Rearranging resources so that a constant number of resources is used each month is called: A. Crashing. B. Floating. C. Leveling. D. Fast tracking.
C. Levelling
The _____ is a time-phased budget that will be used to measure and monitor cost performance in the project. A. WBS B. project schedule C. cost baseline D. cost budget
C. cost baseline
CPPC
Cost Plus Percentage of Control
A fundamental tenet of modern quality management holds that quality is most likely to be achieved by: A. planning it into the project B. developing careful mechanism to inspect for quality C. striving to do the best job possible D. conducting quality circle activities
A. planning it into the project