Construction Blueprint Reading 16wk Final Exam Review

¡Supera tus tareas y exámenes ahora con Quizwiz!

Both restrooms have quarry tile floors.

False

Face brick is the only masonry material used on the building.

False

The rough opening for plastic laminate-covered flush doors with adjustable aluminum frames is 3 foot 3/4 inch wider than the door leaf.

False

The steel gate arm for the trash enclosure is 3/8 inch by 2 inches by 30 inches

False

The storage module is provided by the general contractor.

False

The triangle pavement marker for the pick-up window is larger than the marker indicating the exit.

False

Three interior elevations on Sheet 6D are referenced in Room 105

False

Two scuppers with downspouts are shown on the Front elevation.

False

Unless otherwise noted, ½ inch anchor bolts at 6 foot on center are typical for all foundation walls.

False

Water closets in restrooms are backed up to a common wall.

False

Wrought iron railings are placed outside both entrance doors.

False

A doors have tempered glass.

True

A sliding glass window is installed on the west side of the pickup window area.

True

A wrought iron railing is installed outside the South entrance to the building.

True

All exterior elevations are drawn to the same scale.

True

All footings are designed for 3000 PSF soil-bearing pressure.

True

All interior elevations for the Office are included on sheet 6 E

True

Anchor bolts for exterior pole lights are installed by the electrical contractor.

True

Brick veneer is 4" thick throughout the entire exterior.

True

Crosshatch grooving is required on all sloped surfaces of a sidewalk ramp.

True

Exterior dimensions are from out -to- out of plywood sheeting.

True

Exterior pole lights are metal halide vertical fixtures.

True

Footing depths below grade must be verified with the local code.

True

Foundation walls at the pick-up windows are 8 inch and 12 inch concrete masonry units

True

Interior dimensions are given from face-to-face of framing.

True

Patrons enter and exit the building through A doors.

True

Return walls for vestibules are 5 foot 4 inches long.

True

The Dry Storage area has a quarry tile floor

True

The Men's Room is designated as room 102.

True

The Wendy's sign is supplied by the owner.

True

The downspouts are connected to underground drain lines.

True

The electrical contractor must install 30 feet light poles for the exterior pole lights.

True

Blocking in frame walls is to be no more than 4 foot apart.

False

Concrete control joints must be sawn within eight hours of concrete placement.

False

Eight sections are referred to on the Floor Plan.

False

Exterior masonry walls are entirely constructed of brick.

False

Extruded curbs are reinforced with number four rebar running continuously.

False

Footings for trash closure post on the rear wall are 16 inches in diameter.

False

Four sections and two elevations are referenced on the Standard Trash Enclosure Plan.

False

Hood 2 is the same size as Hood 1.

False

Piping runs for plumbing are shown as hidden lines on the foundation plan.

False

Pivot hinges are specified for three door types.

False

Stainless steel panels behind the cooking equipment are installed by carpenters.

False

The dimensions of the Cooler or Freezer module are 12' by 16'

False

The front and rear of the building are illuminated with an equal number of wall-mounted light fixtures.

False

The general contractor is to paint all pavement markers solid yellow.

True

The shear wall and is detailed on sheets 3 and 7A.

True

The thickness of the concrete floor slab is 4 inches.

True

Three number 4 by 24 inches long rebar are placed through exterior door openings.

True

Wall tile for the recessed mop basin is laid 2 inches below the finished floor surface.

True


Conjuntos de estudio relacionados

AP English 3 Vocab week 8 semester 2

View Set

3 Steps to Writing an Introduction

View Set