CM 1011 final exam part 2

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

"TQM" stands for Terminal Quality Management

false

A Certificate of Substantial Completion should not be recorded at the courthouse.

false

BIM is not a good tool for site planning.

false

BIM is not good for "what if" situations.

false

BIM is two dimensional

false

Changes orders should be seen as an opportunity to make a large profit

false

Corrective action has to wait until the project is completed.

false

Delays in construction are expected and cannot be measured

false

Drafting the contract documents is one of the contractor pre-construction tasks

false

Estimating is used in BIM as a sixth dimension

false

Field observations are useless for tracking quality

false

Goals for the construction team should be set by the superintendent alone

false

Inspection is not needed when determining quality

false

Knowing the contract will not help you when it comes to a change order

false

Our guest lecturer, Rudy Comeaux, works for Turner Industries

false

Palmisano does not use Post-It stickies on its construction projects.

false

Permits are not part of the execution plan

false

Quality is the most important thing for a contractor on a project.

false

Removing and reworking incorrect work costs approximately twice that of doing it right the first time.

false

Retainage is a penalty amount kept by the owner.

false

Substantial completion is when the project is completely paid

false

Testing of materials is part of Quality Assurance, not Quality Control

false

The guest lecturer, John Manion, works for Boh Brothers.

false

The guest lecturers on Technology work for Parkinson Construction

false

The quality of the work force does not impact performance

false

Unforeseen conditions do not justify a change order

false

the status of productivity is unimportant in management of a project.

false

"BIM" stands for Building Information Modeling

true

A change order means accepting more risk.

true

A construction project should be monitored to assure contract compliance.

true

BIM allows building a project in a virtual world before actually building it.

true

BIM is a good tool for communicating with the owner

true

BIM is a good tool for presentations

true

BIM is used mostly in commercial construction

true

Building code inspections are part of Quality Control.

true

Change orders may arise from regulatory compliance

true

Commissioning is part of construction close-out

true

Completion date forecasts are part of management reports.

true

Cost control requires documentation

true

Documentation includes material delivery tickets

true

Equipment is one of the scopes to consider when pricing a change order

true

Final payment is part of contract close-out.

true

It is a good idea to have diversity in abilities on a construction team

true

It is the will to prepare to win that separates success from failure.

true

Key performance indicators measure performance against the goals.

true

One of Palmisano's core markets is restorations

true

One of the objectives of QA/QC is doing the job correctly the first time.

true

Operation and maintenance manuals are part of contract close-out.

true

Palmisano Construction does mostly commercial projects.

true

Palmisano is a design-build / design-assist company

true

Palmisano self-performs concrete work.

true

Palmisano uses Bluebeam for estimating

true

Palmisano uses Primavera P6 for its scheduling

true

Palmisano uses a Job Box on its construction sites

true

ProCore is a construction management program.

true

Punch list is part of construction close-out

true

Quality is "meeting or exceeding the requirements established in the design documents.

true

Quality is determined by the owner's expectations.

true

Quality is meeting the acceptance criteria 100% of the time.

true

Scheduling is used in BIM as a fourth dimension

true

Selection of subcontractors is part of Quality Assurance, not Quality Control

true

Subcontractor performance is important in evaluating project performance

true

Team activities include identifying who has what responsibilities

true

The presenter's first rule regarding changes to the work is "First, do no harm."

true

There are legal implications to consider when doing a change order

true

There are three project close-out reports

true

Time is one of the scopes to consider when pricing a change order.

true

Training is part of Quality Assurance, not Quality Control

true

when the plan doesn't work, stop and re-plan.

true


Kaugnay na mga set ng pag-aaral

4.2-Change Active Voice to Passive Voice

View Set

Digital Library Development Tech Terms

View Set

Net Present Value and Other Investment Criteria

View Set

Principles of Accounting - Chapter Five Study Guide

View Set