BUS 140 Chapter 3 (EXAM 1)

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

A combination of effective Gantt chart use and other tactics allowed Delta to cut the average time for a plane layover by what % of the original 60 minute duration? A) 33%, to 40 minutes B) 50%, to 30 minutes C) 20%, to 48 minutes D) 25%, to 45 minutes E) 40%, to 36 minutes

A

A project manager is interested in crashing a project with variable activity times. Which of the following tools should he/she employ? A) PERT B) CPM C) Gantt Chart D) either PERT or CPM E) PERT, CPM, or a Gantt chart are fine

A

Match the following steps in Microsoft's development of Windows 8 to their respective WBS level. Step Level Develop Windows 8 Operating System ? System Testing ? Compatible with Windows 7 ? Develop GUI's ? Module Testing ? A) Level 1, Level 2, Level 4, Level 3, Level 3 B) Level 1, Level 2, Level 3, Level 4, Level 5 C) Level 0, Level 1, Level 2, Level 3, Level 4 D) Level 0, Level 2, Level 2, Level 3, Level 3 E) Level 5, Level 3, Level 4, Level 1, Level 2

A

Two activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _____ should be crashed first, adding ______ to project cost. Activity Normal Time Normal Cost Crash Duration Crash Cost One 8 days $6,000 6 days $6,800 Two 10 days $4,000 9 days $5,000 a. One; $400 b. One; $6,800 c. Two; $1,000 d. Two; $5,000 e. One or two should be crashed; $1,400

A

A project organization that becomes permanent is often referred to as a: A) fixed project organization. B) matrix organization. C) normal organization. D) standard organization. E) permanent project organization.

B

The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate Predecessors A 10 --- B 8 --- C 2 A D 4 A E 5 B,C, D a. A-C; 12 b. A-D-E; 19 c. B-E; 13 d. A-B-C-D-E; 29 e. none of the above

B

The time an activity will take assuming very unfavorable conditions is: A) the optimistic time. B) the pessimistic time. C) the activity variance. D) the minimum time. E) exactly twice as long as the expected time

B

Activity M on a CPM network has predecessors N and R, and has successor S. M has duration 5. N's late finish is 18, while R's is 20. S's late start is 14. Which of the following is true? a. M is critical and has zero slack b. M has no slack but is not critical c. The LS time of S is impossible d. N is a critical activity e. S is a critical activity

C

Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true? A) R is critical and has zero slack. B) R has no slack but is not critical. C) The set of times cannot all be possible. D) N is a critical activity. E) S is a critical activity.

C

The project organization works best when which of the following conditions are satisfied? I. Work tasks can be defined with a specific goal and deadline. II. The job is typical and familiar to the existing organization. III. The work contains interrelated tasks requiring specialized skills. IV. The project is temporary but unimportant to long-term organizational success. V. The project cuts across organizational lines. A) I, II, III, IV, V B) None of the above conditions need to be satisfied. C) I, III, V D) I, II, III, V E) I, III, IV, V

C

Two activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _____ should be crashed first, adding ______ to project cost. Activity Normal Time Normal Cost Crash Duration Crash Cost B 4 days $6,000 3 days $8,000 C 6 days $4,000 4 days $6,000 a. B; $2,000 b. B; $8,000 c. C; $1,000 d. C; $2,000 e. C; $6,000

C

When the length of critical path of a project is 40 days and the variance of the project is 4 days, what due date should be set for this project so that the probability of completing the project is 95%? Since it is on days, round the answer to the nearest higher integer. The z value of 95% is 1.645 A) 41 B) 42 C) 44 D) 47 E) 49

C (1.645=(x-40)/4, x=44)

A project management technique that uses only one time factor per activity

Critical path method (CPM)

The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate Predecessors A 4 --- B 2 A C 7 -- D 4 A E 5 B,C,D a. A-B-D; 10 b. A-B-E; 11 c. C-E; 12 d. A-D-E; 13 e. A-B-C-D-E; 22

D

WBS stands for which of the following project management tools? A) work break schedule B) work breakdown status C) work breakdown schedule D) work breakdown structure E) work break status

D

Which of the following is NOT one of the phases of project management? A) planning B) scheduling C) controlling D) budgeting E) All of the above are project management phases.

D

Which of the following statements concerning CPM activities is false? a. the EF of an activity is the ES of that activity plus its duration b. the LF is the earliest of the late start times of all successor activities c. the LS of an activity is its LF less its duration d. the LF of an activity is the earliest LS of all preceding activities e. the ES of an activity is the latest EF of all preceding activities

D

4) Which of the following projects were completed by Bechtel? A) Hoover Dam B) Boston Central Artery/Tunnel C) Rebuilding Kuwait after Iraq's invasion in 1990 D) Rebuilding Iraq after the U.S. invasion, starting in 2003 E) All of the above were Bechtel projects

E

Ethical issues that may arise in projects large and small include: A) gifts from contractors. B) exaggerated expense reports. C) compromised quality standards to meet bonuses or avoid penalties related to schedules. D) pressure to mask delays with false status reports. E) all of the above.

E

The control of projects involves close monitoring of which of the following? A) resources B) costs C) quality D) budgets E) all of the above

E

The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate Predecessors A 2 -- B 4 -- C 6 A,B D 1 A,B E 2 B,C,D a. A-D-E; 5 b. B-E; 6 c. B-D-E; 7 d. A-C-E; 10 e. B-C-E; 12

E

The difference between AON and AOA networks is that: A) AOA networks sometimes require dummy activities. B) nodes consume no resources or time in AOA networks. C) both are acceptable in practice; however, Microsoft Project uses AON. D) nodes designate activities in AON, while arrows designate activities in AOA. E) All of the above are true.

E

The main difference between PERT and CPM is that: A) PERT is more accurate than CPM. B) PERT assumes that activity durations are known. C) PERT ignores activity costs. D) CPM assumes activity durations can vary. E) PERT employs three time estimates for each activity.

E

Slack time=

LS-ES LF-EF

The network analysis method that allows activity times to vary is ________.

PERT or Program Evaluation and Review Technique

A project management technique that employs three time estimates for each activity

Program evaluation and review technique (PERT)

The ________ has established a code of ethics especially for project managers.

Project Management Institute

Identify each of the purposes of project scheduling

Project scheduling shows the relationship of each activity to others and to the whole project. It identifies the precedence relationship among activities. It encourages the setting of realistic time and cost estimates for each activity. It helps make better use of people, money, and material resources by identifying critical bottlenecks in the project.

________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.

Slack time

What is the basic difference between PERT and CPM?

The basic difference between PERT and CPM is that PERT requires three time estimates of activity completion time, whereas CPM uses only a single estimate.

Describe the differences between a Gantt chart and a PERT/CPM network.

The differences between a Gantt chart and a PERT/CPM network are mainly that PERT/CPM has the ability to consider precedence relationships and interdependence of activities.

What are the three phases of a project? Describe each in a sentence or two.

The three phases are planning, scheduling, and controlling. Planning includes goal setting, defining the project, and team organization. Scheduling relates people, money, and supplies to specific activities and relates activities to each other. Controlling is where the firm monitors resources, costs, quality, and budgets. It also revises or changes plans and shifts resources to meet time and cost demands.

A code of ethics especially for project managers a. has been established by the Project Management Institute b. has been formulated by the Federal government c. has been formulated by the World Trade Organization d. is inappropriate, since everyone should use the same guidance on ethical issues e. does not exist at this time

a

A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days. The sum of all activity variances is 81; the sum of variances along the critical path is 64. The probability that the project will take 130 or more days to complete is a. 0.1056 b. 0.1335 c. 0.8512 d. 0.8943 e. 1.29

a

A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8. a. The critical path is A-B-C, duration 15. b. The critical path is A-C, duration 12. c. The critical path is A-B-C, duration 13.5 d. The critical path cannot be determined without knowing PERT expected activity times. e. The network has no critical path.

a

A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8. a. The critical path is D-E-F, duration 15. b. The critical path is D-F, duration 12. c. Slack at D is 3 units d. Slack at E is 3 units e. Both a and c are true

a

An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 8. Its expected time and variance (if it is a critical activity) are a. 3.67; 1 b. 3.67; 6 c. 4.33; 1 d. 4.33; 6 e. none of these

a

If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500, the crash cost per period is a. $500 b. $750 b. $1,500 d. $13,000 e. $15,000

a

If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, the crash cost per period is a. $400 b. $2,000 c. $10,000 d. $20,000 e. $30,000

a

The phases of project management are a. planning, scheduling, and controlling b. planning, programming, and budgeting c. planning, organizing, staffing, leading, and controlling d. different for manufacturing projects than for service projects e. GANTT, CPM, and PERT

a

Which of the following statements regarding PERT times is true? a. The optimistic time estimate is an estimate of the minimum time an activity will require. b. The optimistic time estimate is an estimate of the maximum time an activity will require. c. The probable time estimate is calculated as t = (a + 4m + b). d. Pessimistic time estimate is an estimate of the minimum time an activity will require. e. Most likely time estimate is an estimate of the maximum time an activity will require.

a

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is a. 0.0228 b. 0.3446 c. 0.6554 d. 0.9772 e. 18

b

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day ______ (rounded to nearest day). a. 98 b. 112 c. 120 d. 124 e. 220

b

A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. a. There are two paths in this network. b. There are four paths in this network. c. There are five paths in this network. d. There are 25 paths through this network. e. None of these statements is true.

b

An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is a. 2 b. 2.33 c. 2.67 d. 8 e. none of these

b

An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is a. 5 b. 5.33 c. 5.67 d. 17 e. none of these

b

In a PERT network, non-critical activities that have little slack need to be monitored closely a. because PERT treats all activities as equally important b. because near-critical paths could become critical paths with small delays in these activities c. because slack is undesirable and needs to be eliminated d. because they are causing the entire project to be delayed e. because they have a high risk of not being completed

b

The _____ distribution is used by PERT analysis to calculate expected activity times and variances. a. Normal b. Beta c. Alpha d. Gaussian e. Binomial

b

The expected activity time in PERT analysis is calculated as a. the simple average of the optimistic, pessimistic, and most likely times b. the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b c. the sum of the optimistic, pessimistic, and most likely times d. the sum of the optimistic, pessimistic, and most likely times, divided by six e. the sum of the activity variances, divided by six

b

The time an activity will take assuming very unfavorable conditions is a. the optimistic time b. the pessimistic time c. the activity variance d. the minimum time e. exactly twice as long as the expected time

b

Which of the following statements about Bechtel is true? a. Even though Bechtel is over 100 years old, the Kuwaiti oil fields was its first "project." b. Bechtel is the world's premier manager of massive construction and engineering projects. c. Bechtel's competitive advantage is supply chain management. d. While its projects are worldwide, its network of suppliers is largely in the U.S. e. All of the above are true.

b

Which of the following statements regarding time-cost tradeoffs in CPM networks is false? a. "Project Crashing" shortens project duration by assigning more resources to critical tasks. b. Crashing sometimes has the reverse result of lengthening the project duration. c. Crashing must consider the impact of crashing an activity on all paths in the network. d. Activities not on the critical path can become critical after crashing takes place. e. All of the above are true.

b

A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, the probability that the project will be completed in 95 days or less is a. -0.4 b. 0.0228 c. 0.3444 d. 0.9772 e. 4.2

b (if need more practice-54)

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is a. near zero b. 0.0126 c. 0.1587 d. 0.8413 e. 2.14

c

A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before day ______ (rounded to nearest day). a. 631 b. 689 c. 807 d. 833 e. 1009

c

Activity M on a CPM network has predecessors N and R, and has successor S. M has duration 5. N's late finish is 18, while R's is 20. S's late start is 14. Which of the following is true? a. M is critical and has zero slack. b. M has no slack but is not critical. c. The last start time of S is impossible. d. N is a critical activity. e. S is a critical activity.

c

The Beta distribution is used in project management to a. determine which activity should be crashed b. calculate the probability that a project will be completed within its budget c. calculate expected activity times d. calculate slack for activities on the critical path e. none of the above

c

Which of the following statements regarding Gantt charts is true? a. Gantt charts give a timeline and precedence relationships for each activity of a project. b. Gantt charts use the four standard spines of Methods, Materials, Manpower, and Machinery. c. Gantt charts are visual devices that show the duration of activities in a project. d. Gantt charts are expensive. e. All of the above are true.

c

Which of the following statements regarding PERT times is true? a. Expected time is an estimate of the time an activity will require if everything goes as planned. b. The optimistic time estimate is an estimate of the maximum time an activity will require. c. The probable time estimate is calculated as t = (a + 4m + b)/6. d. Pessimistic time estimate is an estimate of the minimum time an activity will require. e. Most likely time estimate is an estimate of the maximum time an activity will require.

c

Which of the following statements regarding project management is false? a. Gantt charts give a timeline for each of a project's activities, but do not adequately show the interrelationships of activities. b. A project organization works best for a project that is temporary but critical to the organization. c. Project organization works well when the work contains simple, independent tasks. d. Gantt charts and PERT/CPM are never used together. e. None of the above is true.

c

__ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced

crashing

The ________ is the computed longest time path(s) through a network

critical path

The ________ is a project management technique using only one time factor per activity that enables managers to schedule, monitor, and control large and complex projects.

critical path method or CPM

A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. The probability that the project can be completed between days 108 and 120 is a. -2.00 b. 0.0227 c. 0.1058 d. 0.4773 e. 0.9773

d

A network has been crashed to the point where all activities are critical. Additional crashing a. is unnecessary b. is impossible c. is prohibitively expensive d. may require crashing multiple tasks simultaneously e. can be done, but all critical tasks must be reduced in duration

d

Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is true? a. B is a critical activity. b. C is completed before B. c. D has no slack but is not critical. d. D is critical, and has zero slack. e. All of the above are true.

d

Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline? a. 0.0401 b. 0.4599 c. 0.8056 d. 0.9599 e. near 1.0000, or almost certain

d

Divulging information to some bidders on a project to give them an unfair advantage a. is the same thing as altering a status report b. is bribery c. is permitted by NAFTA d. is known as bid rigging e. is acceptable for private corporations but not for government agencies

d

Which of the following statements concerning CPM activities is false? a. The early finish of an activity is the early start of that activity plus its duration. b. The late finish is the earliest of the late start times of all successor activities. c. The late start of an activity is its late finish less its duration. d. The late finish of an activity is the earliest late start of all preceding activities. e. The early start of an activity is the latest early finish of all preceding activities.

d

Which of the following statements regarding CPM is true? a. The critical path is the shortest of all paths through the network. b. The critical path is that set of activities that has positive slack. c. Some networks have no critical path. d. All activities on the critical path have their LS equal their predecessor's EF. e. All of the above are false.

d

Which of the following statements regarding CPM networks is true? a. There can be multiple critical paths on the same project, all with different durations. b. The early finish of an activity is the latest early start of all preceding activities. c. The late start of an activity is its late finish plus its duration. d. If a specific project has multiple critical paths, all of them will have the same duration. e. All of the above are true.

d

Which of the following statements regarding PERT analysis is true? a. Each activity has two estimates of its duration. b. Project variance is the sum of all activity variances. c. Project standard deviation is the sum of all critical activity standard deviations. d. Only critical activities contribute to the project variance. e. None of the above is true.

d

Which of the following statements regarding critical paths is true? a. The shortest of all paths through the network is the critical path. b. Some activities on the critical path may have slack. c. Every network has exactly one critical path. d. On a specific project, there can be multiple critical paths, all with exactly the same duration. e. The duration of the critical path is the average duration of all paths in the project network.

d

Which of these statements regarding time-cost tradeoffs in CPM networks is true? a. Crashing is not possible unless there are multiple critical paths. b. Crashing a project often reduces the length of long-duration, but noncritical, activities. c. Activities not on the critical path can never be on the critical path, even after crashing. d. Crashing shortens the project duration by assigning more resources to one or more of the critical tasks. e. None of the above is true.

d

A project organization a. is effective for companies with multiple large projects b. is appropriate only in construction firms c. often fails when the project cuts across organizational lines d. is formed to ensure that programs (projects) get proper management and attention e. a and d are both true

e

Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day ______. a. 98 b. 108 c. 109 d. 115 e. 118

e

Ethical issues that may arise in projects large and small include a. bid rigging b. expense account padding c. compromised safety or health standards d. bribery e. All of the above are true.

e

The Beta distribution is used in project management to a. calculate slack on activities not on the critical path b. calculate the probability that a project will be completed within its budget c. calculate pessimistic and optimistic activity times d. determine which activity should be crashed e. none of the above

e

What was the name of the construction project to rebuild the Pentagon after the terrorist attacks on Sept. 11, 2001? a. Project Panther b. Project Pit Bull c. Project Python d. Project Piranha e. Project Phoenix

e

Which of the following statements regarding Bechtel is true? a. Its competitive advantage is project management. b. Bechtel was the construction contractor for the Hoover Dam. c. While helping to rebuild Iraq, Bechtel's crews had to travel under armed escort. d. Bechtel's procurement program is global in nature. e. All of the above are true.

e

a diagram of all activities and the precedence relationships that exist between these activities in a project is a__

network

A(n) ________ divides a project into more and more detailed components.

work breakdown structure or WBS


Kaugnay na mga set ng pag-aaral

PC Pro Chapter 9.1 - Windows System Tools

View Set

Uppers, Downers, and all Arounders (Biomedical Pharmacology EX 2)

View Set

Chapter 12 Economics Gross Domestic Product and Growth

View Set

SIE - Ch. 2 - Practice Questions

View Set

Liver Failure practice questions

View Set

Chapter 1: Collecting and Analyzing Data

View Set

Systems analysis and design exam 2 study guide (chapter 6)

View Set

Module 20: Basic Learning Concepts and Classical Conditioning

View Set