IS 438: Practice Exam 1 - True/False

Ace your homework & exams now with Quizwiz!

The ROI (return on investment) is always positive

False

The scope baseline in a WBDS consists of the requirements documentation and enterprise environmental factors

False

When deciding on which projects to invest in or continue, one should include sunk costs?

False

the tasks in a WBDS structure must be developed as a sequential list of steps

False

Leadership style has no impact on the success of virtual teams

False!

The burndown chart is a scrum created artifact that provides a list of features prioritized by business value.

False!

The enterprise project management software, which aids project and portfolio management, is a low end tool.

False!

The team members of a virtual team are all of the same nationality

False!

When you separate business from organizational issues from project management planning, you do a better job at ensuring project success.

False!

A cost management plan can include organizational procedure links, control thresholds, and process descriptions

True

The project scope statement, stakeholder requirements documentation, organizational process assets are the primary inputs for creating a WBDS

True

Definitive estimates are made one year or less prior to project completion

True!

Identifying the project sponsor is a pre-initiation task

True!

Initiating processes take place during each phase of the project

True!

Project human resource management is concerned with making effective use of people involved with a project.

True!


Related study sets

Simulate Exam Part 1 (Law), Simulate Exam Part 2 (Law)

View Set

Geometry - Using Deductive Reasoning

View Set

Module 2: Chapters 4 & 5 Eukaryotic Cells and Viruses Quiz

View Set

Quantitative - Test #1 (Non-Math Q's)

View Set