Which of the following are benefits of submitting a formal request for information? (Select all that apply.)

A. Document project questions B. Document the outcome of communication D. Gaining necessary clarity

Project costs that are not related to material include ? . (Select all that apply.)

A. direct job expenses B. fuel costs C. overhead

The entire process of planning an estimate requires the estimator to have as much ? as possible about the final building and the steps required to reach the completed project. (Select all that apply.)

a. clarity b. detail

The primary part(s) of a takeoff are ? . (Select all that apply.)

a. the things that are counted b. the things that are measured

Which of the following is/are a way to classify a construction project and should be considered when preparing a project estimate?

c. Both a. and b.

The type of project does not matter when creating an estimate

False

A standardized takeoff process makes it easy for? to look at a project.

E. a., b., and c.

Estimate the amount of non-metallic sheathed cable that will be required for circuit 14(RP-B) (excluding the amount required for the home run at the specified box).Use the vertical dimensions below to aid in your estimate:Box to ceiling space: 86"Horizontal Distance from the center of the wall to the location that the cable passes through the ceiling joists: 6"Box to horizontal holes in stud: 18" (Although the question allows for some tolerance, it is important to be as accurate as possible because even minor errors when carried across the entire project will be impactful on the final bid.)

88ft 2.25in

Drag and drop the parts needed to create the assembly (the part shown on the print) that can be used to estimate all similar symbols. (Note that wire connectors are not needed inside the fixtures as the fixtures come with quick connect connection points pre-installed (id:140756)

1-1 2-1 3-8 4-2 5-1 6-2 8-8 9-4

Given the estimated costs, along with the overhead and desired profit, what is the amount of the final bid? (id:131595)

16987.5

Estimate the total amount of straight lengths of cable tray needed for the third floor of the building.

220ft 10 3/4in

How much labor should be estimated to install the conduit shown on the pricing sheet? (Round the FINAL answer to two decimal places.) (id:138380)

223.17 hours 31.74 hours 6.12 hours 11.04 hours 5.69 hours 11.37 hours 289.13 hours

How much labor should be estimated to install the conduit shown on the pricing sheet? (ID: 132167)

25.96 2.64 1.04 6.36 0.67 36.67

Given the estimated costs, along with the overhead and desired profit, what is the amount of the final bid? (id:131594)

33697

Estimate the 4" PVC and associated fittings needed to run the 4" conduit that feeds DP-G using standard PVC, which comes with a bell end coupling on each stick, and factory bends that do not come with an integral bell end fitting.

4" PVC Conduit: 40ft 4" PVC Coupling: 4 4" PVC Connector: 1 4" PVC 45° elbow: 1 4" PVC 90° elbow: 1

what are the two major groupings for construction material on a takeoff?

B. Commodities D. Systems or Packages

the accuracy of a takeoff is not a critical part of the success of a construction project

B. False

The two major parts of a takeoff are ? and ? . (Choose two.)

B. counting C. measuring

The project contract often includes line items describing the extent of each trade's responsibility, or ? .

D. scope of work

A(n) ? is the process of enumerating a project's component parts so that required material can be aggregated into a total amount of material and a total cost.

D. takeoff

Drag and drop the expenses into the appropriate category. (id:DL02025)

Direct Expenses: Backhoe Rental Clean up PPE Submittals

Given the estimated costs, along with the overhead and desired profit, what is the amount of the final bid? (id:138381)

Scenario #1: 107613 Scenario #2: 104352 Scenario #3: 104352


Related study sets

Author's Purpose/Modes of Writing Language Arts 700

View Set

I.S Chapter 9 Systems Development and Project Management: Corporate Responsibility

View Set

Unit Circle Inverse Functions- Trigonometric functions (Sin, Cos, Tan)

View Set

Intro to Networks, Chapter 3, Network Protocols and Communications

View Set

Aerospace & Aviation Ch. 2 Study Set

View Set