Project+ quizzes

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

Activity G has a late finish (LF) of eighteen days and an early finish (EF) of three days. Activity E follows Activity G. Activity E has an early start (ES) of six days. What is the free float (FF) for Activity G? A. 3 days B. 12 days C. 15 days D. 21 days

A. 3 days The calculation of the FF of Activity G = ES of Activity E - EF of Activity G = 6-3 = 3 days.

Which of the following is the most critical for the project manager (PM) to share with leaders to obtain approval to start a project and secure funding and resources? A. A business case B. An executive summary C. A problem statement D. A problem analysis

A. A business case

A potential vendor is reviewing a request for proposal (RFP) and statement of work (SOW) for a new project. The project manager (PM) wrote the SOW as a functional SOW outlining the requirements of the finished product only. In response to the RFP, what would be suitable for the vendor to address since the PM provided a functional SOW? (Select all that apply.) A. A creative approach used in a previous project with a similar deliverable B. An alternative product completed for a previous project containing the same design specifications C. A list of prior performances building the same product to demonstrate a variety of approaches D. A list of requirements the vendor thinks the final product should include to improve it

A. A creative approach used in a previous project with a similar deliverable C. A list of prior performances building the same product to demonstrate a variety of approaches

What is the main difference between a procurement contract and a purchase order (PO)? A. A procurement contract establishes an agreement to purchase something at some point, while a PO is a customer's request for specific goods or services. B. A procurement contract defines the terms of a vendor-buyer relationship, while a PO establishes an agreement to purchase something at some point. C. A procurement contract is a customer's request for specific goods or services, while a PO establishes an agreement to purchase something at some point. D. They are both legally binding documents used to purchase goods or services; therefore, there is no difference.

A. A procurement contract establishes an agreement to purchase something at some point, while a PO is a customer's request for specific goods or services.

A project manager (PM) is working on a project with a flexible budget and has just defined cost inputs and parameters at the start of the project. The PM is working on what type of project? A. Agile project B. Waterfall project C. Scrum project D. PRINCE2

A. Agile project

A junior project manager (PM) assigns resources to a delivery tracking software project. Upon checking the responsibility assignment matrix (RAM), the PM finds that two senior developers are accountable for the app development activity, four junior developers are responsible for the app development activity, one software architect for consultation, and a project director for reporting. What could be the potential issue in this RAM? A. Assigning two senior developers accountable for the software development activity B. Assigning four junior developers responsible for the software development activity C. Having only one software architect for consultation D. Assigning only one project director to inform about development activity

A. Assigning two senior developers accountable for the software development activity

A project manager (PM) completes vendor evaluation techniques to determine which vendor to select for a project. The PM finds that vendor A has a great reputation and offers an approach to the project that is desirable and reliable. Vendor A's quote is higher than expected, but reasonable. Vendor B has an unknown reputation and offers an approach to the project that is unique but untested in the market. Vendor B's quote is lower than expected. What evaluation technique was applied, and what vendor should be selected? A. Best value evaluation technique, select Vendor A B. Best value evaluation technique, select Vendor B C. Cost-benefit evaluation technique, select Vendor A D. Cost-benefit evaluation technique, select Vendor B

A. Best value evaluation technique, select Vendor A

A change in organizational leadership creates the opportunity for a new stakeholder to take responsibility for a project during the execution phase. The stakeholder asks the project manager (PM) if the project will end on budget. Which performance measure value allows the PM to answer affirmatively? A. CV = $0 B. SPI = 1.3 C. VAC = -200 D. ETC = $16,500

A. CV = $0

Which communication plan methods ensure the message shared matches reality? (Select all that apply.) A. Capturing information B. Centralizing information C. Reflecting reality D. Project auditing

A. Capturing information B. Centralizing information C. Reflecting reality

Which sections are included in an escalation plan? (Select all that apply.) A. Category B. Level C. Escalation owner D. Records

A. Category B. Level C. Escalation owner

While working the execution phase of a project, leadership provides guidance to the project manager (PM) that new systems and techniques are coming online to make the group work more efficiently. What indicators should a project manager look for when new systems and techniques are introduced to the team during the execution phase of a project? (Select all that apply.) A. Change causes strain; users must decide that a system's benefits outweigh its discomfort. B. The number of people trained on the new systems and techniques. C. Users will not adopt something new just because it is available. D. Organizational change management recognizes that technology makes change successful.

A. Change causes strain; users must decide that a system's benefits outweigh its discomfort. C. Users will not adopt something new just because it is available.

The stakeholder approved the project deliverables, and the project manager began the project's closing process with which of the following activities? (Select all that apply.) A. Close contracts. B. Transfer all deliverables. C. Stakeholder signoff. D. Reconcile the budget.

A. Close contracts. B. Transfer all deliverables. D. Reconcile the budget.

Which of the following are considered Scrum values describing how people should approach each other? (Select all that apply.) A. Commitment B. Focus C. Adaptation D. Openness

A. Commitment B. Focus D. Openness

What are some of the principles that represent the philosophy and best practices of PRINCE2? (Select all that apply.) A. Continued business justification B. Learn from experience C. Defined roles and responsibilities D. Restrict to suit the product

A. Continued business justification B. Learn from experience C. Defined roles and responsibilities

Elements of a records management plan flow through a cycle, which includes standards for each stage. What are the stages of the records management plan lifecycle? A. Creation, storage and retrieval, and archival and disposition B. Storage and retrieval, archival and disposition, and version control C. Creation, storage and retrieval, and maintenance D. Creation, archival and disposition, and authorized users

A. Creation, storage and retrieval, and archival and disposition

A project team is meeting to discuss their options for improving and re-designing existing software code. What project management type of performance diagram can incorporate multiple factors and map various outcomes from a single decision? A. Decision tree B. Data flow diagram C. Mind map D. Quadrant diagram

A. Decision tree

A project manager (PM) is about to start the breakdown of a project for execution. The PM follows which order for the WBS creation process? A. Determine scope, identify deliverable, identify team members, build level 2 B. Build level 2, determine scope, identify team members, identify deliverables C. Identify deliverables, determine scope, identify team members, build level 2 D. Build level 2, identify scope, determine deliverables, identify team members

A. Determine scope, identify deliverable, identify team members, build level 2

Upon consulting a network engineer, the project manager (PM) learns that the engineer can install the software after the completion of the server migration. What kind of dependency is between the server migration and software installation activity? A. Finish-to-Start B. Finish-to-Finish C. Start-to-Start D. Start-to-Finish

A. Finish-to-Start

After several months of building and testing the e-commerce marketing feature, it is ready to go live. The development team has invited the operational team for the hand-off. The project manager senses a mitigation conflict during this period. What can the project manager do in this case? A. Follow the transition plan guidelines. B. Accept this risk as it can happen between different teams. C. This is an educational risk, and the PM should embrace it. D. Conduct impact analysis and leave it as is.

A. Follow the transition plan guidelines.

A project manager is attempting to schedule a project closure meeting with key stakeholders but cannot find the recommended amount of time on their respective calendars to ensure all topics are covered and approved within the meeting. What actions can the PM take to reduce the amount of approvals during the available meeting time? (Select all that apply.) A. Gain written stakeholder sign-off after the meeting. B. Give stakeholders a closing checklist during the meeting. C. Skip the project evaluations and project challenges to increase stakeholder approval. D. Gather lessons learned feedback and self-evaluations prior to the meeting.

A. Gain written stakeholder sign-off after the meeting. D. Gather lessons learned feedback and self-evaluations prior to the meeting.

An agile team is working with the extreme programming model to develop a web application that needs to be ready within the next 30 days. Recognizing that a highly detailed project plan will be needed, the team elects to use a bar chart where the 30-day timeframe is broken down into daily representations on the x-axis and all tasks/activities are recorded on the y-axis. What productivity tool would help keep the team on task with milestones and specify the tasks needed to reach the milestone events? A. Gantt chart B. Milestone chart C. Project roadmap D. Project charter

A. Gantt chart

During the project closure meeting, the project manager discusses the final performance metrics, including cost, budget, and schedule. What important opportunities does the project manager (PM) miss by providing these in writing to stakeholders rather than conducting a thorough project closure meeting? (Select all that apply.) A. Gathering, documenting, and publishing data to ensure that future projects benefit from the lessons learned B. Project evaluations that promote critical thinking and personal reflection from team members and stakeholders C. Delivering an outline to the stakeholders with a list of completed tasks of the project D. Requesting feedback on the project management approach and any improvements

A. Gathering, documenting, and publishing data to ensure that future projects benefit from the lessons learned B. Project evaluations that promote critical thinking and personal reflection from team members and stakeholders D. Requesting feedback on the project management approach and any improvements

The project manager (PM) asks the team to meet and brainstorm solutions together to resolve a project issue. Why should the team members bring issues to the team for group analysis instead of generating solutions individually? (Select all that apply.) A. Groups can work together to find solutions that individuals cannot. B. The individual who brings the problem to the group typically has the best understanding of the root causes and how to solve the issue. C. Individuals cannot often solve complex problems, nor do complex problems have only one root cause. D. Individuals hesitate to report issues, and unreported issues will exponentially affect a project.

A. Groups can work together to find solutions that individuals cannot. C. Individuals cannot often solve complex problems, nor do complex problems have only one root cause.

A team creates a quality assurance plan during the planning phase of a project. Which questions does a quality assurance plan address? (Select all that apply.) A. How will the team verify that the project meets expectations? B. If the risk were to occur, what is the monetary loss? C. How can the team prevent defects? D. If the process is not working, how can the team recognize and improve the process?

A. How will the team verify that the project meets expectations? C. How can the team prevent defects? D. If the process is not working, how can the team recognize and improve the process?

What is the first step in developing a communication plan? A. Identify stakeholders. B. Create the project communication plan. C. Schedule everything. D. Identify stakeholder communication preferences.

A. Identify stakeholders.

A team is responsible for purchasing resources for a large construction project. It is their shared responsibility to minimize the possibility of waste and maximize value in the project. Using a purchasing and fiscal perspective, what resource management technique should the team apply to help the project? A. Include a summary of assumptions and risks in the financial plan. B. Assess all environmental considerations in the project plan. C. Draft a current state diagram. D. Draft a future state diagram.

A. Include a summary of assumptions and risks in the financial plan.

A project manager (PM) for a hearing aid manufacturing company recently discovered that customers have complained about a potential flaw in their hearing aid, causing high volumes. Upon checking the sample sent by the customer, the PM found the unit incorrectly wired. What should the PM do immediately? A. Inform stakeholders and issue a Notice of Escape to the customers. B. No need to alert the stakeholders; continue with the work. C. Give a refund to the customer and continue with the work. D. Ask the QA team to work overtime to fix the issue.

A. Inform stakeholders and issue a Notice of Escape to the customers.

A major production company's project manager (PM) is closing a software implementation project. The PM is now responsible for eliciting feedback from the contributors that directly assisted in the creation of the software. The PM is seeking feedback from which influencer role? A. Internal customer B. End-user C. Sponsor D. Senior management

A. Internal customer

A dashboard analyst develops reports and dashboards for key stakeholders. What type of privacy considerations must be taken into consideration when developing outward facing reports? (Select all that apply.) A. Is the data already public and will not cause relative harm if viewed by outside parties? B. Does the dashboard reflect internal data, which is not otherwise public information? C. Does the dashboard contain confidential data, and if so, has access been set appropriately? D. Does the dashboard include additional costs that will become a financial burden on the stakeholders?

A. Is the data already public and will not cause relative harm if viewed by outside parties? B. Does the dashboard reflect internal data, which is not otherwise public information? C. Does the dashboard contain confidential data, and if so, has access been set appropriately?

Why is a requirements traceability matrix (RTM) a helpful product artifact? (Select all that apply.) A. It simplifies the audit and quality process. B. It traces all of the artifacts utilized in each project requirement. C. It traces which project requirements the team is not meeting if a failed test occurs. D. It traces all of the risks associated with each project requirement.

A. It simplifies the audit and quality process. B. It traces all of the artifacts utilized in each project requirement. C. It traces which project requirements the team is not meeting if a failed test occurs.

A project manager (PM) is working with an agile team that is building small sections at a time and reviewing their progress. In this way, the team can adapt to their approach. For example, the team plans to release their part to production but need to ensure it is the appropriate time. What type of development is this agile framework team implementing? A. Iterative and incremental development B. Incremental development C. Iterative development D. Enterprise resource planning

A. Iterative and incremental development

A project manager (PM) develops a graph for the team's stakeholders. The PM wants to be able to visually depict a comparison in the improvement in quality scores against the cost of achieving them. What type of project tool would best meet the PM's requirements? A. Law of diminishing returns chart B. Pareto chart C. Escalation plan D. Communication plan

A. Law of diminishing returns chart

A project manager at an information technology (IT) consulting firm has received new tasks to add to the project plan. What are some activities included in creating a responsibility assignment matrix (RAM)? (Select all that apply.) A. List the work breakdown structure (WBS) elements or product backlog items (PBIs) in the first column. B. List the project team members, stakeholders, and other necessary parties across the top columns. C. Assign who is responsible, accountable, consulted, and informed for completing work. D. Ensure that every person has a role for each task.

A. List the work breakdown structure (WBS) elements or product backlog items (PBIs) in the first column. B. List the project team members, stakeholders, and other necessary parties across the top columns. C. Assign who is responsible, accountable, consulted, and informed for completing work.

A newly-hired project manager (PM) works for a major software company. Which of the following onboarding events can be categorized as operational work for a project manager when a new employee joins their team? (Select all that apply.) A. Maintains project historical information. B. Conducting routine quality assurance reviews. C. Completes appropriate background checks at onset of project. D. Establish single sign-on for all assigned users.

A. Maintains project historical information. B. Conducting routine quality assurance reviews.

A parts manufacturing company from the Midwest area of the U.S. has sent a letter of notice citing the potential parts shortage due to supply chain issues. The project manager identified a risk response strategy for this and arranged for local companies to create parts until there is a solution to the supply chain problem. This is an example of what type of risk response strategy? A. Mitigate B. Avoid C. Acceptance D. Transfer

A. Mitigate

What type of meeting reviews the criteria of a stage to determine if the project is ready to move to the next stage? A. Phase gate review meeting B. Change control meeting C. Stakeholder meeting D. Team status meeting

A. Phase gate review meeting

What are the three most common tiers in an N-tier architecture? (Select all that apply.) A. Presentation B. Internet C. Application D. Data

A. Presentation C. Application D. Data

A team is working through a Kanban board. What are some activities within the four-part workflow? (Select all that apply.) A. Prioritizing and ordering the backlog B. Selecting the top-ordered backlog items and moving it into progress C. Moving items through the workflow, while keeping within WIP D. Selecting the next item in the backlog before the team is ready to start new work

A. Prioritizing and ordering the backlog B. Selecting the top-ordered backlog items and moving it into progress C. Moving items through the workflow, while keeping within WIP

The project manager submits a change to the software code for approval. What type of approvals will the project manager request? (Select all that apply.) A. Product owner approval B. Architectural approval C. Technical approval D. Software approval

A. Product owner approval B. Architectural approval C. Technical approval

What is a group of several related projects that have a common objective to accomplish a big goal? A. Program B. Stakeholders C. Senior management D. Sponsors

A. Program

In a business endeavor, what role leads, plans, and aligns endeavors to organizational strategy? A. Program manager B. Project manager C. Supportive project management office D. Directive project management office

A. Program manager

What components of the general project information does a project charter include? (Select all that apply.) A. Project name B. Project description C. Risk management plan D. Project sponsor

A. Project name B. Project description D. Project sponsor

A project manager wants to select a productivity tool that will share major progress points, including new feature rollouts and products that would serve well in an executive summary. Which of the following tools would be the best option? A. Project roadmaps B. Milestone charts C. Kanban board D. Project charter

A. Project roadmaps

The project team conducts training to promote user change adoption. However, after three months, tracking measures reveal that the number of active users only reached 30%. A successful project team will take which of the following next steps to increase user adoption? (Select all that apply.) A. Re-identify which groups of users need to do something differently. B. Speak to business leaders and request that they hold users accountable. C. Cancel the use of the legacy system, product, or technology. D. Reconcile the budget and ensure funding is available.

A. Re-identify which groups of users need to do something differently. C. Cancel the use of the legacy system, product, or technology.

Near the end of the execution phase, a project manager (PM) updates the project budget and notices a gap in the cost compared to earlier estimates. What actions did the PM overlook in the project management process? (Select all that apply.) A. Rebaseline the project at the end of each phase. B. Maintain the project dashboard. C. Distribute the project schedule. D. Revise the baseline in change requests.

A. Rebaseline the project at the end of each phase. D. Revise the baseline in change requests.

A project manager determines that the team is ahead of schedule and over budget. However, the team completed deliverables faster than expected, but the vendor charges increased unexpectedly due to unanticipated technology needs. What action should the PM take next to adjust? (Select all that apply.) A. Rebaseline the project cost. B. Change the project scope. C. Revise the cost baseline. D. Create a dashboard.

A. Rebaseline the project cost. C. Revise the cost baseline.

A project manager (PM) drafts the agenda and documents to present at the upcoming project closure meeting. Which artifacts will the project manager include in the documents to prepare for the upcoming project closure meeting? (Select all that apply.) A. Reconciled budget B. Project closeout report C. Closed contracts D. Project sign-off

A. Reconciled budget B. Project closeout report

A project manager (PM) is managing the vendor relationship of a virus detection software project. The PM determines that the vendor and the project team should communicate weekly regarding the project deliverables and that each team member should articulate a recognition at the retrospectives. The PM should document these types of expectations in what artifact? A. Rules of engagement B. Project management plan C. Status reports D. Service level agreement

A. Rules of engagement

The project team plans to monitor when the implemented changes begin to affect system performance. The team will look for what type of variation? A. Special cause variation B. Common cause variation C. Neutral variation D. Control chart variation

A. Special cause variation

What engagement organizes project management activities, with the PM as the primary audience? A. Stakeholder engagement plan B. Stakeholder analysis C. Stakeholder register D. Engagement approach

A. Stakeholder engagement plan

The project manager confirms the completion of all project deliverables while project team members begin focusing on other projects and operational activities. Why should the project manager continue to complete a thorough administrative closure for the project? (Select all that apply.) A. Stakeholders continually request changes to project deliverables without a formal closeout and sign-off process. B. Stakeholders do not realize project benefits until after the project closing phase. C. The project closing phase contains many valuable and necessary activities but are often skipped. D. The closing phase frees team members since they have a sense of accomplishment and finality.

A. Stakeholders continually request changes to project deliverables without a formal closeout and sign-off process. C. The project closing phase contains many valuable and necessary activities but are often skipped. D. The closing phase frees team members since they have a sense of accomplishment and finality.

A company's CEO has announced they are retiring. What resource management activity should the company begin to pursue if they have not already? A. Succession planning B. Maintenance and monitoring C. Acquisition D. Improvement

A. Succession planning

What type of communication is also referred to as real-time communication? A. Synchronous communication B. Asynchronous communication C. Verbal communication D. Nonverbal communication

A. Synchronous communication

A client for a software design project has indicated that the software engineer must develop three software features early on for the product to be minimally viable. Why is creating a minimally viable product (MVP) for the client an essential step? (Select all that apply.) A. The MVP allows the project team to receive feedback from users early in the development. B. The MVP has all features requested to demonstrate how desirable the product is. C. The MVP builds confidence among stakeholders. D. The MVP has all the requirements to test the product appropriately.

A. The MVP allows the project team to receive feedback from users early in the development. C. The MVP builds confidence among stakeholders. D. The MVP has all the requirements to test the product appropriately.

What are examples of artifacts that a project manager should include in the records management plan? (Select all that apply.) A. The approved project budget B. An email discussing the best date/time for the project kickoff meeting C. Audit results covering the duration of the project D. Facility certifications for space used to conduct project business

A. The approved project budget C. Audit results covering the duration of the project D. Facility certifications for space used to conduct project business

A project manager (PM) has just been assigned to a new high-priority project to manage at the end of the planning phase. The PM has the preliminary scope statement, which the previous PM created in the initiation phase. There are also more detailed definitions for the project goals, scope, and requirements. What project document is the PM ready to finalize? A. The detailed scope statement B. The scope baseline C. The work breakdown structure (WBS) D. The project plan

A. The detailed scope statement

The project manager (PM) applies earned value management to monitor schedule performance and generates a $300 schedule variance value and a 1.4 schedule performance index value. What can the project manager conclude about the schedule? (Select all that apply.) A. The project team has been producing lower quality work. B. The project team will complete deliverables earlier than planned. C. The project team overestimated the time to complete project tasks. D. The project team will complete deliverables later than planned.

A. The project team has been producing lower quality work. B. The project team will complete deliverables earlier than planned. C. The project team overestimated the time to complete project tasks.

A project manager creates a scope burndown chart to analyze the performance of an agile project team. What changes can the project manager expect to see over time? (Select all that apply.) A. The scope target will change. B. The project will remain on track to finish on time. C. The chart will have a smooth line with no spikes. D. The chart should show frequent progress.

A. The scope target will change. D. The chart should show frequent progress.

The project team has been working on an application software for the past 20 days. The target for completed work on the burnup chart estimates 14 task hours a day. On day 20, the project team completed 308 task hours. What does this imply? (Select all that apply.) A. The team is ahead of schedule by 28 task hours. B. The team is ahead of schedule by two days. C. The team has been averaging 10 task hours a day. D. The team is right on schedule.

A. The team is ahead of schedule by 28 task hours. B. The team is ahead of schedule by two days.

The project team managing the new cloud computing project has just learned that the software needed for one key deliverable of the project has increased in price due to unexpected development costs. The project manager (PM) has completed the change control process for a scope change, and the client approved the change in scope. What other actions must the PM perform? (Select all that apply.) A. Update the project budget. B. Authorize the use of the contingency reserve. C. Update the cost baseline. D. Update the schedule baseline.

A. Update the project budget. B. Authorize the use of the contingency reserve. C. Update the cost baseline.

The company has hired a project manager (PM) to manage the execution of a project. However, a new college intern is unsure of what work to accomplish on the project and asks the PM. Where can the PM find the detailed description of the work packages? A. WBS dictionary B. Project scope statement C. Scope management plan D. Activity list

A. WBS dictionary

What are the differences between agile and waterfall teams when delivering products? (Select all that apply.) A. Waterfall teams deliver the big design up front, while agile teams deliver in small batches. B. Waterfall teams deliver customers nearly finished products, while agile teams deliver in iterations or increments. C. Waterfall teams deliver in small batches, while agile teams deliver a big design upfront. D. Waterfall teams deliver in increments, while agile teams deliver customers nearly finished products.

A. Waterfall teams deliver the big design up front, while agile teams deliver in small batches. B. Waterfall teams deliver customers nearly finished products, while agile teams deliver in iterations or increments.

Different organizational structures give different roles to project managers (PMs). For example, a corporation has a PM responsible for assigning work but does not have budget responsibilities or any official authority over the people doing the work. The PM is in what type of organizational structure? A. Weak matrix B. Projectized C. Functional D. Strong matrix

A. Weak matrix

A project manager (PM) needs to calculate the return on investment (ROI). The project has generated a revenue of $23,000 with a cost of $108,000. What is the ROI? A. 21.30% B. -78.70% C. -369.57% D. 78.70%

B. -78.70%

What are some of the responsibilities of a business analyst (BA)? (Select all that apply.) A. A business analyst writes tests against technical requirements. B. A business analyst helps define the project. C. A business analyst gathers business and technical requirements. D. A business analyst assists with testing and validation.

B. A business analyst helps define the project. C. A business analyst gathers business and technical requirements. D. A business analyst assists with testing and validation.

The project manager (PM) evaluates a change request for modifying project deliverables to include updating a legacy system. The operational team responsible for that system does not already participate in the project, and the PM will request their participation. What type of change does this represent? A. A technical change B. A strategic change C. An operational change D. A software change

B. A strategic change

A company plans to expand its business throughout the southeast, including the state of Virginia. What additional data regulation will the company need to take into consideration? A. GDPR B. CDPA C. CPRA D. ESG

B. CDPA

One of the three quality assurance (QA) testers for a website project has complained about being burned out. Upon checking the skills matrix, the project manager (PM) sees that of the three, the burned-out QA tester is an expert QA for backend testing, optimization, and mobile testing. How would the PM handle this situation of an employee experiencing burnout? (Select all that apply.) A. Increase pay and assign less work to the burned-out tester. B. Check the utilization gap for other testers and level the resources. C. Provide the burned-out tester an extra three days of leave every quarter. D. Train other QA testers to increase team performance.

B. Check the utilization gap for other testers and level the resources. D. Train other QA testers to increase team performance.

A medical records company wants to upgrade to a more secure database management system (DBMS). They are responsible for thousands of personal health records, billing and financial data, and organizational records. Which of the following data types should the company be the most concerned with safeguarding when selecting a DBMS vendor? A. Public data B. Confidential data C. Internal data D. Secret data

B. Confidential data

A new project manager (PM) is looking to perform a root cause analysis to determine why the project is running behind schedule. Which of the following types of analysis might the PM find effective and easy to use as a starting point? (Select all that apply.) A. Scatter diagram B. Fishbone diagram C. Five-Why analysis D. Pareto chart

B. Fishbone diagram C. Five-Why analysis

A project manager (PM) is working on an upcoming software upgrade project. The software upgrade will take several years due to multiple phases of upgrades. Since the client would like to try and get the project done earlier, they have added language on the contract offering an extra $500,000 if the project finishes six months before the scheduled completion date. This is an example of what type of contract? A. Fixed-price with economic price adjustment B. Fixed-price incentive fee C. Cost-plus award fee D. Cost-plus fixed fee

B. Fixed-price incentive fee

A project manager (PM) has established multiple milestones for a two-year-long project. However, each milestone checkpoint occurs at the one-year mark. What might be the potential issue with this approach? A. Fewer meetings B. Losing project momentum C. Stakeholder conflict D. Expensive cost of the project

B. Losing project momentum

A project manager (PM) is launching a yearlong project that will focus on continuous software development for a well-established firm. Due to the lifecycle of the project, which life cycle phase should focus on employee retention? A. Acquisition B. Maintenance and monitoring C. Improvement D. Retirement

B. Maintenance and monitoring

A project team member notifies the project manager (PM) that a missed maintenance window created a system downtime just after business hours on Friday evening. The PM escalated the necessary change request and received emergency authorization to schedule the system update for Sunday morning. What priority level should the project manager assign this issue on Monday morning at the beginning of the work day? A. Critical severity, critical urgency, medium impact B. Major severity, medium urgency, high impact C. Low severity, minor urgency, high impact D. Minor severity, major urgency, low impact

B. Major severity, medium urgency, high impact

A project manager needs to establish a project team for a new web design project. Before assigning responsibility and bringing on team members, what must the project manager conduct? A. Succession planning B. Needs assessment C. Resource allocation D. Resource optimization

B. Needs assessment

The project manager (PM) creates a scatter diagram to analyze whether faults occur during nightly scheduled system outages. The scatter diagram yields an R2 of 0. What conclusion can the PM draw based on the scatter diagram? A. The faults regularly occur during nightly system outages. B. No relationship exists between the faults and nightly system outages. C. The nightly system outages cause the faults. D. Fewer nightly system outages result in more faults.

B. No relationship exists between the faults and nightly system outages.

A team is in the planning phase of a large project. The project involves protected intellectual property included in a new video game. What communication security methods will the team need to apply during the planning session? (Select all that apply.) A. Communication archiving B. Nondisclosure agreements C. Encrypted communication D. Centralizing information

B. Nondisclosure agreements C. Encrypted communication

A project manager (PM) plans to create an executive dashboard. Which key performance indicators (KPIs) will impact the stakeholders most? (Select all that apply.) A. Cost variance B. Performance to budget C. Cost per requirement D. Revenue generated

B. Performance to budget D. Revenue generated

What high-level documents share major progress points, such as new feature rollouts? A. Milestone charts B. Project road maps C. Gantt charts D. Project charter

B. Project road maps

Which statement defines the project and is created at an early stage to reflect the stakeholders' common understanding of what will be performed in the project? A. Project charter B. Project scope C. Milestone chart D. Gantt chart

B. Project scope

A project manager (PM) leads the team in conducting a thorough root cause analysis. Why is this an important process? (Select all that apply.) A. Root cause analysis enables project teams to quickly and easily get a project on track. B. Project teams conduct root cause analysis to prevent issues from reoccurring. C. Stakeholders accept issues identified by the project when the PM offers them the root cause analysis document. D. Root cause analysis allows the team to determine why an issue is occurring.

B. Project teams conduct root cause analysis to prevent issues from reoccurring. D. Root cause analysis allows the team to determine why an issue is occurring.

What could be a beneficial incentive for the prospective client that a service provider could have in a service level agreement (SLA) A. Requiring the client to pay extra for regular system performance upgrades B. Providing credits to subscription costs for downtime exceeding a certain threshold C. Offering a cancellation clause if the client is not happy with the performance of the system D. Requiring the service provider to resolve all help desk tickets within one business day

B. Providing credits to subscription costs for downtime exceeding a certain threshold

A project manager (PM) updates the project management software to reflect a change in the project scope. The change control board (CCB) approved this change which impacts the project budget and schedule. The PM notices that the project budget and schedule baselines have changed. Why is this appropriate? (Select all that apply.) A. Revised baselines boost team morale. B. Rebaselining makes targets achievable. C. Obsolete baselines prevent performance improvement. D. Revised baselines erase missed milestones.

B. Rebaselining makes targets achievable. C. Obsolete baselines prevent performance improvement.

An organization has earmarked a new data center as a capital expense (CapEx) that the organization will procure in two years. However, a current project needs storage for cloud data, and the current data center will not be viable for this purpose. As the project manager (PM), what is the best way to proceed? A. Purchase a new data center ahead of the CapEx schedule and include it as OpEx. B. Rent cloud storage from a third-party vendor and include it as OpEx. C. Postpone the project for two years until the organization has procured the new data center. D. Submit a change request to eliminate data storage.

B. Rent cloud storage from a third-party vendor and include it as OpEx.

In what ways does the project manager influence the project budget? (Select all that apply.) A. The project manager does not directly control project costs. B. Selecting vendors and managing vendor performance C. Monitoring and controlling costs through assessing the burn rate weekly D. Authorizing scope changes

B. Selecting vendors and managing vendor performance C. Monitoring and controlling costs through assessing the burn rate weekly D. Authorizing scope changes

A project manager (PM) has just assembled the project team. The PM needs to start the next process and build the organizational chart. What are the sections in a project organizational chart that typically include high-level individuals responsible for oversight, guidance, and funding of the project? (Select all that apply.) A. Stakeholder B. Sponsor C. Steering committee D. End-user

B. Sponsor C. Steering committee

A geographically dispersed team frequently collaborates through teleconferencing software. The software is commonly used in the United States, but team members in Europe are unfamiliar with the platform. What type of communication challenge is the team facing? A. Cultural differences B. Technological factors C. Language barriers D. Conflict management

B. Technological factors

A project manager (PM) works on a project that includes a change control board. How does the PM's role in the change control process look different on this project than on a project without a change control board? (Select all that apply.) A. The PM makes change decisions and informs the change control board for formal approval. B. The change control board evaluates, approves, and denies change requests. C. The PM receives and analyzes change requests and makes recommendations to the change control board. D. The change control board analyzes change requests and approves or denies them.

B. The change control board evaluates, approves, and denies change requests. C. The PM receives and analyzes change requests and makes recommendations to the change control board.

When the project stakeholders approve project deliverables, they agree to several conditions. Which conditions apply? (Select all that apply.) A. Ongoing work on the project gets canceled. B. The deliverables are satisfactory. C. The project is officially closed. D. The team will not deliver new work or accept new change requests.

B. The deliverables are satisfactory. D. The team will not deliver new work or accept new change requests.

A project team's average throughput is 10 in the first sprint iteration, 14 in the second sprint iteration, and 12 in the third sprint iteration. What should the team do at the next planning session? A. The team should plan to deliver 10 items in the next sprint session. B. The team should plan to deliver 12 items in the next sprint session. C. The team should plan to deliver 14 items in the next sprint session. D. The team should plan to deliver as many items as they can in the next sprint session.

B. The team should plan to deliver 12 items in the next sprint session.

On checking the critical path method (CPM) diagram for a web development project, the project manager (PM) finds that the "Design Custom Fonts" activity has an Early Start (ES) of nine weeks and a Late Start (LS) of twelve weeks. Based on this information, which of the following statements is true? A. The total float for the Design Custom Fonts activity is nine weeks. B. The total float for the Design Custom Fonts activity is three weeks. C. The total float for the Design Custom Fonts activity is twelve weeks. D. The total float for the Design Custom Fonts activity is four weeks.

B. The total float for the Design Custom Fonts activity is three weeks.

What type of system combines workflows and user interfaces to create a one-stop experience for support? A. Calendaring tools B. Ticketing or case management system C. Real-time surveys and polls D. Print media

B. Ticketing or case management system

What tool should a team use if they want to record their working hours, have accurate working hour estimates, and use it in future projects? A. Kanban board B. Time tracking application C. Project schedule D. Scrum board

B. Time tracking application

A project manager (PM) for a software project creates an e-commerce site for a client. Upon checking the skills matrix, the PM finds that 7 out of 10 team members do not have the skills for creating a backend database. How will the PM close the skill gap on the project? (Select all that apply.) A. Assign all the work to the remaining three skilled workers. B. Train the seven team members on backend database development. C. Hire more team members that know about database development. D. Contract backend development to external service to complete the project in time.

B. Train the seven team members on backend database development. C. Hire more team members that know about database development. D. Contract backend development to external service to complete the project in time.

Upon surveying the stakeholders for a project costs estimation, the project manager (PM) found that if everything happens perfectly, it is $5,000, and the most likely estimate is $10,000. However, if everything goes wrong, the project cost estimation is $21,000. Based on this information, what will be the probable cost estimate for the project? A. $10,000 B. $21,000 C. $12,000 D. $17,000

C. $12,000

Activity G has a late finish (LF) of eighteen days and an early finish (EF) of three days. Activity E follows Activity G. Activity E has an early start (ES) of six days. What is the total float for Activity G? A. 16 days B. 12 days C. 15 days D. 21 days

C. 15 days The total float (TF) calculation is LF-EF. Since LF = 18 days and EF = 3 days, the TF for Activity G is 18-3 = 15 days.

A team has purchased two 3D printers to print the house models for the client. The printers are both available for 120 hours each. The team uses printer A for 70 hours of work, while printer B is for 90 hours. What is the total utilization of both printers? A. 33% B. 75.60% C. 66.60% D. 50%

C. 66.60%

A government organization needs to select a secure method for communicating with public customers. Their top priorities are protected communication and adherence to regulatory guidelines. Which of the following solution design elements are the most critical in this scenario? (Select all that apply.) A. Scalability B. Compatibility C. Compliance D. Security

C. Compliance D. Security

What type of data requires communication security where the data has limited access and is only available to authorized users? A. Public data B. Private data C. Confidential data D. Critical data

C. Confidential data

What is the main difference between contingency reserves and management reserves? A. Contingency reserves cover setbacks not forecasted, while management reserves cover documented risks. B. Contingency reserves cover "unknown unknowns," while management reserves cover "known unknowns." C. Contingency reserves cover documented risks, while management reserves cover setbacks not forecasted. D. Only senior management authorizes contingency reserve spending, while the project manager authorizes management reserve spending.

C. Contingency reserves cover documented risks, while management reserves cover setbacks not forecasted.

A project manager (PM) must break down the work to the company's engineers for a website development project, with a hard deadline of five weeks. The marketing team has requested three fixed and three preferred deliverables for the project if the time is available. The team is self-organizing. How will the PM break down this project? A. Create a WBS with level 1 and level 2. B. Create an activity list. C. Create a project backlog. D. Create a task list for each engineer.

C. Create a project backlog.

A project manager (PM) works through the common SDLC phases and has just created a low-function prototype. What phase is next? A. Requirements B. Testing C. Development D. Deployment

C. Development

An organization has tasked a project manager (PM) to update the business case. The PM has new data that needs to go into the cost-benefit analysis and risks. What part of the business case does the PM need to update? A. Options B. Problem analysis C. Financial overview D. Project analysis

C. Financial overview

A project is two weeks behind schedule, and the project manager (PM) does not know why. So the PM is planning a team brainstorming activity to find the potential cause of this delay. What gap analysis tool will the PM use? A. Resource leveling B. Probability cost estimate C. Fishbone diagram D. Utilization gap

C. Fishbone diagram

A solution architect decides how they can best maximize their time remaining before they must deliver software to a client. How should the architect prioritize the features of the software and still meet their deadline? A. Hardware requirements B. Constraints C. Functional requirements D. Software products

C. Functional requirements

A team develops a website for a client in the grocery industry. The client requests a complex interface that allows consumers to order items for delivery. Additionally, the inventory must be queried and adjusted based on orders placed to ensure consumers are seeing real-time availability. What elements of the solution design process does the team include in this project? (Select all that apply.) A. Scalability B. Extensibility C. High-level design D. Functional requirement

C. High-level design D. Functional requirement

The project manager wants to ensure that future operations team members can contribute to documentation about the new technology long after the project execution phase ends. Which organizational change management tool facilitates this goal? A. Documentation B. Training C. New knowledge base D. New processes

C. New knowledge base

A manufacturing company needs to develop a report that shows its stakeholders which resources generate the most revenue for the company. Which of the following charts would be the best fit? A. Burndown chart B. Burnup chart C. Pareto chart D. Gantt chart

C. Pareto chart

What type of statement of work (SOW) describes the expected outcomes and minimum performance standards? A. Design SOW B. Functional SOW C. Performance SOW D. Terms of reference

C. Performance SOW

A project manager for a plastic bottle company noticed that the material cost of plastic was expected to decrease by 30%. How will the project manager classify such a decrease in material price? A. Change B. Negative risk C. Positive risk D. Issue

C. Positive risk

A business analyst is managing a project for a new training website and needs to perform the qualitative risk analysis process. When the analyst completes the process, which of the following list of items will NOT be a part of the project document? A. Risks grouped by categories B. List of low-priority risks C. Probability of achieving time and cost estimates D. Priority list of risks

C. Probability of achieving time and cost estimates

What is a function of both product owners on agile teams and project managers? A. Product owners and project managers both manage teams. B. Product owners and project managers both measure productivity on a project. C. Product owners and project managers both create work for teams. D. Product owners and project managers both get involved with the details of the project work.

C. Product owners and project managers both create work for teams.

A senior manager attended a regional conference and interacted with several competitor clients. At the conference, the senior manager learned that the contractor currently working on a high-cost retail website project for the senior manager's firm has a history of overbilling for their work. The senior manager returns from the conference and asks to see verification of all the evaluation techniques utilized to select this vendor. The project manager (PM) provides evidence of a vendor demonstration, technical approach review, and evidence of financial solvency. What evaluation technique did the PM miss that could have discovered this information? A. Vendor qualification B. Cost-benefit analysis C. Reference checks D. Financial capacity

C. Reference checks

Due to the pandemic, the team is adopting a remote work environment and is upgrading the infrastructure to move to cloud services. What could be positive risks associated with this process? A. Downtime during migration and testing B. Increase in documentation for a new system C. Remote working and opportunities for recruiting more talent D. More required training time to learn new digital skills

C. Remote working and opportunities for recruiting more talent

What is a document that describes how project requirements will be analyzed, documented, and managed throughout the project lifecycle? A. Project schedule B. Communication requirements C. Requirements management plan D. Change request

C. Requirements management plan

Based on past similar projects, a project manager (PM) needs to anticipate the date the project will end. Which performance measure can the PM use to determine this? (Select all that apply.) A. Cost performance index B. Scope burndown chart C. Schedule performance index D. Schedule variance

C. Schedule performance index D. Schedule variance

A project manager's assistant has calculated many financial aspects of the business case. The project manager (PM) has asked the assistant to determine ESGs for a major water plant facility. What would the assistant add for governance? A. Water management B. Human rights C. Stakeholder engagement D. Employee benefits

C. Stakeholder engagement

A project manager (PM) is preparing for a stakeholder meeting. What important artifact should the PM prepare? A. Performance appraisals B. Project schedule C. Status report D. Change requests

C. Status report

A project manager (PM) is dividing up responsibilities amongst team members prior to their kickoff meeting. The PM assigned the software team as responsible for development of the core software code. What is included in the responsible category of the RACI chart? A. The software is not complete until the software team approves it. B. The software team will give advice on the project. C. The software team will complete the work. D. The software team will receive updates but not interact with the build.

C. The software team will complete the work.

The project manager (PM) has identified a risk event on the current project that could save $50,000 in project costs if it occurs. Based on this, which of the following is true? A. The PM should avoid this risk event to take advantage of its full potential. B. The PM should mitigate this risk event to take advantage of the savings. C. This risk event is an opportunity, and the PM should exploit it. D. The PM should accept this risk event since the reward is greater than the threat to the project.

C. This risk event is an opportunity, and the PM should exploit it.

The project to build software for a point-of-sale system has just ended, and the project team has conducted a retrospective or lessons learned meeting. The project manager stores the outputs from this meeting in a lessons learned document for which primary reason? A. To share the project successes with the client. B. To document disagreements within the project team to share with the team supervisor. C. To become a reference point during the initiation phase of a similar future project. D. To close out the documents required in the project management plan.

C. To become a reference point during the initiation phase of a similar future project.

What tool tracks and manages code changes by automatically tracking what changed, when, and by whom? A. Time tracking application B. Task board C. Version control D. Inspections

C. Version control

What is the biggest difference between waterfall and agile? A. Waterfall uses iterative and incremental design, while agile uses Big Design Up Front (BDUF). B. Waterfall is adaptable, while agile is linear and sequential. C. Waterfall is structured, while agile is flexible. D. Waterfall is for projects whose requirements will change, while agile is for short simple projects.

C. Waterfall is structured, while agile is flexible.

The project manager (PM) dashboard lists issues, change requests, and risks with upcoming deadlines. The PM can continually answer what question with this information? A. Why does the project matter to the PM? B. What milestones will the team achieve next? C. What should the PM pay attention to next? D. Is the project on time, in scope, and on budget?

C. What should the PM pay attention to next?

A project manager (PM) needs to determine a project's return on investment (ROI). In this case, the project's net profit is $50,000.00, costing $15,000.00. What is the ROI? A. 233.33% B. 30.00% C. 3.33% D. 333.33%

D. 333.33%

Activity A has an optimistic (O) estimate of two days, a most likely (M) estimate of four days, and a pessimistic (P) estimate of twelve days. What is the Program Evaluation and Review Technique (PERT) estimate for this activity? A. 6 days B. 9 days C. 4 days D. 5 days

D. 5 days The formula for a PERT estimate is (O +4M + P)/6. Here, the PERT estimate = [2+(4*4) +12]/6 = 30/6 = 5 days.

Two software engineers are working on an e-commerce project. Both are available for 100 hours each. However, the first engineer is scheduled for 30 hours a week, while the second engineer has 50 hours a week. What is the utilization rate of the second engineer in this project? A. 55% B. 30% C. 40% D. 50%

D. 50%

A project manager works with a team to develop a web application. Midway through the process, two senior level programmers begin having disagreements about which font type to use on the user interface. Which conflict resolution strategy should be leveraged to arrive at the best case scenario? A. Smoothing B. Forcing C. Compromising D. Collaborating

D. Collaborating

What is the minimum clearance requirement for employees who will have access to material that may cause damage to national security if disclosed without authorization? A. Secret B. Top secret C. Sensitive compartmented information D. Confidential

D. Confidential

What is NOT an element of a warranty? A. Scope B. Remediation C. Length D. Cost

D. Cost

A project manager (PM) just received the project scope and activities and is building their project team. What data point about a potential team member is NOT needed to create other artifacts in the initiation phase? A. Contact method B. Availability C. Project responsibilities D. Employment history

D. Employment history

A project manager (PM) is drafting a sequence of activities for an educational website project designed for blind people and those with various vision impairments. A third-party accessibility auditor will finish approving the website design at the engineer's conclusion of the website demo. What kind of dependency exists between the website demo and accessibility audit? A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

D. Finish-to-Finish

A senior developer for an e-commerce website of critical importance has to go on leave of absence due to a family emergency. What should a project manager (PM) do for this risk? A. Transfer this risk by getting insurance for intellectual property. B. Conduct a qualitative risk assessment by asking other team members. C. Follow the risk mitigation plan. D. Follow the contingency plan for this risk.

D. Follow the contingency plan for this risk.

At the weekly team status meeting, the team lead would like to discuss a performance issue of a team member that is affecting the morale and productivity of the rest of the team. What should the project manager do? A. Discuss the performance issue at the beginning of the status meeting as it is affecting productivity on the project. B. Email the team asking them to share how the performance issue affects them. Then share the feedback at the team status meeting. C. Have a private meeting with the team member to address the performance issue, explaining how the behavior affects the morale and productivity of others. D. Have a private meeting with the team lead to discover more about the situation before determining how to respond.

D. Have a private meeting with the team lead to discover more about the situation before determining how to respond.

A project manager (PM) must break down the development of a game development project to its five engineers, three testers, and two designers. The team is currently using the agile framework to develop the game. How could the PM break down the project backlog? A. In this order: Level 1, Level 2, and Level 3 B. In this order: Level 2, Level 1, and Level 3 C. In this order: User Stories, Epic, and Features D. In this order: Epic, Feature, and User Stories

D. In this order: Epic, Feature, and User Stories

A project manager (PM) prepares for the project closure meeting. Why is the PM including a lessons learned workshop? A. It provides opportunity for the team to discuss challenges during the project. B. It summarizes the project deliverables or product. C. It represents the largest agenda item for the project closure meeting. D. It provides the best resource for improving future projects.

D. It provides the best resource for improving future projects.

A database manager has begun to notice a decline in key performance indicators (KPIs) on their database. Which phase of the resource lifecycle should the manager prioritize first? A. Acquisition B. Retirement C. Improvement D. Maintenance and monitoring

D. Maintenance and monitoring

A project manager (PM) drafts a sequence of activities for a government website creation project catered to people with disabilities. However, the engineers cannot hand over the project until the accessibility auditor from the third-party organization verifies the accessibility standards for this website comply with the American Disabilities Act (ADA). What would be the best category for this dependency? A. Internal dependency B. Internal discretionary dependency C. Mandatory dependency D. Mandatory external dependency

D. Mandatory external dependency

A procurement specialist collects information to develop the criteria to include in a request for proposal (RFP) for a specific product. What function can the procurement specialist perform to collect information about the product, industry trends, and potential suppliers? A. Competitive analysis B. Request for information C. Purchase requisitions D. Market research

D. Market research

The project team plans to notify customers about changes to how they log in to a system. The team plans to inform customers that login credentials will remain the same, but the logging-in process will look different. This type of change falls into what category? A. Routine change B. Standard change C. Emergency change D. Normal change

D. Normal change

A project manager prepares to distribute tasks to the project team. Before doing this, the project manager must determine each team member's available time. How will the project manager calculate a team member's available time? A. Overhead hours subtracted from allocation time B. The number of projects on which the employee is working divided by working hours in a week C. Overhead time divided by working hours D. Overhead hours subtracted from available working hours

D. Overhead hours subtracted from available working hours

A software development project consists of a design activity with a duration of three weeks, a development activity with a duration of six weeks, and a testing activity with a duration of two weeks. The design, development, and testing activities are on a critical path method (CPM) diagram. Based on this information, what is true about this project? A. The total float for the design, development, and testing activities is 11. B. The total float for the design, development, and testing activities is 2. C. The total float for the design, development, and testing activities is 8. D. The total float for the design, development, and testing activities is 0.

D. The total float for the design, development, and testing activities is 0.

The equipment delivery team leader has left a voicemail saying that a forest fire in California might prevent the equipment from arriving on time. The team leader wanted to give the customer an advanced warning. Which of the following statements is true? A. This is a contingency plan. B. This is a residual risk. C. This is a risk mitigation plan. D. This is a trigger.

D. This is a trigger.

A project manager is in the process of finding the likelihood of a project risk. Of the following, which of the tools can the team NOT use? A. Probability impact B. Scenario analysis C. FMEA D. Utilization gap

D. Utilization gap

What is NOT an activity of the execution phase? A. Execute tasks according to the project plan. B. Monitor project progress. C. Conduct meetings. D. Validate deliverables.

D. Validate deliverables.

What event triggers the movement of a risk from the risk register to the issue log? A. It is a requirement that risks should be on both the risk register and issue log. B. When the project manager (PM) has an action plan to respond to the risk, it moves to the issue log. C. When the PM has identified the risk as having a high likelihood of occurring, it moves to the issue log. D. When the risk materializes, it moves to the issue log.

D. When the risk materializes, it moves to the issue log.


Kaugnay na mga set ng pag-aaral

Chapter 5: Civil Rights (Inquizitive)

View Set

Cultural, Social, and Ethnic Diversity

View Set

CH 60 EAQ Cranial Nerve Disorders and Polyneuropathis

View Set