Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
Day 5
An activity in a network diagram cannot start until
All of the preceding activities that are linked to it by arrows are finished
Constraints for a project are
a number of different factors that influence the project outcome
The earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated
by adding the activity's.....
It is much more expensive to make major changes to a project during the earlier phases.
false
The ______ for an activity is the latest possible time an activity might begin without delaying the project finish date
late start date
A formal request for proposal is prepared for
projects that the company decides need to be addressed by an external resource or through a competitive process
The project ____ usually provides the direction and funding for the project.
sponsor
A ____ deals with the scope of the project, outlining the tasks or work elements the customer wants the contractor or project team to perform
statement of work
A WBS is often depicted as a task-oriented pie chart
False