Revision Control
Informal "in progress" documents sent to clients after first revision (A, 0) shall have a watermark:
"DRAFT - IIP dateXX/YY/ZZZZ" on each page of PDF format, in header /footer of native files.
Fixed fee project suffix
.00
Time and Material project suffix
.50
The 10 types of documents controlled by Project Document Revision Procedure MGT-1010
1. Proposals; 2. Sketches; 3. Technical Reports; 4. Technical Specifications; 5. Lists and Database Reports; 6. Drawings; 7. Instrument and Equipment Specification Sheets; 8. PLC Software; 9. Software; and 10. Operation and Maintenance Manuals
Document Control
A function which keeps track of all documentation, specification, and processes to ensure that everyone uses the correct and most current documentation and specifications.
Which issued documents require transmittals?
ALL documents
Record Retention
An index which includes but is not limited to the following information: Record, Storage Location, Retention Period, Maintenance, and Disposition.
Record
An item or collection of data. Examples of records would be those required by the ISO 901 standard or those needed to demonstrate conformity to our requirements such as project records, verification records, etc.
File Naming Convention for Appendices
DOC# + rR + AppZ + Title
File Naming Convention for Issued files
DOC# + rR + opt. Short Description where DOC# is the unique document number, rR is the document revision level
Editing of controlled documents in the Document Store is Restricted to the
DRR process.
A document is considered approved and released when an electronic copy is filed in the
Document Store
True or false: Appendix revision history has to match the document's revision history.
False. (You can have a report the is Rev 1 and Appendices that are Rev 10)
Place a copy of the "in progress" drawings sent to the client in the ISSUED folder appropriately named and
Include the notation "IIP" at the end of the folder name to identify the contents appropriately.
Transmittal and all deliverables shall be stored in the ___ directory
Issued
The Revision Codes
Issued for Review (IFR), Issued - In Progress (IIP), Issued for Approval (IFA), Issued for Bids (IFB), Issued for Purchase (IFP), Issued for Design (IFD), Issued for Construction (IFC), Issued for Record (IFRec), Issued for Information (IFI), Issued for Fabrication (IFF).
Approvers, while encourage in temporary revisions, are ___ required
Not
Given numerical designations
Permanent Revisions
When a document is to be used for a project, the appropriate document shall be obtained from the Document Store and saved per the project requirements or as outlined in the Electronic Project Document Management Procedure. The project document then becomes a
Record
Unless specifically directed to do otherwise by a client, Temporary Revisions shall be completely ___ from the revision block when the document is issued for its next permanent purpose.
Removed
Given alpha designations
Temporary Revisions
Storage
The action or method of storing records for future use
For documents previously issued with a Permanent Revision, Temporary Revisions shall be labeled with
The latest revision number plus an alpha suffix
Retreival
The method of accessing records or making them available for use or review.
Identification
The method of naming records
Retention
The method of retaining records for a determined length of time.
Protection
The method of safeguarding records
Disposition
The orderly arrangement of or method of removal of records
Checker
The person responsible for checking the final deliverable for the technical content before it is issued to anyone outside the company. Can not also be the By
By
The person responsible for creating or generating the deliverable. (spends the most time doing so). Can not be the Checker.
DRR - Document Review and Release
The process that a document goes through to be identified, reviewed, approved, translated, and released.
All deliverables listed on a transmittal shall be listed with:
The revision number, the revision date, and the assigned revision code.
Once a Revision Code has been assigned, it should be used for all issues for a document until when?
Until the status of the document merits a Revision Code change.
Temporary Revision
Used for coordination with clients, suppliers, and vendors during ongoing project development. Typically followed by a Permanent Revision. Include review, approval, bids.
Permanent Revision
Used to provide clients (internal or external), suppliers, or vendors with information on which they can take action or for final documentation or a project. Include design, purchase, fabrication, construction, record, or information.
Approver
Usually, the project manager or technical lead. Can be the same person as the By or the Checker.
Document Numbering Convention
YYYYNNNN + .SS + PPP + ACR + ID + SQ
Subdirectory templates for Engineering and Automation
_Corresp, _CSIndex, _Issued, _Recd, 000 PM, 005 DIS, 015 DEF, 020 SDN, 025 FDN, 030 EQP, 035 VER, 040 CFG, 065 CON
A new directory is created when
a new proposal is issued
Deviations from the Revision Matrix in MGT-1010 must be approved by
a senior manager or above
Purpose of revision code
define the purpose of a formal or informal document sent to the client
Name of first Permanent Revisions
doc.r0
Name of first Temporary Revision document
doc.rA
Records are to be
legible, readily identifiable, and retrievable
Parent documents issued as a temporary revision include appendices issued as a permanent revision.
may
Revision triangles are required and shall ___ be removed from drawings
not
Where must the Revision Code must be displayed?
on the document, on the transmittal, and on electronic filename if possible
Quick indication of whether or not the project has been awarded and is fully setup
presence or absence of the project number suffix in the directory name.
Unless specifically directed to do otherwise by the customer, Temporary Revisions shall be completely ___ from the revision block when the document is issued for its permanent purpose.
removed
Records are to be prepared according to requirements of each applicable work instruction or procedure. These records are to be retained as objective evidence that
requirements of the quality system, applicable contracts, standards, specifications, or any other obligation have been met.
By and Checker fields need to be filled out when
sending documents out for either temporary or permanent document.
Parent documents issued as a permanent revision ___ include appendices issued as a temporary revision.
shall not