Activity Levels
Facility-level
Activities carried out regardless of which type of products are produced, how many batches are run, or how many units are made.
Facility level activity measure
Direct labor hours *Facility-level costs cannot be traced on a cause and effect basis to individual products.
Facility level activity
General factory administration Plant building and grounds Cafeteria for factory workers
Product Level activity measure
Hours of testing time Number of part types Hours of design times
Unit-Level Activity measures
Machine hours Direct labor hours Units produced
Batch-level activities
Processing purchase orders processing production orders Setting up equipment Handling material
Unit-level Activities
Processing units on machines Processing units by hand Consuming factory supplies
Batch-level activity measures
Purchase orders processed production orders processed Number of setups; setup hours Pounds of material handled; number of times material moved
Product-level
Specific products and typically must be carried out regardless of how many batches or units of the product manufactured
Batch-level
performed each time a batch is handled or processed
Unit-level
performed each time a unit is produced. The costs of unit-level activities should be proportional to the number of units produced.
Product-level activities
testing new products administering parts inventories Designing products