What is the recommended size for a Development Team (within the Scrum Team)?
3-9
Before a story can be included in a sprint plan, it needs to contain?
Acceptance criteria for completion
Which are Scrum Events?
All of the above (Daily Scrum, Scrum Planning, Product Review + Retrospective)
Stories in Scrum take the form of?
As a ___ I want to do ___ because ___
How much work must a Dev Team do to a Product Backlog item it selects for a Sprint?
As much as needed to meet Definition of Done
Progress in a scrum project can be represented, and projected using a?
Burndown chart
Which two (2) things does the Development Team do during the first Sprint?
Develop and deliver at least one piece of functionality
Who creates an Increment?
Development Team
Who is responsible for decomposing a story into tasks for the current sprint?
Development Team
Who is responsible for managing the progress of work during a Sprint?
Development Team
Who is on the Scrum Team?
Development Team, Product Owner, Scrum Master
Who should be able to view the product backlog?
Everyone
Development Team membership should change?
If needed, but productivity will drop as new members adjust.
The CEO asks for an important item be added to the current sprint. What should the Dev Team do?
Inform the Product Owner so he/she can work with the CEO.
What part of the capacity of the Dev Team does Product Backlog refinement usually consume?
No more than 10%
Which statement best describes a Product Owner's responsibility?
Optimizing the value of the work the Development Team does.
Who is involved in story sizing?
P.O. & Dev Team with Scrum Master Guidance
Who has the final say on the order of the Product Backlog?
Product Owner
Who should know the most about the progress toward a business objective or a release?
Product Owner
Who takes the lead on grooming the product backlog?
Product Owner
Which of the following happens at the sprint demo?
Product Owner collects feedback from stakeholders | Dev Team demos the new increment
Who is allowed to make changes in the Product Backlog?
Product Owner, and The Dev Team with P.O. permission
Which of the following is not a principle of the agile manifesto?
Rigid design documents are critical to any successful build
Large, complex, long-term projects are better suited for which methodology?
Scrum
Trello can be used as an online version of which resource?
Scrum Board
The Scrum Master is a?
Servant-Leader
The unit used to estimate the size of a story is known as a?
Story Point
A story point usually represents?
The time it takes to complete the smallest story identified
No one may tell the Dev Team how to create increments of potentially releasable functionality?
True
Scrum does not have a role called "Project Manager"?
True
The Development Team may work with the Product Owner to remove or add work during sprint?
True
The Product Owner can help clarify or optimize the Sprint when asked by the Development Team?
True
The Sprint Backlog changes and may grow as the work emerges?
True
The purpose of a Sprint is to produce a done increment of working product?
True
Short, clearly defined, and stable projects are better suited for which methodology?
Waterfall
The Gantt chart is a common artifact of which development methodology?
Waterfall
The Product Backlog is ordered by?
Whatever is deemed most appropriate by the Product Owner.
Which statement describes the Sprint Review process?
When scrum team + stakeholders inspect sprint outcome.
When is a Sprint over?
When the time-box expires.
The Dev Team takes on as many stories in a sprint as?
Will fit into their fixed allocation of development time