Chapter 14

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

"Phantom bills" are bills of material for subassemblies that do not exist in reality.

False

Since MRP is quite detailed in nature, it has no influence on the longer-range, less detailed aggregate planning.

False

The Aggregate Plan, derived from the Master Production Schedule, specifies in more detail how much of which products is to be made at what times.

False

The master production schedule is a forecast of demand for families of products.

False

A bill of material lists all components, ingredients, and materials needed to produce one unit of an end item.

True

Gross material requirements do not take into account the amount of inventory on hand.

True

If 100 units of Q are needed and 10 are already in stock, then the gross requirement is 100 and the net requirement is 90.

True

If X consists of one A and one B, and each A consists of one F and two Gs, then A is the "parent" component of G.

True

Lead times, inventory availability, and purchase orders outstanding are among the five things operations managers must know for effective use of MRP.

True

Planning bills of material are bills of material for "kits" of inexpensive items such as washers, nuts, and bolts.

True

The time phased product structure, unlike the bill of material, adds the concept of lead times.

True

When safety stock is deemed absolutely necessary, the usual policy is to build it into the projected on-hand inventory of the MRP logic.

True

The MPS calls for 50 units of Product A and 60 of B. There are currently 25 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. The net requirements for C are a. 115 b. 175 c. 240 d. 690 e. 700

a. 115

Which of the following best describes a gross material requirements plan? a. a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started b. an intermediate range plan for the scheduling of families of products c. a chart illustrating whether capacity has been exceeded d. a table that corrects scheduled quantities for inventory on hand e. a schedule showing which products are to be manufactured and in what quantities

a. a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started

The ______ is the input to material requirements planning which lists the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product. a. bill of material b. master production schedule c. inventory records d. assembly time chart e. net requirements chart

a. bill of material

In continuous (make-to-stock) operations, the master production schedule is usually expressed in terms of a. end items b. modules c. kits d. customer orders e. warehouse orders

a. end items

By convention, the top level in a bill of material is a. level 0 b. level 1 c. level T d. level 10 e. level 100

a. level 0

The ______ is (are) the MRP input detailing which end items are to be produced, when they are needed, and in what quantities. a. master production schedule b. gross requirements c. inventory records d. assembly time chart e. bill of material

a. master production schedule

Each R requires 4 of component S; each S requires 3 of part T. The lead time for assembly of R is 1 week. The lead time for the manufacture of S is 2 weeks. The lead time for the procurement of T is 6 weeks. The cumulative lead time for R is ______ weeks. a. 6 b. 9 c. 12 d. 18 e. 28

b. 9

Which of the following statements is true about the MRP plan when using lot-for-lot ordering? a. The quantity of gross requirements for a child item is always equal to the quantity of planned order releases for its parent. b. The quantity of gross requirements for a child item is equal to the quantity of planned order release(s) multiplied by the number of child items used in the parent assembly. c. The quantity of gross requirements for a child item is always equal to the quantity of gross requirements for its parent. d. The quantity and gross requirements for a child item is always equal to the quantity of net requirements for its parent. e. All of the above are true.

b. The quantity of gross requirements for a child item is equal to the quantity of planned order release(s) multiplied by the number of child items used in the parent assembly.

The phrase "demand related to the demand for other products" describes a. a dependent variable b. dependent demand c. recursive demand d. regression analysis e. independent demand

b. dependent demand

A bill of material must be updated with the corrected dimensions of a part. The document that details this change is a(n) a. modular bill b. engineering change notice c. resource requirements profile d. lead time-offset product structure document e. planning bill

b. engineering change notice

Firms making many different final products use __________ to facilitate production scheduling. a. planning bills b. modular bills c. phantom bills d. overdue bills e. none of the above

b. modular bills

Each R requires 2 of component S and 1 of part T. The lead time for assembly of R is 3 days. The lead time for the manufacture of S is 5 days. The lead time for the manufacture of T is 10 days. The cumulative lead time for R is _____ days. a. 6 b. 9 c. 13 d. 17 e. cannot be determined

c. 13

The MPS calls for 110 units of Product A. There are currently 60 of Product A on hand. Each A requires 4 of Part B. There are 20 units of B available. The net requirements for B are a. 20 b. 120 c. 180 d. 240 e. 440

c. 180

The MPS calls for 110 units of Product M. There are currently 30 of Product M on hand. Each M requires 4 of Component N. There are 20 units of N on hand. The net requirements for N are a. 150 b. 170 c. 300 d. 320 e. 440

c. 300

Each X requires 2 of component Y; each Y requires 4 of part Z. The lead time for assembly of X is 1 week. The lead time for the manufacture of Y is 1 week. The lead time for the procurement of Z is 6 weeks. The cumulative lead time for X is _____ weeks. is a. 6 b. 7 c. 8 d. 10 e. cannot be determined

c. 8

When safety stock is deemed absolutely necessary, the usual policy is to build it into which category of the MRP logic? a. Gross Requirements b. Scheduled Receipts c. Projected On Hand d. Net Requirements e. Planned Order Receipts

c. Projected On Hand

Low level coding means that a. a final item has only a few levels in the BOM structure b. it is the code for the lowest level in the BOM structure c. a component item is coded at the lowest level at which it appears in the BOM structure d. the top level of the BOM is below level zero and that BOMs are not organized around the finished product e. none of the above

c. a component item is coded at the lowest level at which it appears in the BOM structure

A bill of material lists the a. times needed to perform all phases of production b. production schedules for all products c. components, ingredients, and materials required to produce an item d. operations required to produce an item e. components, ingredients, materials, and assembly operations required to produce an item

c. components, ingredients, and materials required to produce an item

Amaterial requirements plan contains information with regard to all of the following except a. quantities and required delivery dates of all subassemblies b. quantities and required delivery dates of final products c. the capacity needed to provide the projected output rate d. inventory on hand for each final product e. inventory on hand for each subassembly

c. the capacity needed to provide the projected output rate

A master production schedule specifies a. the raw materials required to complete the product b. what component is to be made, and when c. what product is to be made, and when d. the labor hours required for production e. the financial resources required for production

c. what product is to be made, and when

Dependent demand and independent demand items differ in that a. for any product, all components are dependent-demand items b. the need for independent-demand items is forecast c. the need for dependent-demand items is calculated d. All of the above are true. e. None of the above is true.

d. All of the above are true.

In job shop (make-to-order) operations, the master production schedule is usually expressed in a. end items b. modules c. kits d. customer orders e. warehouse orders

d. customer orders

In MRP record calculations, the appearance of a negative value for the gross requirements of an end item in a specific time bucket a. signals the need to purchase that end item in that period b. implies that value was scheduled by the MPS c. signals the need for a negative planned order receipt in that period d. is impossible e. All of the above are true.

d. is impossible

A document calls for the production of 50 small garden tractors in week 1; 50 small garden tractors and 100 riding mowers in week 2; 100 riding mowers and 200 garden utility carts in week 3; and 100 riding mowers in week 4. This document is most likely a(n) a. net requirements document b. resource requirements profile c. aggregate plan d. master production schedule e. Wagner-Whitin finite capacity document

d. master production schedule

The number of units projected to be available at the end of each time period refers to a. net requirements b. scheduled receipts c. the projected usage of the item d. the amount projected to be on hand e. the amount necessary to cover a shortage

d. the amount projected to be on hand

Demand for a given item is said to be dependent if a. it originates from the external customer b. there is a deep bill of material c. the finished products are mostly services (rather than goods) d. there is a clearly identifiable parent e. the item has several children

d. there is a clearly identifiable parent

The minimum record accuracy required for successful MRP is approximately a. lower than 90% b. 90% c. 95% d. 97% e. 99%

e. 99%

Which of the following statements regarding the gross material requirements plan is true? a. It shows total demand for an item. b. It shows when an item must be ordered from a supplier or when production must be started. c. It combines a master production schedule with the time-phased schedule. d. It requires several inputs, including an accurate bill of material. e. All of the above are true.

e. All of the above are true.

Which of the following statements best compares modular bills and phantom bills? a. Both pertain to assemblies that are not inventoried. b. There is no difference between the two. c. Both pertain to assemblies that are inventoried. d. Modular bills are used for assemblies that are not inventoried, unlike phantom bills. e. Modular bills represent subassemblies that actually exist and are inventoried, while phantom bills represent subassemblies that exist only temporarily and are not inventoried.

e. Modular bills represent subassemblies that actually exist and are inventoried, while phantom bills represent subassemblies that exist only temporarily and are not inventoried.

The bill of material contains information necessary to a. place an order to replenish the item b. calculate quantities on hand and on order c. convert net requirements into higher level gross requirements d. convert gross requirements into net requirements e. convert (explode) net requirements at one level into gross requirements at the next level

e. convert (explode) net requirements at one level into gross requirements at the next level


Kaugnay na mga set ng pag-aaral

Charles Darwin, "Of the Origins of Species 1859"

View Set

sociology chapter 4 - social class inequality & poverty

View Set

Chapter 39 vehicle extrication and special rescue

View Set

Chapter 1 Early Education Curriculum

View Set

6.REF/defeasnace/ reconveyance/right of redemption/multi-state note/ FHA/203(B)/Home ownership voucher assistance/good neighbor next door/disaster relief/HECM/energy efficiency/MIP/COE/COV/Seller concession/VA cashout refinance/IRRR/NADL/SAH/SHA

View Set