process management

The act of executing and controlling the productive functions of a firm

capcity=

m/activity time 1/processing time

flow rate (in terms of capacity)

minimum between demand rate and process capacity

bottleneck

process with lowest capacity

Demand Rate

the number of flow units that customers want per unit of time

demand rate

the number of flow units that customers want per unit of time

cycle time

the time between completing two consecutive flow units

lead time

the time between when an order is placed and when it is received

Cost of Direct Labor

total wages per unit of time / flow rate per unit of time

efficiency=

capacity used/effective capacity

utilization

how much available capacity is actually used

Efficiency

how much of effective capacity is actually used

cycle time=

1/flow rate

Project Managment

A controlled process of initiating, planning, executing, and closing down a project.

capacity constrained

Demand exceeds supply and the flow rate is equal to process capacity

Average labor utilization

Labor Content/(Labor Content + Idle Time)

effective capacity

achievable level under normal conditions, for an extended time

throughput

aka as flow rate

capacity

amount of input that can go into or the amount of output that can be created by a process, at a given level of resources over a given time period

Flow units waiting in the process without being worked on are often referred to as

buffer inventory

For a process that is ___________ constrained the bottleneck resource will have 100% utilization.

capacity

process capacity

capacity of the bottleneck

maximum capacity is also know as

design or rate capacity

Flow rate can be __________ process capacity (2 answers)

equal to, greater than

True or false: A process that is demand constrained can have utilization of 100%.

false

True or false: The flow rate for a process should be greater than the demand rate

false

utilization=

flow rate/capacity

maximum capacity

highest achievable level under ideal conditions, for a limited time

process analysis

identifies and analyzes all the activities involved in serving one unit of demand or, put differently, in providing one unit of supply

Resources help the flow units to move from being a unit of ________ to a unit of _________

input;output