SCM 4362 Exam 3 Review
Which of the following is an assumption commonly made in using MRP lot-sizing procedures?
All of the options are assumptions commonly made in using MRP lot-sizing procedures.
Which of the following statement is(are) true in ROP analysis?
All statements are true
PAC is located in which part (phase) of the MPC framework?
Back end
In Theory of Constraints, which of the following is represented by "drum"?
Bottleneck resource
The Theory of Constraints (TOC) approach is also referred to as
Drum - Buffer - Rope
A CR (Critical ratio) > 1 of a job implies that the job is already late. (T/F)
False
As the service level increases, the probability of not running out of stock during a cycle decreases. (T/F)
False
EOQ inventory models are basically concerned with the timing of orders. (T/F)
False
Everything else remaining the same, if Lead Time (LT) increases, ROP will decrease. (T/F)
False
In MRP, the only source of uncertainty is supply. (T/F)
False
In a TOC system, inventory buffers before bottleneck resources are eliminated. (T/F)
False
In a single machine job shop, the makespan depends on the rule used for scheduling. (T/F)
False
Inventory items that are found at many points in a supply chain, including finished goods in factories, field warehouses, and distribution centers; spare-parts inventories; office and factory supplies; and maintenance materials are referred to as dependent demand inventories. (T/F)
False
Johnson's rule when applied in a two-machine case will provide minimum average lateness. (T/F)
False
KBB will provide the minimum total cost only if the net requirements in MRP are lumpy. (T/F)
False
Lead times are typically made up of operation or machine run time per piece × lot size. (T/F)
False
Short term capacity planning should be driven by identification and management of non-bottlenecks. (T/F)
False
TOC stands for Theory of Operating Controls. (T/F)
False
The Critical Ratio rule uses the information about the processing time of the job in the current work center only. (T/F)
False
The economic order quantity (EOQ) lot-sizing technique produces or acquires exactly the amount of product that is needed each time period with none carried over into future periods. (T/F)
False
The economic order quantity (EOQ) lot-sizing technique uses the "square root formula" to balance setup cost, carrying cost, and cost of stockouts. (T/F)
False
The objective of inventory management is to minimize the cost of holding inventory. (T/F)
False
The primary consideration in the development of lot-sizing procedures for MRP is the nature of the gross requirements data. (T/F)
False
Which one of the following reasons creates a pressure for reducing inventories?
High interest or opportunity cost
Priority sequencing rules determine which of the following? I- Allocation of goods to customers II- Which machine to service next? III- Which job to work on at the work center?
III only
Which of the following statement is false?
Johnson's rule will minimize average job completion (flow) time in two machine case
Which of the below lot-sizing procedures provide an optimal solution in MRP lot-sizing?
KBB
Which one of the following lot-sizing rules guarantees an optimal solution when demand is constant?
KBB & EOQ
Freezing the schedule is one way of mitigating
MRP system nervousness
Which of the below activities in MPC provide direct input to PAC?
Material Requirements Planning
The lowest planning and control level in MPC is:
PAC
Which one of the following is not an assumption of the basic EOQ model?
Quantity discounts can be taken advantage of for large lot sizes.
Practical application of the Theory of Constraints involves the implementation of all of the following steps except
Reduce the capacity at the bottleneck(s).
Which sequencing rule ignores all due date information as well as all information about work remaining?
SPT
What type of stock provides protection against irregularities or uncertainties in an item's demand?
Safety stock
A critical information service provided by MRP is apprising the SFC systems of all changes in material plans. (T/F)
True
Demand for raw materials and component items is derived demand, calculated exactly once a firm has the MPS. Therefore, items contained in manufacturing inventories is called dependent demand inventory. (T/F)
True
In TOC, bottleneck work centers are scheduled using finite loading techniques. (T/F)
True
KBB sometimes may yield the same total cost (cost of ordering + cost of carrying) as when some other Lot sizing method is used. (T/F)
True
One component of the holding cost of inventory is interest. (T/F)
True
Sequencing rules simply prioritize jobs at work centers without reference to the capacity. (T/F)
True
The SPT rule represents the best way to pick the next job to run, if the objective is to minimize average time per job, to minimize average number of jobs in the system, or to minimize average job lateness. (T/F)
True
The Theory of Constraints scheduling loads work centers to full capacity by using finite scheduling. (T/F)
True
The primary connection between PAC and the rest of the MPC systems comes from material requirements plans. (T/F)
True
The primary reason for keeping inventories low is that inventory represents a temporary monetary investment in goods on which a firm must pay interest. (T/F)
True
The process with the least capacity is called a bottleneck. (T/F)
True
The quantities and timings for planned order releases are determined via MRP logic using the inventory records, the gross requirements data, and a quantity-determination (lot-sizing) procedure. (T/F)
True
The routing specifies each operation to be performed to make the part and which work center will perform the operation. (T/F)
True
Variability in demand and/or lead time can be compensated for by safety stock. (T/F)
True
When finite scheduling through bottleneck resources is complete, the result is
a doable MPS
The general objective of all MRP lot-sizing procedures is to
balance inventory-related costs to achieve a low total cost requirement schedule.
According to Theory of Constraints, buffers should
be actively managed
In an ABC classification of inventory items which of the following is false?
class B items have a lower monetary value than class C items.
The lot-for-lot (L4L) procedure
creates order quantities that are exactly equal to net requirements.
In Theory of Constraints, "exploit the bottleneck(s)," suggests
creation of a schedule that maximizes the throughput of the bottlenecks.
If no variations in demand or lead time exist, the ROP will equal
demand during lead time.
The economic order quantity (EOQ) procedure
is based on the assumption of constant uniform demand.
Using the Theory of Constraints scheduling logic in simulation mode can help
negotiate achievable delivery dates and meet customer service goals.
Which of the following statements is correct about implicit enumeration?
only promising alternatives are judiciously selected & evaluated.
One way of dealing with the shop-floor complexity is by
priority sequencing rules
Examining realistic, multiple-machine, dynamic scheduling situations is possible by using
simulation
Which one of the following would not be a factor in determining the reorder point?
the EOQ
Theory of Constraints scheduling combines data in which of the following pairs?
the bill of materials (BOM) file with data in the routing file
The Stock-out probability is
the probability that inventory will not be sufficient to meet demand during the cycle
The Stock-out probability is:
the probability that inventory will not be sufficient to meet demand during the cycle