Chapter 4. Activity-Based Costing

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

product

Activities such as research and development that are not dependent on the number of units or batches are ____-level activities.

- increasing the number of cost pools used to accumulate overhead cost. - Using cost pools that are more homogeneous than departmental cost pools. - Using a variety of activity measures to assign overhead costs to products.

Activity-based costing improves the accuracy of product costs by:

- overhead costs are high and increasing and no one knows why - products differ substantially in batch size and the activities they require

Activity-based costing is most likely to be beneficial when:

allocation

An activity measure is a(n) _____ base in an activity-based costing system.

batch

Customer orders are considered to be a(n) ____-level activity.

- may use different allocation bases in different departments - may not assign overhead correctly when a company has a range of products

Departmental overhead rates:

performance within the same industry

The basis of benchmarking is comparing ______.

activity rates

Total cost of each activity divided by the total activity is the computation by _____.

$30 $900,000 /$30,000 = $30

Total estimated manufacturing overhead is $900,000 and total estimated activity is 30,000 machine-hours. The plantwide overhead rate is $ ____ per machine hour.

two

Under activity-based costing, the manufacturing overhead costs are allocated to products via a ____-stage process

overcosts, undercosts

Usually, traditional costing __ high-volume products and __ low-volume products

- A variety of products are made by companies - Direct labor is no longer directly correlated to overhead for many products. - Many tasks are now done with automated equipment

Which of the following are reasons that companies are moving away from a plantwide overhead rate like direct labor?

- The cost in each activity cost pool may not be strictly proportional to its activity measure - The cost of designing and implementing the system may outweigh the benefits of the system.

Which of the following issues needs to be considered when implementing an ABC system?

- products do not all use resources in the same way -traditional costing systems can distort product costs.

Which of the following statements are true?

activity rate

A predetermined overhead rate in an activity based costing system is called a(n) ____ ____

both service and manufacturing companies

ABC can be used in _______.

$6,000 $2 × 3,000 = $6,000

A company's activity rate for the general factory is $2.00 per machine hour. Product A used 3,000 machine hours and 1,000 labor hours. General factory overhead assigned to Product A is ______.

$8 per customer call and $15 per development hour $200,000/25,000 = $8 per customer call $300,000/20,000 = $15 per development hour

A company's total expected overhead for the year is $500,000. Two activity cost pools have been identified: Customer Service with a total cost of $200,000 and a total activity of 25,000 customer service calls; and Product Development with a total cost of $300,000 and total activity of 20,000 development hours. The activity rates are ______.

-heating a manufacturing plant -setting up a computer network -preparing annual reports

Facility-level activities include:

activity based

Focusing on activities to eliminate waste, decrease processing time, and reduce defects is the basis of ______ _____ management.

they fall within the same level in the cost hierarchy

Generally, when simplifying an activity based costing system, activities and costs should only be combined if:

$41 $10 + $15 + $16 = $41

Given direct material cost of $10, direct labor cost of $15, direct-labor based overhead of $12 and Activity-Based Costing overhead of $16, the total cost of the product using Activity-Based costing is $ ______.

activity

In activity-based costing, each cost pool accumulates costs that relate to a single ____ measure in the ABC system.

activity

In activity-based costing, each cost pool accumulates costs that relate to a single ______ measure in the ABC system.

an activity

In activity-based costing, the consumption of overhead resources is caused by:

unit

Power to run production equipment is a(n) ____-level activity.

- ignores other significant causes of overhead - may result in selling products at a loss - may result in overcharging customers for products

using direct-labor hours or another volume based cost driver to assign overhead


Kaugnay na mga set ng pag-aaral

Chapter 6: Crafting Effective Sentences and Paragraphs

View Set

chapter 1 Life skills black book

View Set

Keystone species: keystone predators and ecosystem engineers (exam 4)

View Set

APHG Tests (Afternoon) NOW ITS DONE

View Set