE

Submittals are one of the final design steps and also one of the first steps in quality control.

TRUE

The construction team must submit everything that the specifications require as a minimum.

TRUE

The general contractor must provide adequate notice to each subcontractor regarding the planned start date and the scheduled completion date for his or her phase of the work.

TRUE

Type of Lien release required on final payment to a subcontractor or supplier.

Unconditional Lien

Which of the following are challenges of subcontractor management? (select all that apply)

all but specialized skills

Unrealistically low or high quotations generally indicate that the subcontractor...

all of the above

Efficient subcontractor management by the general contractor is critical to ensure the project is completed... (select all that apply)

all of them

Which of the following is not true about the change order process?

any owner initiated change order must be accepted by the contractor, if a conflict arises the change order becomes a dispute and the contractor can use the dispute resolution outlined in the contract to resolve the issue.

Workers' compensation insurance is based on a percentage of the workers average wages. Typically at what percent?

75%

A typical General Contractor subcontracts _____ % to _____ % of the project scope of work?

75% to 85%


Related study sets

Physics Conceptual Questions Exam 3

View Set

Networking Essentials - Chapter 2 Exam

View Set

Supply Chain Quiz Questions- Exam 2

View Set

Section 7: Executives - quiz questions

View Set

Chapter 18: Control of Gene Expression in Bacteria

View Set

Pedi Success - Cumulative Questions

View Set

Bio Tech Exam 2 (copy; not official)

View Set

Prep U Chapter 34: Assessment and Management of Patients with Inflammatory Rheumatic Disorders

View Set

IS Data Structures & Java 4415 Quiz 2

View Set