PMP 5th - Chapter 6 - Project Time Management

Ace your homework & exams now with Quizwiz!

Critical Path Method (CPM)

- A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. - Calculates the theoretical early start and finish dates, and late start and finish dates, for all activities without regard for any resource limitations, by performing a forward and backward pass analysis through the schedule network. - The resulting early and late start and finish dates are not necessarily the project schedule; rather, they indicate the time periods within which the activity could be scheduled, given activity durations, logical relationships, leads, lags, and other known constraints.

Characteristics of Parametric Estimating

- Can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model. - Can be applied to a total project or to segments of a project, in conjunction with other estimating methods.

Project Management Plan

- Contains the schedule management plan and the schedule baseline. - The schedule management plan describes how the schedule will be managed and controlled. - The schedule baseline is used to compare with actual results to determine if a chance, corrective action, or preventative action is necessary.

Discretionary Dependencies

- Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. - Also sometimes referred to as preferred logic, preferential logic, or soft logic.

Expert judgment

- Guided by historical information, provides valuable insight about the environment and information from prior similar projects.

Activity Resource Requirements

- Identifies the types and quantities of resources required for each activity in a work package. - These requirements can then be aggregated to determine the estimated resources for each work package and work period. - The amount of detail and the level of specificity of the resource requirement descriptions can vary by application area.

Outputs (3) of the Define Activities process

1 Activity list 2 Activity attributes 3 Milestone list

Inputs (13) of the Develop Schedule process

1 Schedule management plan 2 Activity list 3 Activity attributes 4 Project schedule network diagrams 5 Activity resource requirements 6 Resource calendars 7 Activity duration estimates 8 Project scope statement 9 Risk register 10 Project staff assignments 11 Resource breakdown structure 12 Enterprise environmental factors 13 Organizational process assets

Inputs (8) of the Estimate Activity Resources process

1 Schedule management plan 2 Activity list 3 Activity attributes 4 Resource calendars 5 Risk register 6 Activity cost estimates 7 Enterprise environmental factors 8 Organizational process assets

Rolling Wave Planning

A form of progressive elaboration (iterative) planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS.

AON

Activity-On-Node.

produce network paths with a zero or positive total float

Adjustments to activity durations, logical relationships, leads and lags, or other schedule constraints.

Lead

Allows an acceleration of the successor activity

Scheduling Tool

Automated scheduling tools expedite the scheduling process by generating start and finish dates based on the inputs of activities, network diagrams, resources and activity durations. A scheduling tool can be used in conjunction with other project management software applications as well as manual methods.

Zero Total Float

Critical Path

CPM

Critical Path Methodology

Schedule Management Plan

Defines the method used and the level of accuracy along with other criteria required to estimate activity duration including the project update cycle.

Scheduling Methodology

Defines the rules and approaches for the scheduling process. Some of the better known methodologies include: - Critical path method (CPM) - Critical chain

Project charter

Defines the summary milestone schedule and project approval requirements that will influence the management of the project schedule.

Process descriptions

Descriptions of each of the schedule management processes are documented.

Lag

Directs a delay in the successor activity

EVM

Earned Value Management

Project Management Plan Updates

Elements can be updated: - Schedule baseline - Schedule management plan - Cost baseline

Project Management Plan Updates

Elements of the project management plan that may be updated: - Schedule baseline - Schedule management plan

Organizational process assets

Factors can be influence: project files from the corporate knowledge base used for scheduling methodology, existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling methodology that are considered in developing logical relationships, and templates that can be used to expedite the preparation of networks of project activities. Related activity attributes information in templates can also contain additional descriptive information useful in sequencing activities.

Enterprise Environmental Factors

Factors can influence: resource location, availability, and skills.

Milestone List

Identifies all milestones and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based upon historical information.

Activity List

Identifies the activities that will be included in the schedule model.

Activity list

Identifies the activities that will need duration estimates.

Activity list

Identifies the activities which will need resources.

Schedule management plan

Identifies the level of accuracy and the units of measure for the resources to be estimated.

Schedule management plan

Identifies the scheduling method and tool to be used for the project, which will guide how the activities may be sequenced.

Schedule management plan

Identifies the scheduling method and tool used to create the schedule, and how the schedule is to be calculated.

Internal Dependencies

Internal dependencies involve a precedence relationship between project activities and are generally inside the project team's control.

Simulation

Involves calculating multiple project durations with different sets of activity assumptions.

Examples of Mandatory Dependencies

Mandatory dependencies often involve physical limitations: - construction project where it is impossible to erect the superstructure until after the foundation has been built; - an electronics project, where a prototype must be built before it can be tested.

Alternative Analysis

Many schedule activities have alternative methods of accomplishment. They include using various levels of resource capability or skills, different size or type of machines, different tools (hand versus automated), and makerent-or-buy decisions regarding the resource.

Schedule Management Plan

May be updated to reflect a change in the way the schedule is managed.

Cost Baseline

May be updated to reflect changes caused by compression or crashing techniques.

Risk Register

May need to be updated to reflect opportunities or threats perceived through scheduling assumptions.

Performance Reviews

Measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress.

Control Schedule

Monitoring and Controlling Process Group

Networks are going to have multiple...

Near critical paths

Schedule Data

New project schedule network diagrams may be developed to display approved remaining durations and modifications to the work plan. In some cases, project schedule delays can be so severe that development of a new target schedule with forecasted start and finish dates is needed to provide realistic data for directing the work, and for measuring performance and progress.

Expert Judgement

Often required to assess the resource-related inputs to this process. Any group or person with specialized knowledge in resource planning and estimating can provide such expertise.

Project Document Updates

Project documents can be uptaded: - Schedule data - Project schedule - Risk Register

Resource Breakdown Structure

Provides a hierarchical structure of the identified resources by resource category and resource type.

Resource Breakdown Structure

Provides the details by which resource analysis and organizational reporting can be done.

Risk Register

Provides the details of all identified risks and their characteristics that affect the schedule model.

Activity Attributes

Provides the primary data input for use in estimating those resources required for each activity.

Schedule Model

Representation of the plan for executing the project's activities including durations, dependencies, and other planning information, used to produce project schedules along with other scheduling artifacts.

SPI

Schedule Performance Index

SV

Schedule Variance

Published Estimating Data

Several companies routinely publish updated production rates and unit costs of resources for an extensive array of labor trades, material, and equipment for different countries and geographical locations within countries.

PERT: Optimistic Estimate

The activity duration is based on analysis of the best-case scenario for the activity.

PERT: Pessimistic Estimate

The activity duration is based on analysis of the worst-case scenario for the activity.

Work performance information

The calculated SV and SPI values for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders.

Activity Cost Estimates

The cost of resources may impact resource selection.

PERT: Most Likely Estimate

The duration of the activity, given the resources likely to be assigned, their productivity, realistic expectations of availability for the activity, dependencies on other participants, and interruptions.

Reporting formats

The formats and frequency for the various schedule reports are defined.

Scope Baseline

The project deliverables, constraints, and assumptions documented in the project scope baseline are considered explicitly while defining activities.

Negative Critical Path

The project float compares the critical path with an externally imposed date and may be negative. You may be forced to fast track or perform crashing to ensure that the project is completed on time as required by the management. There will be no change to the critical path.

Schedule data

Will be reviewed and updated in the Control Schedule process.

Slack for tasks on the critical path

is equal to zero

Examples of Resource Categories

labor, material, equipment, and supplies

Examples of Resource Types

skill level, grade level or other information as appropriate to the project

The more critical paths

the more project risk

All baselines and plans are a part of

the project management plan

Enterprise environmental factors

• Government or industry standards, • Project management information system (PMIS), • Scheduling tool, • Company work authorization systems.

Milestone

- A significant point or event in the project. -They have zero duration because milestones represent a moment in time.

Schedule Management Plan

- A subsidiary plan of, and component of the project management plan through the Develop Project Management Plan process; - Identifies a scheduling method and scheduling tool; - Sets the format and establishes criteria for developing and controlling the project schedule; - May be formal or informal, highly detailed or broadly framed, based upon the needs of the project, and includes appropriate control thresholds; - Defines how schedule contingencies will be reported and assessed; - may be updated to reflect a change in the way the schedule is managed;

Resource Smoothing

- A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. - Opposite the technique resource leveling. - The project's critical path is not changed and the completion date may not be delayed. In other words, activities may only be delayed within their free and total float. - May not be able to optimize all resources.

Bottom Up Estimating Activity Dependencies

- Activities may or may not have dependencies between them that can affect the application and use of resources. - If there are dependencies, this pattern of resource usage is reflected and documented in the estimated requirements of the activity.

Project Document Updates

- Activity attributes - Assumptions made in developing the activity duration estimate such as skill levels and availability

Project Document Updates

- Activity list - Activity attributes - Resource calendars

Precedence Diagramming Method (PDM)

- Also referred to as Activity-On-Node (AON) - A method used in Critical Path Methodology (CPM) for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities, and connects them with arrows that show the logical relationships that exist between them. - The method used by most project management software packages.

Characteristics of Contingency Reserves

- As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. - Contingency should be clearly identified in schedule documentation.

Graphical Formats of the Project Schedule

- Bar charts - Milestone charts - Project schedule network diagrams

Characteristics of Resource Leveling

- Can be used when shared or critical required resources are only available at certain times, are only available in limited quantities, or to keep resource usage at a constant level. - Is necessary when resources have been over-allocated, when shared or critical required resources are only available at certain times or are only available in limited quantities. - Can often cause the original critical path to change.

Project management plan

- Contains information used to develop the schedule management plan which includes: - scope baseline => includes the project scope statement and the work breakdown structure (WBS) details used for defining activities, duration estimation, and schedule management; - Other information => Other scheduling related cost, risk, and communications decisions from the project management plan are used to develop the schedule.

Schedule Compression Techniques

- Crashing - Fast-tracking

Purpose of Control Schedule

- Determining the current status of the project schedule. - Influencing the factors that create schedule changes. - Determining that the project schedule has changed. - Managing the actual changes as they occur.

Fast Tracking and Discretionary Dependencies

- Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. - When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal.

Earned Value Management (EVM)

- Earned Value Management utilized the schedule variance(SV) and schedule performance index (SPI). - An important part of schedule control is to decide if the schedule variation requires corrective action.

Characteristics of Develop Schedule

- Entering the activities, durations, and resources into the scheduling tool generates a schedule with planned dates for completing project activities. - It determines the planned start and finish dates for project activities and milestones. - Developing an acceptable project schedule is often an iterative process. - Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to track progress. - Revising and maintaining a realistic schedule continues throughout the project as work progresses, the project management plan changes, and the nature of risk events evolves.

Risk Register

- Events may impact resource selection and availability. - Updates to the risk register are included with project documents updates.

Characteristics of Sequence Activities

- Every activity and milestone except the first and last are connected to at least one predecessor and one successor. - It may be necessary to use lead or lag time between activities to support a realistic and achievable project schedule. - Sequencing can be performed by using project management software or by using manual or automated techniques.

Organizational Process Assets

- Existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling methodology, that are considered in developing the activity definitions. - Lessons-learned knowledge base containing historical information regarding activities lists used by previous similar projects.

Organizational Process Assets

- Existing formal and informal schedule control-related policies, procedures and guidelines - Schedule control tools - Monitoring and reporting methods to be used

Precedence Diagramming Method (PDM) Relationship Types

- Finish-to-start (FS). - Finish-to-finish (FF). - Start-to-start (SS). - Start-to-finish (SF).

Expert Judgement

- Guided by historical information, can provide duration estimate information or recommended maximum activity durations from prior similar projects. - Can also be used to determine whether to combine methods of estimating and how to reconcile differences between them.

Project calendars

- Identifies working days and shifts that are available for scheduled activities - It distinguishes time periods in days or parts of days that are available to complete scheduled activities from time periods that are not available. A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the project schedule. -The project calendars may be updated.

Activity attributes can be used to

- Identify the person responsible for executing the work, - geographic area, or - place where the work has to be performed, and - activity type such as level of effort (LOE), discrete effort, and apportioned effort (AE).

Characteristics of Project Schedule

- If resource planning is done at an early stage, then the project schedule would remain preliminary until resource assignments have been confirmed and scheduled start and finish dates are established. - This process usually happens no later than completion of the project management plan. - A project target schedule may also be developed with a defined target start and target finish for each activity. - The project schedule may be presented in summary form, sometimes referred to as the master schedule or milestone schedule, or presented in detail. - Although a project schedule can be presented in tabular form, it is more often presented graphically.

Work performance data

- Information about project progress, such as which activities have started, their progress, and which activities have finished.

Determining the Critical Chain

- Initially, the project schedule network diagram is built using duration estimates with required dependencies and defined constraints as inputs. - The critical path is then calculated. - After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. - The resulting schedule often has an altered critical path.

Decomposition

- Involves subdividing the project work packages into smaller, more manageable components called activities. - Activities represent the effort needed to complete a work package. - The Define Activities process defines the final outputs as activities rather than deliverables, as done in the Create WBS process. - The activity list, WBS, and WBS dictionary can be developed either sequentially or concurrently, with the WBS and WBS dictionary as the basis for development of the final activity list. - Each work package within the WBS is decomposed into the activities required to produce the work package deliverables. - Involving team members in the decomposition can lead to better and more accurate results.

Components of a Project Schedule Network Diagram

- It can include full project details, or have one or more summary activities. - A summary narrative can accompany the diagram and describe the basic approach used to sequence the activities. - Any unusual activity sequences within the network should be fully described within the narrative.

Project Schedule Network Diagram

- It is a graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities. - The project schedule network diagram can be produced manually or by using project management software.

Bottom Up Estimating

- It is a method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS. - When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail. - The resource needs are estimated. - These estimates are then aggregated into a total quantity for each of the activity's resources.

Dependency Determination

- Mandatory dependencies - Discretionary dependencies - External dependencies - Internal dependencies

Mandatory Dependencies

- Mandatory dependencies are those that are contractually required or inherent in the nature of the work. - Also sometimes referred to as hard logic or hard dependencies.

PERT Estimate Types

- Most Likely - Optimistic - Pessimistic

Duration Buffers

- Non-work schedule activities to manage uncertainty. - The size of each buffer should account for the uncertainty in the duration of the chain of dependent tasks leading up to that buffer. - Once the buffer schedule activities are determined, the planned activities are scheduled to their latest possible planned start and finish dates.

Risk Register

- Provides the list of risks, along with the results of risk analysis and risk response planning. - Updates to the risk register are included with project document updates.

Leads and Lags

- Refinements applied during network analysis to develop a valid schedule. - Leads are used in limited circumstances to advance a successor activity with respect to the predecessor activity. - Lags are used in limited circumstances where processes require a set period of time to elapse between the predecessors and successors without work or resource impact..

Scheduling Tool

- Schedule data is updated and compiled into the schedule to reflect actual progress of the project and remaining work to be completed. - The scheduling tool and the supporting schedule data are used in conjunction with manual methods or other project management software to perform schedule network analysis to generate an updated project schedule.

Variance Analysis

- Schedule performance measurements (SV - schedule variance, SPI - schedule performance inde) are used to assess the magnitude of variation to the original schedule baseline. - The total float variance is also an essential planning component to evaluate project time performance. - Important aspects of project schedule control include determining the cause and degree of variance relative to the schedule Baseline and deciding whether corrective or preventive action is required.

Change Requests

- Schedule variance analysis, along with review of progress reports, results of performance measures, and modifications to the project schedule can result in change requests to the schedule baseline and/or to other components of the project management plan. - Change requests are processed for review and disposition through the Perform Integrated Change Control process. - Preventive actions may include recommended changes to reduce the probability of negative schedule variances.

Duration of a Project

- Should be calculated after drawing a network diagram and determining the critical path. - The length of the critical path and not the sum of the duration of all the tasks in the project.

Group decision-making techniques

- Team-based approaches: - brainstorming - the Delphi or nominal group techniques, are useful for engaging team members to improve estimate accuracy and commitment to the emerging estimates. - Involving a structured group of people who are close to the technical execution of work in the estimation process, additional information is gained and more accurate estimates obtained. - People are involved in the estimation process, their commitment towards meeting the resulting estimates increases.

Analogous Estimating

- Technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. - Uses parameters such as duration, budget, size, weight, and complexity, from a previous, similar project, as the basis for estimating the same parameter or measure for a future project.

Project Scope Statement

- The constraints and assumptions from the project scope statement are considered when estimating the activity duration. -Examples of the Assumptions: - Existing conditions, - Availability of information, and - Length of the reporting periods Examples of the Constraints: - Available skilled resources, and - Contract terms and requirements

Project Schedule

- The most recent version of the project schedule with notations to indicate updates, completed activities, and started activities as of the indicated data date.

Analytical techniques

- The process involve strategic options to estimate and schedule the project such as: scheduling methodology, scheduling tools and techniques, estimating approaches, formats, and project management software. Examples: - rolling wave planning - leads and lags - alternatives analysis - methods for reviewing schedule performance

Process: Develop Schedule

- The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. - The key benefit of this process is that by entering schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool, it generates a schedule model with planned dates for completing project activities.

Process: Estimate Activity Durations

- The process of approximating the number of work periods needed to complete individual activities with estimated resources. - The key benefit of this process is that it provides the amount of time each activity will take to complete.

Process: Plan Schedule Management

- The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. - The benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project.

Process: Estimate Activity Resources

- The process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. - The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates.

Process: Sequence Activities

- The process of identifying and documenting relationships among the project activities - The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.

Process: Define Activities

- The process of identifying the specific actions to be performed to produce the project deliverables. - The key benefit of this process is to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.

Process: Control Schedule

- The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. - The key benefit of this process is that it provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk.

Leads and Lags

- The project management team determines the dependencies that may require a lead or a lag to accurately define the logical relationship. - The use of leads and lags should not replace schedule logic. - Activities and their related assumptions should be documented.

Schedule forecasts

- They are estimates or predictions of conditions and events in the project's future based on information and knowledge available at the time of the forecast. - Forecasts are updated and reissued based on work performance information provided as the project is executed. - The information is based on the project's past performance and expected future performance, and includes earned value performance indicators that could impact the project in the future.

Techniques of Performance Reviews

- Trend analysis - Critical path method - Critical Chain method - Earned Value Management (EVM)

Characteristics of Resource Calendars

- Used for estimating resource utilization. - Resource calendars specify when and how long identified project resources will be available during the project. - This information may be at the activity or project level. - This knowledge includes consideration of attributes such as resource experience and/or skill level, as well as various geographical locations from which the resources originate and when they may be available.

Characteristics of Estimate Activity Durations

- Uses information on activity scope of work, required resource types, estimated resource quantities, and resource calendars. - The inputs for the estimates of activity duration originate from the person or group on the project team who is most familiar with the nature of the work in the specific activity. - The duration estimate is progressively elaborated, and the process considers the quality and availability of the input data. - Requires that the amount of work effort required to complete the activity is estimated and the amount of resources to be applied to complete the activity is estimated; these are used to approximate the number of work periods (activity duration) needed to complete the activity. - All data and assumptions that support duration estimating are documented for each estimate of activity duration.

Characteristics of Analogous Estimating

- When estimating duration, this technique relies on the actual duration of previous, similar projects as the basis for estimating the duration of the current project. - It is a gross value estimating approach, sometimes adjusted for known differences in project complexity. - Frequently used to estimate project duration when there is a limited amount of detailed information about the project. - Uses historical information and expert judgment. - Generally less costly and time consuming than other techniques, but it is also generally less accurate. - Can be applied to a total project or to segments of a project and may be used in conjunction with other estimating methods. - Is most reliable when the previous activities are similar in fact and not just in appearance, and the project team members preparing the estimates have the needed expertise.

Components of Activity Attributes

-The components for each activity evolve over time. - During the initial stages of the project they include the Activity ID, WBS ID, and Activity Name, and when completed may include activity codes, activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.

Outputs (2) of the Estimate Activity Durations process

1 Activity duration estimates 2 Project documents updates

Outputs (3) of the Estimate Activity Resources process

1 Activity resource requirements 2 Resource breakdown structure 3 Project documents updates

Tools & Techniques (3) Define Activities process

1 Decomposition 2 Rolling wave planning 3 Expert judgment

Tools & Techniques (5) Estimate Activity Resources process

1 Expert judgment 2 Alternative analysis 3 Published estimating data 4 Bottom-up estimating 5 Project management software

Tools & Techniques (6) for Estimate Activity Durations process

1 Expert judgment 2 Analogous estimating 3 Parametric estimating 4 Three-point estimating 5 Group decision-making techniques 6 Reserve analysis

Tools & Techniques (3) of the Plan Schedule Management process

1 Expert judgment 2 Analytical techniques 3 Meetings

Tools & Techniques (7) for Control Schedule process

1 Performance reviews 2 Project management software 3 Resource optimization techniques 4 Modeling techniques 5 Leads and lags 6 Schedule compression 7 Scheduling tool

Project Time Management Processes (7)

1 Plan Schedule Management 2 Define Activities 3 Sequence Activities 4 Estimate Activity Resources 5 Estimate Activity Durations 6 Develop Schedule 7 Control Schedule

Tools & Techniques (3) Sequence Activities process

1 Precedence diagramming method (PDM) 2 Dependency determination 3 Leads and lags

Input (4) of the Plan Schedule Management process

1 Project management plan 2 Project charter 3 Enterprise environmental factors 4 Organizational process assets

Inputs (6) of the Control Schedule process

1 Project management plan 2 Project schedule 3 Work performance data 4 Project calendars 5 Schedule data 6 Organizational process assets

Outputs (2) of the Sequence Activities process

1 Project schedule network diagrams 2 Project documents updates

Outputs (6) of the Develop Schedule process

1 Schedule baseline 2 Project schedule 3 Schedule data 4 Project calendars 5 Project management plan updates 6 Project documents updates

Output (1) of the Plan Schedule Management process

1 Schedule management plan

Inputs (10) of the Estimate Activity Durations process

1 Schedule management plan 2 Activity list 3 Activity attributes 4 Activity resource requirements 5 Resource calendars 6 Project scope statement 7 Risk register 8 Resource breakdown structure 9 Enterprise environmental factors 10 Organizational process assets

Inputs (7) of the Sequence Activities process

1 Schedule management plan 2 Activity list 3 Activity attributes 4 Milestone list 5 Project scope statement 6 Enterprise environmental factors 7 Organizational process assets

Inputs (4) of the Define Activities process

1 Schedule management plan 2 Scope baseline 3 Enterprise environmental factors 4 Organizational process assets

Tools & Techniques (8) for Develop Schedule process

1 Schedule network analysis 2 Critical path method 3 Critical chain method 4 Resource optimization techniques 5 Modeling techniques 6 Leads and lags 7 Schedule compression 8 Scheduling tool

Outputs (6) of the Control Schedule process

1 Work performance information 2 Schedule forecasts 3 Change requests 4 Project management plan updates 5 Project documents updates 6 Organizational process assets updates

Schedule management plan

A component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule. The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the needs of the project, and includes appropriate control thresholds.

Activity List

A comprehensive list including all schedule activities required on the project. The activity list includes the activity identifier and a scope of work description for each activity in sufficient detail to ensure that project team members understand what work is required to be completed.

Resource Breakdown Structure

A hierarchical structure of the identified resources by resource category and resource type.

Schedule management plan

A key input from the schedule management plan is the prescribed level of detail necessary to manage the work.

Crashing

A schedule compression technique in which cost and schedule trade offs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost.

Fast Tracking

A schedule compression technique in which phases or activities normally performed in sequence are performed in parallel.

Project calendars

A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the schedule forecasts.

Scheduling Network Analysis

A technique that generates the project schedule model. It employs various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource leveling to calculate the early and late start and finish dates for the uncompleted portions of project activities. Some network paths may have points of path convergence or path divergence that can be identified and used in schedule compression analysis or other analyses.

Activity Attributes

Activity attributes extend the description of the activity by identifying the multiple components associated with each activity.

Feeding Buffer

Additional buffers are placed at each point that a chain of dependent tasks not on the critical chain feeds into the critical chain. Feeding buffers thus protect the critical chain from slippage along the feeding chains.

What-If Scenario Analysis

An analysis of the question "What if the situation represented by scenario 'X' happens?". A schedule network analysis is performed using the schedule to compute the different scenarios.

Project Schedule

An updated project schedule will be generated from the updated schedule data to reflect the schedule changes and manage the project.

Activity Duration Estimates

Are quantitative assessments of the likely number of work periods that will be required to complete an activity. Duration estimates do not include any lags. May include some indication of the range of possible results. For example: - 2 weeks ± 2 days to indicate that the activity will take at least eight days and no more than twelve (assuming a five-day workweek). - 15% probability of exceeding three weeks to indicate a high probability—85% percent—that the activity will take three weeks or less.

Activity Total Float

Calculated early start and finish dates, and late start and finish dates, may be affected by activity total float, which provides schedule flexibility and, may be positive, negative, or zero.

Schedule Baseline

Changes to the schedule baseline are incorporated in response to approved change requests related to project scope changes, activity resources, or activity duration estimates.

Critical Chain method

Comparing the amount of buffer remaining to the amount of buffer needed to protect the delivery date can help determine schedule status. The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate.

Critical path method

Comparing the progress along the critical path can help determine schedule status. The variance on the critical path will have a direct impact on the project end date. Evaluating the progress of activities on near critical paths can identify schedule risk.

The Critical Chain Method focuses on

Consequently, instead of managing the total float of network paths, the critical chain method focuses on managing remaining buffer durations against the remaining durations of task chains.

Resource calendars

Contain information on the availability of resources during the project.

Project Schedule Network Diagrams

Contain the logical relationships of predecessors and successors that will be used to calculate the schedule.

Activity duration estimates

Contain the quantitative assessments of the likely number of work periods that will be required to complete an activity that will be used to calculate the schedule.

Activity list

Contains all schedule activities required on the project, which are to be sequenced. Dependencies and other constraints for these activities can influence the sequencing of the activities.

Project Scope Statement

Contains assumptions and constraints that can impact the development of the project schedule.

Project Scope Statement

Contains the product scope description, which includes product characteristics that may affect activity sequencing, such as the physical layout of a plant to be constructed or subsystem interfaces on a software project. While these effects are often apparent in the activity list, the product scope description is generally reviewed to ensure accuracy.

Activity attributes

Describe a necessary sequence of events or defined predecessor or successor relationships.

Benefit of PERT

Duration estimates based on the PERT equation, or even on a simple average of the three points, may provide more accuracy, and the three points clarify the range of uncertainty of the duration estimates.

Reserve Analysis

Duration estimates may include contingency reserves, (sometimes referred to as time reserves or buffers) into the overall project schedule to account for schedule uncertainty.

Units of measure

Each unit used in measurements (such as staff hours, staff days, or weeks for time measures, or meters, liters, tons, kilometers, or cubic yards for quantity measures) is defined for each of the resources.

Rules of performance measurement

Earned value management (EVM) rules or other physical measurement rules of performance measurement are set. For example, the schedule management plan may specify: ○○ Rules for establishing percent complete, ○○ Control accounts at which management of progress and schedule will be measured, ○○ Earned value measurement techniques (e.g., baselines, fixed-formula, percent complete, etc.) to be employed (for more specific information, refer to the Practice Standard for Earned Value Management) [9], ○○ Schedule performance measurements such as schedule variance (SV) and schedule performance index (SPI) used to assess the magnitude of variation to the original schedule baseline.

Trend analysis

Examines project performance over time to determine whether performance is improving or deteriorating. Graphical analysis techniques are valuable for understanding performance to date and for comparison to future performance goals in the form of completion dates.

Resource optimization techniques

Example of resource optimization techniques that can be used to adjust the schedule model due to demand and supply of resources. Can be: - Resource Leveling - Resource Smoothing

Modeling techniques

Examples of modeling techniques: - What-If Scenario Analysis - Simulation - Monte Carlo analysis

External Dependencies

External dependencies involve a relationship between project activities and non-project activities. These dependencies are usually outside the project team's control.

Organizational Process Assets

Factors can be include: - Scheduling methodology - Project calendar

Entperise Environmental Factors

Factors can be include: - Standards - Communication channels - Scheduling tool to be used in developing the schedule model.

Organizational Process Assets Updates

Factors can be: - Causes of variances, - Corrective action chosen and the reasons, and - Other types of lessons learned from project schedule control

Enterprise Environmental Factors

Factors can influence: - Duration estimating databases and other reference data - Productivity metrics - Published commercial information - Location of team members.

Organizational Process Assets

Factors can influence: - Historical duration information - Project calendars - Scheduling methodology - Lessons learned

Organizational process assets

Factors can influence: - Monitoring and reporting tools to be used; - Historical information; - Schedule control tools; - formal and informal schedule control related policies, procedures, and guidelines; - Templates; - Project closure guidelines; - Change control procedures; - Risk control procedures including risk categories, probability definition and impact, and probability and impact matrix.

Organizational Process Assets

Factors can influence: - Policies and procedures regarding staffing. - Policies and procedures relating to rental and purchase of supplies and equipment. - Historical information regarding types of resources used for similar work on previous project.

FF

Finish-to-finish. The completion of the successor activity depends upon the completion of the predecessor activity.

FS

Finish-to-start. The initiation of the successor activity depends upon the completion of the predecessor activity. The most commonly used type of precedence relationship

Hammock Activity

For control and management communication, the broader, more comprehensive summary activity, is used between milestones or across multiple interdependent work packages, and is displayed in barchart reports.

Resource Requirements Documentation

For each activity, can include the basis of estimate for each resource, as well as the assumptions that were made in determining which types of resources are applied, their availability, and what quantities are used.

Calendar

For each project may use different calendar units as the basis for scheduling the project.

Project management software

Has the capability to help plan, organize, and manage resource pools and develop resource estimates. Depending on the sophistication of the software, resource breakdown structures, resource availability, resource rates and various resource calendars can be defined to assist in optimizing resource utilization.

Critical Path

Have either a zero or negative Total Float

Activity Resource Requirements

Identify the types and quantities of resources required for each activity used to create the schedule model.

Project Schedule

Includes a planned start date and planned finish date for each activity.

Schedule Data

Includes at least the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints.

Composite Resource Calendar

Includes the availability, capabilities, and skills of human resources

Project Time Management

Includes the processes required to manage timely completion of the project.

Enterprise Environmental Factors

Influence the Define Activities process include: - Organizational cultures and structure, - Published commercial information from commercial databases - The project management information system (PMIS)

Enterprise environmental factors

Influence the Plan Schedule Management process include: - Organizational culture and structure can all influence schedule management; - Resource availability and skills that may influence schedule planning; - Project management software provides the scheduling tool and alternative possibilities for managing the schedule; - Published commercial information, such as resource productivity information, is often available from commercial databases that track; - Organizational work authorization systems.

Resource Calendars

Information on which resources (such as people, equipment, and material) are potentially available during planned activity period.

Resource optimization techniques

Involve the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time.

Critical Chain Method (CCM)

Is a schedule network analysis technique that modifies the project schedule to account for limited resources. Adds duration buffers that are non-work schedule activities to manage uncertainty.

Schedule Baseline

Is a specific version of the project schedule developed from the schedule network analysis. It is accepted and approved by the project management team as the schedule baseline with baseline start dates and baseline finish dates. It is a component of the project management plan.

Resource Leveling

It is a schedule network analysis technique applied to a schedule that has already been analyzed by the critical path.

Total Float

On any network path, the schedule flexibility is measured by the positive difference between early and late dates.

Project Buffer

One buffer, placed at the end of the critical chain, protects the target finish date from slippage along the critical chain.

Plan Schedule Management Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule

Planning Process Group

PDM

Precedence Diagramming Method

PERT

Program Evaluation and Review Technique. Uses three estimates to define an approximate range for an activity's duration. PERT analysis calculates an Expected (tE) activity duration using a weighted average of these three estimates.

Project Document Updates

Project documents that may be updated include: - Activity lists - Activity attributes - Milestone list - Risk register

Project Document Updates

Project documents that may be updated include: - Activity resource requirements - Activity attributes - Calendar - Risk register

Project Management Software

Project management software for scheduling provides the ability to track planned dates versus actual dates, and to forecast the effects of changes to the project schedule.

Expert Judgement

Project team members or other experts, who are experienced and skilled in developing detailed project scope statements, the WBS, and project schedules, can provide expertise in defining activities.

Meetings

Project teams may hold planning meetings to develop the schedule management plan. Participants: project manager, the project sponsor, selected project team members, selected stakeholders, anyone with responsibility for schedule planning or execution, and others as needed.

Activity Attributes

Provide the details used to build the schedule model.

Activity attributes

Provide the primary data input for use in estimating durations required for each activity in the activity list.

Activity Resource Requirements

Resource leveling can have a significant effect on preliminary estimates of the types and quantities of resources required. If the resource-leveling analysis changes the project resource requirements, then the project resource requirements are updated.

Critical Activities

Schedule activities on a critical path.

Activity attributes are used for

Schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports.

Schedule Compression

Shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives.

Project Staff Assignments

Specify which resources are assigned to each activity.

SF

Start-to-finish. The completion of the successor activity depends upon the initiation of the predecessor activity.

SS

Start-to-start. The initiation of the successor activity depends upon the initiation of the predecessor activity.

The majority of effort in the Project Time Management Knowledge Area will occur in...

The Control Schedule process to ensure completion of project work in a timely manner.

Organizational procedures links

The WBS provides the framework for the schedule management plan, allowing for consistency with the estimates and resulting schedules.

Level of accuracy

The acceptable range used in determining realistic activity duration estimates is specified and may include an amount for contingencies.

Three-Point Estimates

The accuracy of activity duration estimates can be improved by considering estimation uncertainty and risk.

Free Float

The amount of time that an activity can be delayed without delaying the early start date of any immediate successor activity within the network path. Can be determined after the total float of network path has been calculated.

Milestone list

The milestone list may have scheduled dates for specific milestones, which may influence the way activities are sequenced.

Monte Carlo Analysis

The most common Simulation technique. A distribution of possible activity durations is defined for each activity and used to calculate a distribution of possible outcomes for the total project.

Characteristics of What-If Analysis

The outcome of the whatif scenario analysis can be used to assess the feasibility of the project schedule under adverse conditions, and in preparing contingency and response plans to overcome or mitigate the impact of unexpected situations.

Project schedule model maintenance

The process used to update the status and record progress of the project in the schedule model during the execution of the project is defined.

How to deal with a project with a negative float

The project manager will have to either fast-track or crash the project schedule.

Resource Calendars

The resource calendars influence the duration of schedule activities due to the availability of specific resources, type of resources, and resources with specific attributes.

Critical Chain

The resource-constrained critical path

Risk Register

The risk register, and risk response plans within it, may also be updated based on the risks that may arise due to schedule compression techniques.

Project schedule model development

The scheduling methodology and the scheduling tool to be used in the development of the project schedule model are specified.

Milestone Charts

These charts are similar to bar charts, but only identify the scheduled start or completion of major deliverables and key external interfaces.

Bar Charts

These charts, with bars representing activities, show activity start and end dates, as well as expected durations. Bar charts are relatively easy to read, and are frequently used in management presentations.

Project Schedule Network Diagrams

These diagrams, with activity date information, usually show both the project network logic and the project's critical path schedule activities. These diagrams can be presented in the activity-on-node diagram format, or presented in a time-scaled schedule network diagram format that is sometimes called a logic bar chart.

Contingency Reserves

Time reserves or buffers. May be a percentage of the estimated activity duration, a fixed number of work periods, or may be developed by using quantitative analysis methods.

Activity Attributes

Updated to include any revised resource requirements and any other revisions generated by the Develop Schedule process.

Leads and Lags

Used to find ways to bring project activities that are behind into alignment with the plan.

Schedule Compression

Used to find ways to bring project activities that are behind into alignment with the plan.

Modeling Techniques

Used to review various scenarios guided by risk monitoring to bring the schedule model into alignment with the project management plan and approved baseline.

Purpose of Resource Breakdown Structure

Useful for organizing and reporting project schedule data with resource utilization information.

Parametric Estimating

Uses a statistical relationship between historical data and other variables (e.g., square footage in construction) to calculate an estimate for activity parameters, such as cost, budget, and duration. Activity durations can be quantitatively determined by multiplying the quantity of work to be performed by labor hours per unit of work.

Control thresholds

Variance thresholds for monitoring schedule performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the parameters established in the baseline plan.

Activity Resource Requirements

Will have an effect on the duration of the activity, since the resources assigned to the activity and the availability of those resources will significantly influence the duration of most activities.

Characteristics of Fast Tracking

• May result in rework and increased risk. • Only works if activities can be overlapped to shorten the duration.

Characteristics of Crashing

• Only works for activities where additional resources will shorten the duration. • Doesn't not always produce a viable alternative and may result in increased risk and/or cost. Examples: • approving overtime, • bringing in additional resources, or • paying to expedite delivery to activities on the critical path

The schedule management plan can establish the following

• Project schedule model development • Level of accuracy • Units of measure • Organizational procedures links • Project schedule model maintenance • Control thresholds • Rules of performance measurement • Reporting formats • Process descriptions

Schedule Data Supporting Detail

• Resource requirements by time period, often in the form of a resource histogram. • Alternative schedules, such as best-case or worst-case, not resource-leveled, or resource leveled, with or without imposed dates. • Scheduling of contingency reserves. • could include such items as resource histograms, cash-flow projections, and order and delivery schedules.


Related study sets

Quizzes for Exam One: Strength and Conditioning

View Set

Ethics Finals Study Guide- Week 6

View Set

A&P 2: Chapter 21: Blood Vessels

View Set

AP Chemistry Final (Second Semester)

View Set

Abeka Science Matter and Energy Test 1

View Set

Passive Transport and Active Transport (7.3 and 7.4)

View Set

ChatGPT in our daily or professional lives. Fill in

View Set

Fungi (characteristics and function)

View Set

Learnsmart Chapter 8 Part 1 and Part 2

View Set