planning charts used to schedule resources and allocate time.

Gantt charts are A. not easy to understand. B. not widely used. C. planning charts used to schedule resources and allocate time. D. widely used network techniques.

ES​ + Activity time

How is the EF​ computed? A. Min{LS of all immediate following​ activities} B. LF minus−Activity time C. ES​ + Activity time D. Max{EF of all immediate​ predecessors}

6,900

How many births was Arnold Palmer designed to handle per​ year? A. 6,900 B. 5,000 C. 18,000 D. 52,000

longest time path through the network.

The critical path of a network is the A. shortest time path through the network. B. longest time path through the network. C. path with the most activities. D. path with the fewest activities.

most likely time

The most realistic estimate of the time required to complete an activity is referred to as​ what? A. most likely time B. optimistic time C. slack time D. pessimistic time

​planning, scheduling, and controlling.

The three phases involved in the management of large projects are A. planning, scheduling, and evaluating. B. ​planning, scheduling, and controlling. C. scheduling, designing, and operating. D. scheduling, operating, and evaluating.

35

To aid development of the hospital​ design, how many user groups did the hospital start​ with? A. 35 B. 10 C. 1,000 D. 100

MS Project

What Operation Management tools were used extensively in building Arnold Palmer​ Hospital? A. Queuing theory B. Arena C. CPM D. MS Project E. Linear programming

MS Project

What Project Management software did Arnold Palmer​ utilize? A. Harvard Project Manager B. Timeline C. MS Project D. PERT Master

crash time

What is the shortest duration required to complete an​ activity? A. crash time B. most likely time C. pessimistic time D. optimistic time

Building of the hospital itself.

What is the top level of the Work Breakdown Structure for new construction​ projects? A. Breaking ground. B. Building of the hospital itself. C. Subtasks. D. Major tasks.

Managers only need to closely monitor the critical path.

Which of the following is NOT true regarding PERT and​ CPM? A. Managers only need to closely monitor the critical path. B. PERT and CPM are useful in monitoring costs. C. PERT and CPM are useful when controlling large projects. D. Time estimates are subject to fudging by managers.

making sure that the people assigned to the project receive the​ motivation, direction, and information needed to do their jobs

Which of the following is a direct responsibility of the project​ manager? A. drawing the network diagram B. performing all of the activities in the project C. making sure that the people assigned to the project receive the​ motivation, direction, and information needed to do their jobs D. calculating completion probabilities for all tasks in the project

standard time

Which of these time estimates is NOT used in​ PERT? A. standard time B. most likely time C. optimistic time D. pessimistic time

is the amount of time a task may be delayed without changing the overall project completion time.

With respect to PERT and​ CPM, slack A. is the latest time an activity can be started without delaying the entire project. B. is a task or subproject that must be completed. C. marks the start or completion of a task. D. is the amount of time a task may be delayed without changing the overall project completion time.


Related study sets

PEDS Chapter 23: Nursing Care of the Child With an Alteration in Tissue Integrity/Integumentary Disorder

View Set

Chapter 25. The Digestive System

View Set

CFP Retirement Planning - Lesson #3 - Administration of Qualified Plans

View Set

What is the capital city of Rwanda

View Set

Drivers ED " Texas Teen Drivers" Lesson 2-8

View Set

Chpt 24- Personality disorder and impulsivity

View Set

Cognitive ch. 5, 6, 7, & 8 quizzes

View Set

BIO 2K17 UNIT 2: FEMALE REPRODUCTIVE SYSTEM /Ovarian Cycle

View Set