IT Project Management Chapter 4 Quiz
A Gantt chart is the same as a project management plan.
False
A SWOT analysis, being a linear process, cannot be performed using the nonlinear mind mapping technique.
False
A project charter typically does not authorize the project manager to use organizational resources to complete the project.
False
An organization should consider only projects with a negative NPV if financial value is a key criterion for project selection.
False
An organization's information technology project selection process should guide the strategic plan.
False
Corrective actions reduce the probability of negative consequences associated with project risks, while preventive actions should result in improvements in project performance.
False
Many projects fail because of unclear requirements and expectations, so starting with a payback analysis makes a lot of sense.
False
Opportunities and directives are essentially the same thing.
False
Project integration management must occur just within the context of a particular project.
False
The ROI is always positive.
False
The number of interfaces in a single project is limited, and does not depend on the number of people involved in the project.
False
The organization should complete low-priority projects before high-priority ones, if the low-priority ones take less time.
False
In project integration management, directing and managing project execution involves carrying out the project management plan by performing the activities included in it.
True
Information systems can help an organization support a strategy of being a low-cost producer.
True
NPV analysis is a method for making equal comparisons between cash flows for multi-year projects.
True
Organizational process asset updates are an important output of the closing process of a project.
True
Payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project.
True
Projects that arise as a result of problems and directives must be resolved quickly to avoid hurting an organization's business.
True
Some organizations initiate projects using a contract in place of a project charter.
True
A summary of the planned approach for managing the project should describe stakeholder needs and expectations, important assumptions, and constraints.
True
An annual discount factor is a multiplier for each year based on the discount rate and year.
True
As projects progress, the organization must reevaluate the need, funding, and will for each project to determine if the project should be continued, redefined, or terminated.
True
Change requests are always made in writing.
True
Interface management involves identifying and managing the points of interaction between various elements of a project.
False
It is necessary that IT project managers have prior technical experience in creating and managing IT products.
False
Projects that address broad organizational needs are likely to fail.
False