HW 4 Bidding and Contract Documents 2
Identify the correct pairing of the most common procurement method and selection criteria. A. Design-Bid-Build and qualifications based selection B. Design bid build and low bid selection C. design build and qualifications and prose selection D. design build and low bid selection
B.
Which document is submitted to the owner for bid consideration before the contractor can receive the bidding documents? A. Instructions to bidders B. Pre qualification forms C. Noncollusive affidavit D. Proposal Supplements
B.
Which document applies to the contractor and the subcontractors and describes the administrative, procedural and temporary procedures on the job site? A. Instructions to bidders B. Supplementary conditions C. General Conditions D. General Requirements
D.
Which document describes the duties and responsibilities of each party and the business procedures for administering the contract? A. General Requirements B. Supplementary conditions C. Instructions to bidders D. General Conditions
D.
Which document makes changes, modifications, and corrections prior to bid opening? A. Proposal supplements B. Change Directive C. Contract Change Order D. Addenda
D.
Bidders try to bid every job that they see advertised in order to maximize the number of hits. T/F
F
A bidder cannot withdraw or revise a proposal after it has been deposited with the owner, provided the request for such withdrawal or revision is received by the owner, in writing, before the time set for opening of proposals. T/F
False
AIA 201 is the standard form of agreement between the owner and architect. T/F
False
The GC goes through the post qualification process after the job is completed. T/F
False
Failure of the bidder to satisfy the participation goal for minority business enterprises among the subcontractors is considered irregular or nonresponsive. T/F
True
Which document establishes the forms, content and procedures for submitting the bid proposals? A. General Requirements B. Supplementary conditions C. Instructions to bidders D. General Conditions