Project Management Project 2016 Tutorial Video - Introduction to Microsoft Project 2016

Ace your homework & exams now with Quizwiz!

How do you create a split view in MS Project? a. Dragging two views side by side b. Clicking File>>View>>Split View c. Clicking the timeline or details checkbox d. Right clicking and choosing dual-view

NOT b. Clicking File>>View>>Split View

Which of the following is not a way to change the details view? a. Clicking the view shortcut buttons b. Choosing a view in the View Tab c. Right clicking the view name d. Clicking the Task Tab>>Change View

NOT d. Clicking the Task Tab>>Change View

How does MS Project schedule tasks by default? a. Manually b. Automatically c. Inadvertently d. Annually

a. Manually

What is the purpose of the timeline? a. To give an overview of the project as a whole b. To show how other projects are paced c. To give the project manager a detailed status report d. To track timed resources

a. To give an overview of the project as a whole

Where do you set the project start date? a. In the Timeline View b. In the Project Tab c. In the File menu under Project Information d. In the Working Time menu

b. In the Project Tab


Related study sets

General Chemistry II Exam #4 CLP Questions

View Set

Approach to Abdominal Pain Questions

View Set

ATI Safe Dosage Calculations: Critical Care Medications

View Set

Surface Currents (Science Lesson 2.06)

View Set