CIS 5800_Chapter 7
planned value PV
also called the budget, is the portion of the approved total cost estimate planned to be spent on an activity during a given period
estimate at completion EAC
an estimated cost of completing a project based on performance to date
Bottom-up estimates
involve estimating the costs of individual work items or activities and summing them to get a project total
EVM earned value management
is a powerful cost control technique that is unique to the field of project management
cost baseline
is a time-phased budget that project managers use to measure and monitor cost performance
earned value EV
is an estimate of the value of the physical work actually completed
Base line
is the budget figure in the original project plan plus approved changes
Estimated time to complete
Original time estimate/SPI
EV
PV to date * RP
Cost variance CV
CV= EV - AC If cost variance is a negative number, it means that performing the work cost more than planned. If cost variance is a positive number, performing the work cost less than planned
Cost performance index CPI
CPI= EV/AC If the CPI is less than one or less than 100 percent, the project is over budget. If the CPI is greater than one or more than 100 percent, the project is under budget.
Estimate at completion EAC
EAC= BAC/CPI
Schedule performance index SPI
SPI= EV/PV IF SPI of one, or 100 percent, means the project is on schedule. If the SPI is greater than one or 100 percent, then the project is ahead of schedule. If the SPI is less than one or 100 percent, the project is behind schedule
Schedule variance SV
SV =EV - PV A negative schedule variance means that it took longer than planned to perform the work, and a positive schedule variance means that the work took less time than planned
Budget at completion BAC
the original total budget for the project
Parametric estimating
uses project characteristics (parameters) in a mathematical model to estimate project costs
WBS
work break down structure
rate of performance RP
is the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity
actual cost AC
is the total direct and indirect costs incurred in accomplishing work on an activity during a given period