SCM4362 - Exam 3 Review
Which of the following is an assumption commonly made in using MRP lot-sizing procedures?
All of the options are assumptions commonly made in using MRP lot-sizing procedures.
Which of the following are functions of inventory?
All of the options are functions of inventory
Which of the following statements is correct?
All of the statements are correct.
Which of the following statement is(are) true in ROP analysis?
All statements are true
PAC is located in which part (phase) of the MPC framework?
Back end
In Theory of Constraints, which of the following is represented by "drum"?
Bottleneck resource
he Theory of Constraints (TOC) approach is also referred to as
Drum - Buffer - Rope
For a certain item, it was observed that the holding cost per annum per unit was equal to the setup cost per order. What can we say about the EOQ in this case?
EOQ =Sqrt (2A) , where A is the annual demand.
The prime objective of PAC is:
Executing MPC plans
A CR (Critical ratio) > 1 of a job implies that the job is already late.
False
In a TOC system, inventory buffers before bottleneck resources are eliminated
False
In a single machine job shop, the makespan depends on the rule used for scheduling.
False
In the A-B-C approach, C items typically represent about 15 percent of the number of items, but 60 percent of the dollar usage.
False
Inventory items that are found at many points in a supply chain, including finished goods in factories, field warehouses, and distribution centers; spare-parts inventories; office and factory supplies; and maintenance materials are referred to as dependent demand inventories.
False
Johnson's rule when applied in a two-machine case will provide minimum average lateness.
False
KBB will provide the minimum total cost only if the net requirements in MRP are lumpy.
False
PAC stands for Process Activity Control
False
Short term capacity planning should be driven by identification and management of non-bottlenecks.
False
TOC stands for Theory of Operating Controls.
False
The A-B-C approach involves classifying inventory items based on their name.
False
The Critical Ratio rule uses the information about the processing time of the job in the current work center only.
False
The EOQ is based on the assumption of lumpy demand,
False
The economic order quantity (EOQ) lot-sizing technique produces or acquires exactly the amount of product that is needed each time period with none carried over into future periods.
False
The primary consideration in the development of lot-sizing procedures for MRP is the nature of the gross requirements data.
False
The use of the lot-for-lot procedure tends to increase the lumpiness of the gross requirements of items further down in the BOM.
False
Which one of the following reasons creates a pressure for reducing inventories?
High interest or opportunity cost
Which of the following three strategies can be useful in reducing MRP system nervousness?
I- Using Time fences II- Using Firm Planned Orders III- Careful use of Lot-Sizing procedures
Which one of the following lot sizing rules guarantees an optimal solution when demand is constant?
KBB & EOQ
The total time to process an entire set of jobs at a work center is referred to as
Make-span
Which one of the following statements about lot sizing rules is correct?
None of the statements is correct
Summing the setup times and run times for all remaining operations, and subtracting this from the time remaining until the due date is referred to as
Order Slack (ST) rule
Which one of the following is not an assumption of the basic EOQ model?
Quantity discounts can be taken advantage of for large lot sizes.
Practical application of the Theory of Constraints involves the implementation of all of the following steps except
Reduce the capacity at the bottleneck(s).
Which sequencing rule ignores all due date information as well as all information about work remaining?
SPT
Which one of the following descriptions best defines customer service level?
The desired probability of not running out of stock during the lead time
. In TOC, bottleneck work centers are scheduled using finite loading techniques.
True
A bottleneck is an operation that has the lowest capacity of any operation in the process.
True
A bottleneck resource should never be starved.
True
A negative SPO (Slack per remaining operations) of a job implies that the job is already late
True
Carrying cost is a function of order size; the larger the order quantity, the higher the inventory carrying cost.
True
Everything else remaining the same, if EOQ increases, Time Between Orders (TBO) will increase.
True
Johnson's sequencing rule for two machines will minimine the makespan
True
KBB sometimes may yield the same total cost (cost of ordering + cost of carrying) as when some other Lot sizing method is used
True
MRP lot-sizing procedures are designed specifically for the discrete demand case.
True
POQ and LFL will be the same if TBO = 1 period.
True
Sequencing rules simply prioritize jobs at work centers without reference to the capacity.
True
The SFC system of PAC is updated on changes in the MRP system
True
The SPT rule represents the best way to pick the next job to run, if the objective is to minimize average time per job, to minimize average number of jobs in the system, or to minimize average job lateness.
True
The Theory of Constraints scheduling loads work centers to full capacity by using finite scheduling.
True
The average inventory level and the number of orders per year are inversely related: As one increases, the other decreases.
True
The basic EOQ model ignores the purchasing cost.
True
The calculation of safety stock requires knowledge of demand and lead time.
True
The overall objective of inventory management is to achieve satisfactory levels of customer service while keeping inventory costs reasonable.
True
The primary PAC objective is managing the materials flow to meet MPC plans
True
The primary connection between PAC and the rest of the MPC systems comes from material requirements plans.
True
The process with the least capacity is called a bottleneck
True
The quantities and timings for planned order releases are determined via MRP logic using the inventory records, the gross requirements data, and a quantity-determination (lot-sizing) procedure.
True
Using the EOQ model, the higher an item's carrying costs, the more frequently it will be ordered.
True
When ordering costs are relatively small compared to inventory carrying costs, LFL will yield favorable results
True
Priority sequencing rules determine which of the following?
Which job to work on at the work center?
When several jobs arrive at a work center, there is a need for
a system of scheduling and prioritizing
The need for safety stocks can be reduced by an operations strategy which
all of the options are incorrect
Which of the following statements is correct about complete enumeration?
all possible alternatives are evaluated and compared to pick the best solution.
The general objective of all MRP lot-sizing procedures is to
balance inventory-related costs to achieve a low total cost requirement schedule.
According to Theory of Constraints, buffers should
be actively managed
Consider consecutive processes A-B-C, where process A has a capacity of 20 units per hour, process B has a capacity of 25 units per hour, and process C has a capacity of 30 units per hour. Where would an operations manager, with some understanding of TOC, want any buffer inventory?
in front of process A.
In Theory of Constraints application, "breaking the constraint" or "elevate the bottleneck(s)," means
increasing capacity of the bottleneck.
Using the Theory of Constraints scheduling logic in simulation mode can help
negotiate achievable delivery dates and meet customer service goals.
Which of the following statements is correct about implicit enumeration?
only promising alternatives are judiciously selected & evaluated.
One way of dealing with the shop-floor complexity is by
priority sequencing rules
In the basic EOQ model, if lead time increases from five to 10 days, the EOQ will
remain the same.
Which one of the following would not be a factor in determining the reorder point?
the EOQ
sequencing rules are used to establish
the priorities for the jobs in a queue waiting to be processed at a work center.