SCMS 432. Chapter 7
A planning bill of material is
A bill of material that represents probably usage in an assemble-to-order environment
The master production schedule (MPS) translates the sales and operations plan (SOP) into
A specific production plan
Cycle stock is
Inventory carried as a result of lot size requirements
Available-to-promise (ATP) is likely to be least useful in which environment
Make-to-stock
The master production schedule (MPS) differs from the forecast by considering
Capacity limits, Production costs, and The sales and operations plan (SOP) (I, II, and III)
Inside the planning fence, which of the following is true?
Changes to production orders are not allowed
Prerequisites to implementing a master production scheduling system?
Define master production schedule (MPS) unit & Train an employee in MPS concepts and techniques (I and III only)
The master production schedule (MPS) shows when products will physically be available to ship
False
The master production schedule must be stated in terms of actual products
False
The master production schedule (MPS) is
Neither a statement of current production nor current demand
Which formula is used to calculate the projected available inventory balance
Projected available inventory = Previous available inventory + Master production schedule - MAX(Forecast, Actual orders)
In which environment is a planning bill-of-material (BOM) most likely to be used?
Assemble-to-order
Inside the demand fence, which of the following is true?
Available-to-promise (ATP) calculations ignore forecasts
One key to avoiding an overstated master production schedule (MPS) is to
Force the MPS to match the production plan (in terms of total units)
The final assembly schedule (FAS) represents which of the following
The assembly plan when a planning bill-of-materials (BOM) is used, The exact set of end products to be built in an assemble-to-order environment, The plan for moving pre-fabricated components into completed products (I, II, and III)
A super bill represent average usage of components in an assemble-to-order envionment
True
The master production schedule (MPS)) considers preferred lot sizes when constructing the plan
True
The master production schedule must be stated in terms that relate to a producible product
True
When the master production schedule (MPS) is frozen for some period, changes to the plan within that period are typically prohibited
True