Construction Operations Exam #2
Which document issued by the Architect illustrates what is to be built? b. Shop Drawings. c. Product Data Sheets. d. Schematics Drawings.
a. Plans.
Refer to chart PUC 1. How many days (whole) are required to install 12,000 S.F.C.A.? a. 9 b. 22 c. 200 d. 1500
b. 22
Which document applies to the Contractor and the Subcontractors and describes the administrative, procedural and temporary procedures on the job site? a. General Conditions. b. General Requirements. c. Instructions to Bidders. d. Supplementary Conditions.
b. General Requirements.
Which document contains a description of the alternate(s)? a. General Conditions. b. General Requirements. c. Instructions to Bidders. d. Supplementary Conditions.
b. General Requirements.
Which document describes the business procedures for a specific project and they change the initial procedures? a. General Conditions. b. General Requirements. c. Instructions to Bidders. d. Supplementary Conditions.
d. Supplementary Conditions.
Which document describes the duties and responsibilities of each party and the business procedures for administering the contract? a. General Conditions. b. General Requirements. c. Instructions to Bidders. d. Supplementary Conditions.
a. General Conditions.
Which of the following documents is normally incorporated by reference? a. General Conditions. b. General Requirements. c. Instructions to Bidders. d. Supplementary Conditions.
a. General Conditions.
Which document specifies the Regulations required such as soil erosion or minorities? a. General Requirements. b. Technical Specifications. c. Supplementary Conditions. d. Information Available to Bidders.
a. General Requirements.
Which document specifies the temporary facilities needed on a project? a. General Requirements. b. Technical Specifications. c. Supplementary Conditions. d. Information Available to Bidders.
a. General Requirements.
Which of the following documents are submitted by the Contractor at bid opening? a. Proposal Form, Bid Breakdown, Addendum, Bid Bond & Noncollusive Affidavit. b. Proposal Supplements, Performance Bond, Payment Bond & Insurance certificate. c. Prequalification Forms, Alternates, Cash Allowances, Prevailing Wages, Deposit. d. Agreement, Regulatory Requirements, Shop Drawings, Product Data & Samples.
a. Proposal Form, Bid Breakdown, Addendum, Bid Bond & Noncollusive Affidavit.
Refer to chart PUC 1. What is the Total Crew Cost per day? a. $746.08 b. $1,423.36 c. $2,071.36 d. $5,595.60
b. $1,423.36
Refer to chart PUC 1. What is the Labor Cost per S.F.C.A. ($L/S.F.C.A.)? a. $0.06 b. $2.61 c. $23.72 d. $177.92
b. $2.61
Refer to chart PUC 1. What is the Productivity Rate expressed in Workhours per Unit (Whr/Unit)? a. 00.059 b. 00.110 c. 09.083 d. 17.031
b. 00.110
Refer to chart PUC 1. How many total workhours are required to install 12,000 S.F.C.A.? a. 708 b. 1,320 c. 65, 400 d. 108,996
b. 1,320
What does the Means Book unit of measure abbreviation Sq. stand for? a. Square inches. b. One Hundred Square Feet. c. One-hundred Square inches. d. One thousand Square Feet.
b. One Hundred Square Feet.
What does the Means Book unit of measure abbreviation C stand for? a. Ten. b. One hundred. c. One thousand. d. One Million.
b. One hundred.
What does the Means book unit of measure abbreviation M.B.F. stand for? a. One-hundred Board Feet. b. One-thousand Board Feet. c. One-million Feet. d. One-million Board Feet.
b. One-thousand Board Feet.
What does the Means Book unit of measure abbreviation V.L.F. stand for? a. Five Lineal Feet. b. Vertical Lineal Feet. c. Volume Lineal Feet. d. Vinyl Lineal Feet.
b. Vertical Lineal Feet.
Refer to chart PUC 2. What is the Equipment Cost per Cubic Yard ($Eq/CY)? a. $ 0.01 b. $ 2.91 c. $ 5.34 d. $57.23
c. $ 5.34
The plans call for you to purchase 4 x 4 - W2.9 x W 2.9 (6x6) of Welded Wire Fabric for a reinforced concrete bridge deck. The estimated quantity is 13,200 Square Feet (SF). The agreed upon purchase price is $18.30 per CSF. What is the Total Materials costs to purchase? a. $241.56 b. $721.31 c. $2,415.60 d. $241,560.00
c. $2,415.60
Refer to chart PUC 1. What is the Total Labor Cost for installing the 12,000 S.F.C.A.? a. $720.00 b. $1,440.00 c. $31,320.00 d. $284,640.00
c. $31,320.00
Refer to chart PUC 1. How many total crew workhours are expended per day? a. 28 b. 32 c. 60 d. 100
c. 60
Refer to chart PUC 1. What is the productivity rate in S.F.C.A. per Workhour? a. 0.045 b. 0.110 c. 9.083 d. 68.130
c. 9.083
Which document establishes the forms, content and procedures for submitting the bid proposals? a. General Conditions. b. General Requirements. c. Instructions to Bidders. d. Supplementary Conditions.
c. Instructions to Bidders.
What does the Means book unit of measure abbreviation C.S.F. stand for? a. Cubic Square Feet. b. Contact Square Feet. c. One-hundred Square Feet. d. One-thousand Square Feet.
c. One-hundred Square Feet.
What does the Means Book unit of measure abbreviation S.F.C.A. stand for? a. Square Feet Continuous Area. b. Square Feet Cubic Area. c. Square Feet Contact Area. d. Square Feet Critical Area.
c. Square Feet Contact Area.
What is the term called which requires all Bidders to include in their bid a specified amount or unit price for a particular item? a. Plug. b. Alternate. c. Contingency. d. Cash Allowance.
d. Cash Allowance.
What types of projects establish prevailing wage rates? a. Union projects. b. Merit Shop Projects. c. Privately Funded Projects. d. Federally Funded Projects.
d. Federally Funded Projects.
Which document specifies the existing soil conditions? a. General Requirements. b. Technical Specifications. c. Supplementary Conditions. d. Information Available to Bidders.
d. Information Available to Bidders.