Prince2 questions

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

Which of these statements are the purposes of IP?

Establishes solid foundation for the project Ensures there is clear understanding of the work involved to deliver the project's products Avoids commitment of funds before it is appropriate to do so

What type of control is an end stage assessment?

Event-driven

Which products should have their own configuration item record?

Every configured item

When is the project plan baselined?

Every time the PID is approved and baselined

Which item is a PB control point?

Exception assessment

When a major deviation to a stage plan is forecast, what contains the PM's description of the deviation, its consequences and a list of options?

Exception report

In which activity are checkpoint reports created?

Execute a work package

Review work package status receives information on work package status from which of these activities?

Execute a work package

Which roles should NOT be combined?

Executive and project manager

What is NOT a recommended response type to respond to a threat?

Exploit

The PB meeds to consider an exception report at an exception assessment? TRUE OR FALSE

FALSE

Which principle is being applied when a project product description is produced?

Focus on products

What is the reason for an exception assessment in Prince2?

For the PB to review and approve an exception plan

What is a product description used for in the CS?

Forming part of a work package passed to a supplier for creation

In describing how to define management stages, the Prince2 manual talks of balancing a number of elements. Which of the following is NOT one of them?

Frequency of highlight reports

What time-driven control advises the PB of the status of the stage?

Highlight report

Which regular report provides the project board with a summary of stage status?

Highlight report

Which report contains details of requests for change?

Highlight report

Which of the following quality measures is covered in IP?

How quality will be achieved

Which information appears in the business case?

How the project is to be funded

In which process is the risk register created?

IP

The quality management approach is written in which process?

IP

When is the issue register created?

IP

When is the risk register created?

IP

Which of the following is NOT a type of issue addressed within the change theme?

Identification of a new risk

Which is a minimum requirement for applying the risk theme?

Identified threats and opportunities must be documented

What is the first step in the recommended risk management procedure?

Identify

Which is a step in Prince2's recommended approach to planning?

Identify activities and dependencies

When should the project board request a decision from corporate, programme management or customer?

If it is forecast that project level tolerance will be exceeded

Where is the type of quality check required for a product defined?

In the product description

What does the 'initiating a project' process provide?

Information for the project board to decide if the project is aligned to business objectives

The purpose of the [?] process is to establish solid foundations for the project

Initiating a project

Which process aims to ensure that during the project all parties understand the project objectives?

Initiating a project

Which process provides the project board with the information it requires in order to commit resources to the project?

Initiating a project

Which management stages must a Prince2 project consist of, as a minimum?

Initiation, and at least one other stage for the rest of the project

Which product keeps track of requests for change?

Issue register

What other products are reviewed and updated at the end of each stage apart from the business case and project plan?

Issue/risk register

Which two statements about the risk theme are CORRECT?

It aims to support better decision-making through a good understanding of threats and opportunities and it explains the risk management activities to use to improve the chances of a project delivering its objectives

Which statement about the project support role is CORRECT?

It can be performed by the project manager

Which statement describes the 'directing a project' process?

It enables the project board to assure that there is continued business justification

What makes a project a Prince2 project?

It has project processes that satisfy the objectives of Prince2 processes

Which characteristic distinguishes a project from regular business operations?

It introduces business change

Which is a characteristic of a project?

It involves cross-functional teams

Which statements apply to a stage plan?

It is produced close to the time when the planned events will take place and it provides the basis for day-to-day control by the project manager

How is the PID used during the 'closing a project' process?

It is used as the basis for comparing the original aim of the project against what was actually achieved

Which is a feature of Prince2?

It promotes continual learning in organizations

Which two statements describe a highlight report?

It provides a summary of the stage status and it is used by the project board to monitor the progress of the stage and project

Which is a benefit of using Prince2?

It provides established and proven best practice and governance for project management

A management stage can be longer when risk is [?], typically in the middle of projects

Lower

Controlling a stage drives which other process on a frequent, iterative basis?

MP

Apart from initiating a project in which of these processes is the business case updated?

Managing a stage boundary

Approval for developed specialist products is formally obtained as part of which process?

Managing product delivery

In which process are team plans produced?

Managing product delivery

Which process is used by a TM to coordinate work on one or more of the project's products?

Managing product delivery

What would you NOT find in a business case?

Names of people responsible for achieving the benefits

After first stage, when are the stage plans for further stages produced?

Near the end of the current stage

What is NOT included in the PID?

Next stage plan

Can a product description be changed, once it has been baselined?

Only via change control

What takes place during the 'closing a project' process?

Ownership of the project's products is transferred to the customer

Which project management team role can trigger a premature closure of a project?

PB

What document is input to the PB with a request to deliver the project?

PID

What is an input into DP?

PID

Which document provides the basis for all PB decisions that need to be made during the project?

PID

Which product forms the 'contract' between PM and PB?

PID

Who is primarily responsible for executing the CS?

PM

Quality [?] defines the type of quality methods the project will use

Planning

What is described in Prince2 as the backbone of the management information system required for any project?

Plans

The Prince2 approach to project management is...

Process-based

Which is one of the four integrated elements within Prince2?

Processes

Which two statements about tailoring are CORRECT?

Processes can be simplified or carried out in more detail and terminology can be changed to suit organisational standards

Which activity can take place within the 'managing a stage boundary' process?

Produce an exception plan

Which is part of quality control?

Produce quality records to show that the planned quality activities have been carried out

In which management product are the measurable quality criteria for a product defined?

Product description

Deciding whether a stage has completed successfully can be a problem where a management stage ends part way through one or more delivery steps. Which Prince2 product helps to solve this problem?

Product descriptions

Which product provides the version number of all products in a particular stage?

Product status account

Which of the following techniques is part of Prince2?

Product-based planning

A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives

Progress

The purpose of which theme is to establish ways to monitor and compare actual achievements against those planned?

Progress

Which theme establishes mechanisms to monitor and compare actual achievements against those planned?

Progress

All members of the PB have responsibilities for...

Project Assurance

Which role advises on suitable reviewers for each quality review?

Project Assurance

With whom should a TM consult about the need for extra quality reviewers?

Project Assurance

If the project needs staff to handle the use of specific planning and control software, they would be part of which group?

Project Support

Which of the following contains the decision on whether a project's solution will be bought off the shelf?

Project approach

The way in which the work will be conducted is determined when preparing which product?

Project brief

Tolerances for the project as a whole ideally should first appear in which management product?

Project brief

What is the name of the product that advises all those who have provided resources that the project is coming to an end?

Project closure notification

Which of the following must be included in the project brief?

Project definition

Which option is extracted from the project brief to become part of the PID?

Project definition

Which subject must be described in the project brief?

Project definition

What happens when a Prince2 project's work has been completed?

Project is disbanded

Who is responsible for documenting any tailoring of work packages?

Project manager

Which roles CANNOT be combined with the role of project assurance?

Project manager and project support

What is NOT created during the Prince2 process model?

Project mandate

Threats or opportunities should be estimated in terms of...

Project objectives

Which are Prince2 levels of plan?

Project plan, stage plan and team plan

First product created in product-based planning?

Project product description

What is a purpose of the project brief?

Provides a firm basis on which to initiate the project

Which management product should always be updated when a product fails its quality check?

Quality register

How is the PPD used in IP?

Refined when creating the project plan

In which activity of controlling a stage is the risk register NOT updated?

Report highlights

What is defined within the organisation theme?

Responsibilities for directing, managing and delivering the project

Which of these is NOT a valid step in the risk management procedure?

Review

Which of these is a specific objective of an end stage assessment?

Review and approve any new product description(s)

What takes place within the SB?

Review of the business justification for the project

Which activity gathers details of progress?

Review work package status

Which role is responsible for the management of a risk assigned to it?

Risk owner

What is included in the project brief?

Role descriptions, project approach and project definition

Acceptance criteria are defined in which process?

SU

Which process turns a project mandate into a project brief?

SU

Which aspect of project performance must be managed in order to have a clear understanding of what the project is to deliver?

Scope

What must be used, as a minimum requirement for applying the progress theme?

Stage authorisation

What should be provided by corporate, programme management or customer before the 'starting up a project' process commences?

Sufficient information to identify the prospective executive

Which is a purpose of an End Stage Report?

Summarise progress to enable the PB to decide what action to take next

In a Prince2 project the team plan is produced by which role?

TM

A stakeholder is anyone who thinks they will be affected by a project and a stakeholder may be internal or external to the corporate organisation

TRUE

Quality assurance provides assurance to the corporate, programme or the customer organisation whereas Project Assurance provides assurance to the project's stakeholders

TRUE

The project brief contains the reasons for the project and the project objectives

TRUE

What should be provided by a project mandate?

Terms of reference for a project

What does applying the 'manage by stages' principle ensure?

That the project is properly initiated before work begins on delivery of the project's outputs

Which of the following does NOT occur as part of IP?

The Executive and PM are appointed

Who sets the tolerance for a stage plan?

The PB

What must be recorded in the quality management approach, as a minimum requirement for applying the quality theme?

The approach to managing project assurance

What should be reviewed as part of authorise a work package?

The appropriate product descriptions

From whom does a TM obtain approval for a completed product?

The authority defined in the Product Description

In Prince2 what is the name of the product that is used to define the information that justifies the setting up, continuation or termination of the project?

The business case

Which two statements about the 'continued business justification' principle are CORRECT?

The business justification for a project should be documented & compulsory projects still require business justification

Which statement about the 'continued business justification' principle is CORRECT?

The chosen option must provide value for money

What is established within the 'initiating a project' process?

The formats for communicating project information to stakeholders

What other product(s) is reviewed and updated at the end of each stage apart from the risk register and business case?

The issue register and the quality register

What group creates, maintains and monitors the use of a quality management system?

The organisation sponsoring the work

What must be recorded in the PID to meet the minimum requirements for applying the progress theme?

The overall approach to managing by exception

Who does the senior user represent when making decisions?

The people or organisations that benefit from using the project's product

The decision on whether a project's solution will be developed in-house is made in...

The project approach

Prince2 requires that the business justification is formally verified by [?] at stage boundaries

The project board

In which management product is the choice of solution the business will use to deliver the business option selected?

The project brief

What is updated at the end of every stage to reflect progress already made, any agreed changes in circumstances, any revised forecast of cost and duration?

The project plan

Which is a benefit of applying the 'manage by stages' principle?

The project will have review and decision points so that progress can be assessed

The Chair of a specific quality review is first identified where?

The quality register

What is a project outcome?

The result of the change derived from using the project's outputs

Which describes the 'implement' step within the recommended risk management procedure?

The risk owner and the risk action carry out activities to control and deal with the risk

Inputs to DP are the project brief and which other product?

The stage plan (initiation)

Which statement about management stages is CORRECT?

There can be more than one delivery step within a management stage

Tolerance may be set for what?

Time and cost

Is a checkpoint report time-driven or event-driven?

Time-driven

Which is a responsibility of the change authority?

To approve or reject requests for change within the delegated limits

Which is an objective of the 'closing a project' process?

To check that all the project's products have been accepted by the users

Which is an objective of the 'starting up a project' process?

To confirm that there are no known restrictions that would prevent the project from being delivered

Which is a purpose of the quality theme?

To define how the project will ensure that its products are fit for purpose

Which is a minimum requirement for applying the organisation theme?

To define the approach to engaging with stakeholders

Which is a purpose of the plans theme?

To define the means of delivering the products

Which is a minimum requirement for applying the quality theme?

To define the project's approach to project assurance

Which is a purpose of a quality management approach?

To define the quality standards to be applied to a project

Which is a purpose of the organisation theme?

To define the structure of accountability and responsibilities on the project

Which is a purpose of the risk management approach?

To define the techniques to be used when assessing project risks

In a customer/supplier context, which is a responsibility of a supplier?

To deliver the outputs of the project

Which is a purpose of the 'starting up a project' process?

To do the minimum to decide whether it is worthwhile initiating the project

Which is a purpose of a project brief?

To document a common understanding of the starting point for the project

Which is a minimum requirement for applying the business case theme?

To document the responsibility for defining the standards for the business case

Which is a purpose of the 'directing a project' process?

To enable overall control of a project by the project board

Which is a purpose of the change theme?

To ensure any potential changes to baselined products are controlled

Which is a minimum requirement for applying the organization theme?

To ensure that all the responsibilities of the project board are fulfilled

Which is a purpose of the 'starting up a project' process?

To ensure that the prerequisites for initiating the project are in place

Which is a responsibility of the managing level within the project management team?

To ensure that the products are produced within the constraints agreed with the project board

Which is an objective of the 'managing product delivery' process?

To ensure that work on products is authorised

Which is a purpose of the business case theme?

To establish methods to judge whether the ongoing project is justified

Which is an objective of the quality review technique?

To involve key interested parties in checking the product's quality and in promoting wider acceptance of the product

Which is a purpose of the quality theme?

To look for ways to improve the effectiveness of the management of the project

In which situation might the 'controlling a stage' process be used?

To manage a long initiation stage of a complex project

Which is a purpose of the 'closing a project' process?

To provide a fixed point at which acceptance of the project product is confirmed

Which is a purpose of the CP?

To provide a fixed point at which acceptance of the project product is confirmed

Which is a purpose of the benefits management approach?

To provide a schedule for measuring the achievement of benefits

Which is a minimum requirement for applying the risk theme?

To record identified threats in a risk register

Which is an objective of the 'managing a stage boundary' process?

To request authorisation to start the next stage

Which is an objective of the 'managing a stage boundary' process?

To review and, if necessary, update the project initiation documentation

Which is assumed to be the customer's responsibility in the Prince2 customer/supplier environment

To specify the desired result

Which is an objective of the 'initiating a project' process?

To summarise how the organisation's project management method will be tailored for the project

Which is a purpose of the 'controlling a stage' process?

To take action so that the stage remains within tolerance

What is likely to be avoided by applying the 'tailor to suit the project' principle?

Unnecessary management effort

When are tolerances for a Work Package agreed?

When accepting a Work Package

What is defined when deciding how to tailor Prince2 to suit the project?

When the project's progress will be reviewed

Which product is used by the PM to authorise work?

Work Package

Given that producing a PBS and product flow diagram are two of the four steps of product-based planning, which one of the following is a third?

Writing a product description for each product

What purpose does the benefits management approach fulfil after the project has closed?

- As a reference for who will undertake the review activities - To define what benefits assessments need to be undertaken - Establishes a baseline from which the improvements will be measured

What is a reason for tailoring Prince2?

- Ensuring project's controls are based on project's scale - Ensuring the method is related to the project's environment

Which type of issue should be raised if a new product is required after a team has started work?

A request for change

What must be produced, as a minimum requirement for applying the plans theme?

A hierarchy of all the products to be produced during a plan

What is a risk cause?

A known situation which creates uncertainty

What is an exception plan?

A replacement for the plan that can no longer finish within agreed tolerances

Which statement about project stakeholders is CORRECT?

All three principle categories of stakeholder have their interests represented by the project board

Which action is NOT taken by the PB?

Allocate tolerance to specialist teams

A project is a temporary organisation that is created for the purpose of delivering one or more business products according to

An agreed business case

Which statement describes a threat to a project?

An uncertain event that could have a negative impact on objectives

Which is an output?

Any of the project's specialist products

In a Prince2 project, who is empowered to raise issues?

Anyone with an interest in the project/outcome

Which fact is true of Project Assurance but not quality assurance?

Appointed as part of the project management team

Which one of these is NOT a key criterion for producing a product flow diagram?

Are the product clearly and unambiguously defined?

When should the team manager product a checkpoint report?

At a frequency agreed in the work package

When is an exception plan reviewed by the PB?

At an exception assessment

Once the PID has been approved, when can the PB close the project down?

At any time

When can the PB close a project down?

At any time

When would the PB first confirm the CQE?

Authorising initiation

Which is a reason why the 'defined roles and responsibilities' principle must be applied?

Because more than one function may be involved in the project

What does project management wish to control?

Benefits

The six aspects of project performance to be managed are [?], costs, timescales and scope

Benefits, quality, risk

How does Prince2 suggest resolving the problem where the desired management stages do not coincide with the technical stages?

Breaking down the deliver step so that it can be divided over two management stages

How does defining a product's quality requirements support the 'focus on products' principle?

By providing an explicit understanding of what the project must deliver

If a work package is forecast to exceed its tolerances, how should a team manager inform the project manager?

By raising an issue

How is the 'learn from experience' principle applied?

By reviewing the management of previous projects

How is the 'manage by exception' principle applied?

By setting controls to warn the higher level of management of potential problems

Which process produces operational and maintenance acceptance of products?

CP

In which process would a concern about the amount of stage tolerance remaining be recorded in the issue register?

CS

Which process handles the day-to-day management of the project?

CS

Which is a possible responsibility of Project Assurance?

Checking that the focus on business need is maintained

Which is a specific responsibility of Project Assurance?

Checking that the right people are being involved

When should the 'managing a stage boundary' process be undertaken?

Close to the end of each management stage

Prince2 management stages relate to [?], which is a factor that differentiates them from delivery steps

Commitment of resources

Which document is used to identify interested parties that need to be informed of project closure?

Communication management approach

Which of the following forms part of the PID?

Communication management approach

What name is given to an off-specification accepted by the PB without corrective action?

Concession

How does the authorisation of initiation support the defined roles and responsibilities principle?

Confirms that all members of the project team have agreed their roles

How does CP support the focus on products principle?

Confirms that the project's products have been accepted

Any change to the products agreed at the start of a stage is monitored as part of the [?] process, on a day-to-day basis

Controlling a stage

What is the purpose of the MP?

Controls the link between the PM and the TM

Who sets project tolerances?

Corporate, Programme Management or the Customer

Which of the following does project management wish to control?

Costs and timescales

Which is a task of 'defining and analysing products'?

Create the product flow diagram

What is a responsibility of the PM?

Create the risk management approach

Which process ensures that plans for achieving the expected benefits are managed and reviewed?

Directing a project

Which process is triggered by the project manager's request to initiate a project?

Directing a project

When is it confirmed whether a project's objectives have been achieved?

During the 'closing a project' process

In which process are decisions made on exception situations?

DP

Which process covers key decision-making of the project?

DP

What must the project board do, as a minimum requirement for applying the change theme?

Define a change authority

What is a purpose of the risk management approach?

Define techniques to be used when assessing project risks

In which process is authorisation given to deliver the project's products?

Directing a project


Kaugnay na mga set ng pag-aaral

Psychobiology and Psychopharmacology

View Set

Water, Electrolytes, and Carbohydrates

View Set

MSSC-Q02 Quality Practices Dimensional Measurement

View Set

Property II -- Practice Questions

View Set