If the cycle time increases, but no new resources are added to the process, then the time needed to serve 100 customers will ______.

Increase

__________________ __________________ id's and analyzes all the activities involved in serving one unit of demand or, put differently, in providing one unit of supply.

Process Analysis

What shape is used to represent flow units waiting in a system( BUFFER INVENTORY)?

Triangle

Understanding the location of the ______________ is critical for improving a process.

bottleneck

Inventory ______ accumulate between workers in a worker-paced line.

can

True or false: Utilization can be greater than 100%.

F

True or false: A process that is demand constrained can have utilization of 100%.

F. If process is demand constrained then flow rate will be less than capacity.

In a worker-paced line each worker always works at the same rate.

False

A rigorous framework for understanding the detailed operations of a business is known as

Process Analysis

To increase the capacity of a process one must increase the capacity of the resource that is the__________________

bottleneck

Flow units waiting in the process w/o being worked on are often referred to as _________________ inventory.

buffer

An organization that wants to fulfill customer orders more quickly should make the cycle time of their fulfillment process __________.

decrease

If the flow time for a process goes down then the time to finish X units starting with empty inventory buffers will ________.

decrease

The__________________rate is the number of flow units that customers want per unit of time.

demand

When the flow rate is less than the capacity the process is referred to as______________ constrained

demand

A process flow diagram is a graphical way to ______________ the process.

describe

In a process flow diagram, triangles are used to represent ________________ waiting in a sys.

flow units

If cycle time stays constant but inventory goes down what will happen to lead time?

go down

If inventory goes up but flow time stays constant what will happen to cycle time?

go down

If cycle time goes up what will happen to lead time?

go up

As cycle time increases, the time to make Q units __________.

increase

To increase the capacity of a process, one should __________.

increase the capacity of the bottleneck resource regardless of where it is located in the process

Flow units waiting in the process w/o being worked on are often referred to as buffer_______________.

inventory

a _______________ _____________ ______________ is a graphical way to describe a process

process flow diagram

The _______________time of a resource is how long that particular resource takes to complete one flow unit.

processing

Consider a process with two resources where the first has capacity of 2 customers/minute and the second has capacity of 1.5 customers/minute. If the processing time at the first resource goes down then what will happen to the capacity of the process?

stay the same

Flow rate can be __________ or____________________ process capacity.

= to or <

What shape is used to represent resources in a process flow diagram?

Box

If process capacity is 60 units per hour and customers desire 80 units per hour then the process is ____________________ constrained,

Capacity

When the flow rate is less than the demand rate the process is referred to as_________ constrained.

Capacity

What is an appropriate unit for cars for a demand rate?

Cars per day

In a process flow diagram, triangles are used to represent___________ waiting in a sys.

Flow units

Resources help the flow units to move from being a unit of _________________ to a unit _________________.

Input, output

__________________ help the flow units to move from being a unit of input to becoming a unit of output

Resources

____________________are shown as rectangular boxes in the process flow diagram.

Resources

T or F: A process flow diagram outlines a directional flow in the process

T

A resource will have idle time when it comes ______ the bottleneck in the process.

after

A process flow diagram indicates

both where a flow unit is processed and where it is held in inventory.


Conjuntos de estudio relacionados

Muscles of the Elbow and Forearm

View Set

Nevada Statutes & Regulations Common to All Lines

View Set

Andrew Carnegie, J.P. Morgan, and John D. Rockefeller

View Set

Purines and pyrimidines.........

View Set