IDS 200: Chapter Extension 18 Quiz

¡Supera tus tareas y exámenes ahora con Quizwiz!

How many members are recommended for a scrum​ team?

5 to 9

Which of the following is NOT a scrum​ essential?

Complete the project early and forget about it

Which of the following statements about a scrum team is​ FALSE?

Creating tasks as a group in a team meeting is often avoided since it delays the implementation process.

When using an Agile development​ approach, what is the maximum amount of time acceptable to deliver a working version of the​ product?

Eight weeks

What is​ just-in-time design?

Only those portions of the design that are needed to complete the current work are done.

Scrum is an agile development process that follows the scrum essentials principles. According to​ scrum, what are the three principal​ roles?

Product​ owner, scrum​ master, and team members

What is a characteristic of the scrum methodology that proves the methodology is a valid​ method?

Providing a framework for process learning

Which of the following statements about SDLC is​ FALSE?

SDLC works just as well for software as for the construction of buildings.

Which of the following are NOT alternatives to the SDLC​ process?

Scum master

Which of the following is NOT an agile development​ principle?

Test the project after it is complete

The following are reasons why the SDLC process is falling out of favor. Which one is​ not?

The SDLC is a slow process.

Which of the following statements about​ stand-ups is​ FALSE?

The duration for the​ stand-up varies from day to day.

Which of the following statements about the scrum process is​ FALSE?

The result of the​ team's work includes the design and other documents.

Which of the following is NOT a function of the scrum​ master?

The scrum master has the authority to​ add, delete, or change requirements and their priority.

Which of the following processes is NOT part of the scrum estimation​ technique?

The team assigns two points to a task that will take five times longer.

What is the key purpose of the​ stand-up?

To achieve accountability for team​ members' progress and to give a public forum for blocking factors

Which of the following is a principle in the scrum development​ process?

Welcome and expWhich of the following is a principle in the scrum development​ process?ect change

During the daily​ stand-up, each team member provides which of the following​ information?

What they have done in the past​ day, what they will do in the coming​ day, and any factors that are blocking their progress

Which of the following statements about team velocity is​ FALSE?

When the team is unaware of its​ velocity, the estimates​ it, but this may not be accurate and once​ made, it can never improve.

After the product is​ delivered, the scrum team meets for all of the following reasons EXCEPT to​ ________.

test the product

Work continues in a repeating cycle of scrum periods until one of the following conditions is met EXCEPT​ ________.

the project manager is satisfied with the product developed

As teams work​ together, they will learn the total number of points of work they can accomplish each scrum period. This term is called the​ team's ________.

velocity


Conjuntos de estudio relacionados

F2: Determine the need for Behavior-Analytic Services

View Set

Management Test 2 Answers answered incorrectly

View Set

Chapter 13- Cardiovascular System

View Set

(not mine) CFP Retirement Planning Final

View Set

Nuance Clintegrity Physician Query

View Set

Chapter 58 practice questions- PrepU

View Set