The Owner wants to Fast-Track a construction project., Which project delivery system best supports this process? Partnering Design-Bid-Build Design-Build SoleOwnership
Design-Bid
Which statement is true about the Design-Build delivery method? Design is complete when contractor is involved Fast tracking is difficult with this delivery method There is a sole source for fault for building system failures Most DB firms are temporary affiliation created for a single project
There is a sole source for fault for building system failures
T or F: A design firm and a construction company can team up to bid a D/B contract
True
T or F: An important advantage of the D/B delivery system is that construction can start while design is proceeding
True
T or F: In the D/B delivery system, the owner signs a single contract with the D/B firm rather than separate contracts with a designer and a contractor
True