Project management MS Project 2016 Tutorial Video - Precedence, Duration, and Critical Path Using MS Project
How are task precedence relationships between predecessor and successor tasks built? a. The chain-link icon in the Schedule group b. The pushpin icon in the Tasks group c. The plus icon in the Schedule group d. By double-clicking on the summary task
a. The chain-link icon in the Schedule group
How can the critical path color be modified? a. From the critical path options subgroup b. By formatting the critical path bar style c. By right clicking on the critical path and choosing "format color" d. The critical path color cannot be modified
b. By formatting the critical path bar style
What is the purpose of the Predecessor column? a. It shows the WBS code of the previous task b. It shows the task ID number of the previous task c. It shows the predecessor code for the most useful tasks d. It shows the predecessor code for critical path tasks
b. It shows the task ID number of the previous task
How are task precedence relationships removed? a. By right clicking a task and choosing "remove relationship" b. By double clicking a summary task for the relationship c. By deleting the task ID number from the predecessor column d. By choosing "remove relationship" from the Tasks group
c. By deleting the task ID number from the predecessor column
How is the critical path displayed on the Gantt Chart? a. The critical tasks checkbox b. The critical path can't be shown on a Gantt Chart c. Right click on the critical path summary task and choose "show path" d. All critical path tasks must be marked as "important"
IT IS NOT! c. Right click on the critical path summary task and choose "show path"