Operations Management Chapter 4: quiz

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

True or false: it is not possible to have a process chance project that accommodates a large amount of change.

false

True or false: there are relatively few project management software options for practitioners.

false

A project has how many critical paths?

it is possible to have multiple critical paths

A big competitor to Microsoft Project is ____

Primavera Project Planner

Treu or false: the hierarchy of project tasks, subtasks and work packages is known as a work breakdown structure.

True

True or falsE: When all the activities are completed, the project is finished.

True

True or false: a benefit of using three time estimates is that it allows you to estimate whether or not a project will be done by a certain date.

True

What is the major assumption when determining the cost per unit of time to expedite each activity?

a linear relationship between time and cost

The _____ activity time is calculated using a weighted average of a minimum, maximum, and most likely time estimate.

estimated

In the following identification of Activity C, the number represents which of the following? C(4)

expected duration

When working on time-cost trade-off projects, which of the following pieces of information is not required?

expected time

The cost associated with sustaining a project are referred to as ___

indirect costs

The costs associated with sustaining a project are referred to as ____

indirect costs

How many immediate predecessors does an activity have?

it depends on the project

When calculating the slack time of an activity, it is the difference between an activity's _____

late start and early start times

Which of the following is NOT a form of a matrix project?

major

When crashing a project, the first activity your crash should be ____

on the critical path with the lowest crash cost per day

Which of the following is not a direct activity cost?

overhead

All of the following are constraints addressed in project management except _____

people

A specific event the should be reached at a certain point in time are often referred to as _____

project milestones

What term best describes the written description of the objectives to be achieved in a project?

statement of work

When breaking down a project, what term is used to describe these subdivisions?

task and subtests

The critical path is ___

the longest chain of activities in a project

In a project, which of the following has the shortest duration?

work package

What term describes the group of activities assigned to a single organizational unit?

work package

Which of the following are required for a project? Check all that apply.

1. Series of related jobs 2. requiring a significant period of time 3. having a major output

What are the essential features of any earned value management (EVM) system? Check all that apply.

1. a valuation of each activity work 2. predefined earning or costing rules to quantify the accomplishment of work 3. a project plan that identifies the activities to be accomplished

What are the points in time that we need to calculate for each activity in the project?

1. late finish time 2. late start time

Which of the following are disadvantages fo the functional project organizational structure? check all that apply.

1. needs of the client are secondary and are responded to slowly 2. aspects of the project unrelated to the functional area get shortchanged 3. motivation of team members is often weak

Which of the following are advantages of a pourers project? Check all that apply.

1. the project manager has full authority over the project 2. lines of communication are shortened 3. team pride, motivation, and commitment are high 4. team members report to one boss

The expected completion time is computed as a+xm+b/y. What are the values of X and Y respectively.

4,6

When calculating the probability of project completion, you use the sum of variances of _____ in the denominator.

activities on the critical path

the early finish is calculated by ___

adding the early start and duration

Gantt charts show which of the following?

amount of time and sequence of activities

When calculating activity variance, what is X in the following calculation? (x/6)^2

b-a

At what point in the project planning process is the organizational structure of the project decided?

before the project begins

The compression or shortening of the time to complete a project is referred to as ______.

crashing

A schedule that lists all activities by their early start times is a(n) ___

early start schedule

A schedule that lists all activities by their early start times is a(n) ____

early start schedule


Kaugnay na mga set ng pag-aaral

GA-Introduction to Healthcare Science(First half)

View Set

Early Childhood Education II EOC test review

View Set