System Analysis and Design: Project Management (CH3)

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

The Rational Unified Process (RUP) framework is incompatible with the PMBOK. Answers: True False

False

The burndown chart is a Scrum created artifact that provides a list of features prioritized by business value. Answers: True False

False

An organization's project management plan expresses the vision, mission, goals, objectives, and strategies of the organization. Answers: True False

False

Decisions and actions taken in one knowledge area at a certain time rarely affect other knowledge areas. Answers: True False

False

Initiating and closing tasks are usually the longest and require the most amount of resources and time. Answers: True False

False

Initiating processes are not required to end a project. Answers: True False

False

Which process includes measuring progress toward project objectives and taking corrective action to match progress with the plan? Answers: a. Executing b. Planning c. Initiating d. Monitoring and controlling

Monitoring and controlling

What processes include devising and maintaining a workable scheme to ensure that the project addresses the organization's needs? Answers: a. Executing b. Initiating c. Planning d. Monitoring and controlling

Planning

Kick-off meeting agendas are usually recorded in a Word document. Answers: True False

True

Many project management activities occur as part of the planning process group. Answers: True False

True

Monitoring and controlling processes overlap all of the other project management Answers: True False

True

The DMAIC (Define, Measure, Analyze, Improve, and Control) methodology of the Six Sigma projects, is used to improve an existing business process. Answers: True False

True

The level of activity and length of each process group varies for every project. Answers: True False

True

Which planning process is within the Project Scope Management knowledge area? Answers: a. Schedule development b. Quality planning c. Developing a project management plan d. Creation of a WBS

Creation of a WBS

The project scope management knowledge area maps to which process group through the activities of scope validation and scope control? Answers: a. planning b. initiating c. monitoring and controlling d. executing

monitoring and controlling

What is the main purpose of project plans? Answers: a. guide project execution b. define project scope c. schedule management plans d. estimate activity resources

guide project execution

What process group does the project integration management knowledge area map to through the activities of developing project charters? Answers: a. planning b. monitoring and controlling c. initiating d. executing

initiating

The project cost management knowledge area maps to which process group through the activities of estimating costs and budget determination? Answers: a. monitoring and controlling b. planning c. executing d. initiating

planning

What important Scrum artifact is used to graphically display progress on each sprint during the monitoring and controlling process? Answers: a. sprint backlog b. burndown chart c. product backlog d. WBS

burndown chart

Agile methods are used when deliverables have a low degree of change. Answers: True False

False

Which is an example of a pre-initiation task? Answers: a. Drafting the project charter b. Developing a business case for a project c. Identifying stakeholders d. Drawing up a work breakdown structure

Developing a business case for a project

Key outcomes of the executing process group are formal acceptance of the work and creation of closing documents. Answers: True False

False

The pre-initiation phase of a project using the Scrum method does not involve project charters, stakeholder management strategy, and kick-off meetings. Answers: True False

False

A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint. Answers: True False

True

The WBS provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance. Answers: True False

True

The executing process group generally requires the most resources. Answers: True False

True

The project schedule management knowledge area maps to which process group through the activity of schedule control? Answers: a. executing b. initiating c. planning d. monitoring and controlling

monitoring and controlling

Project initiation involves taking the actions necessary to ensure that activities in the project plan are completed. Answers: True False

False

The output of the stakeholder management strategy results is a project charter. Answers: True False

False

Identifying the project sponsor is a pre-initiation task. Answers: True False

True

Initiating processes take place during each phase of a project. Answers: True False

True

The two main items for monitoring and controlling in the Scrum framework are the daily Scrum and the sprint retrospectives. Answers: True False

True

What tool provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance? Answers: a. work breakdown structure b. project charter c. cost management plan d. scope statement

work breakdown structure

In the Scrum method, team members work as a self-directed group coached by the ScrumMaster. Answers: True False

True

Which are outputs of the executing process of project integration management? Answers: a. Enterprise environmental factor updates b. Resource calendars c. Issue logs d. Deliverables

Deliverables

Which process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end? Answers: a. closing b. planning c. monitoring d. executing

closing

A milestone list is an output associated with the Project Scope Management knowledge area. Answers: True False

False

What process provides enterprise environmental factors as an output? Answers: a. project human resource management b. project integration management c. project quality management d. project procurement management

project human resource management

Which planning process is associated with project scope management? Answers: a. Planning schedule management b. Performing qualitative risk analysis c. Collecting requirements d. Estimating costs

Collecting requirements

What processes include defining and authorizing a project or project phase? Answers: a. Executing b. Initiating c. Planning d. Monitoring and controlling

Initiating

Which is true about the agile method? Answers: a. It is often used when a project team can express the scope early in the product life cycle. b. It is used when a project team wants to provide a potentially shippable product earlier rather than later. c. It is used when project teams want to use the predicative approach to a project. d. It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.

It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.

Which project would be compatible with the use of the agile approach? Answers: a. Projects with clear-up front requirements b. Projects that have a fairly rigid completion date c. Projects that have more flexible scheduling d. Projects with inexperienced and dispersed teams

Projects that have more flexible scheduling

Which framework is an iterative software development process that focuses on team productivity and delivers software best practices to all team members? Answers: a. Six Sigma b. Dynamic Systems Development Method c. Rational Unified Process d. Agile Unified Process

Rational Unified Process

The project management plan is the output of which project planning process? Answers: a. integration management b. procurement management c. quality management d. scope management

integration management

Administrative activities, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project, are often involved in which processes? Answers: a. initiating b. monitoring and controlling c. closing d. executing

closing

What is one of the main outputs of the initiation process? nswers: a. selecting the project manager b. identifying the project sponsor c. developing the project charter d. creating the work breakdown structure

developing the project charter

The organization recognizes that a new project exists and completes a project charter during which processes for a new project? Answers: a. opening b. controlling c. initiating d. planning

initiating

The project stakeholder management knowledge area maps to which process group by identifying stakeholders? Answers: a. planning b. initiating c. executing d. monitoring and controlling

initiating

What is developed in the Project Integration Management knowledge area? Answers: a. project management plan b. quality management c. WBS d. schedule management plan

project management plan

In the Scrum method, during which meeting is the improvement of the product and process discussed? Answers: a. daily Scrum b. kick-off c. sprint review d. sprint retrospective

sprint retrospective

A _____ is usually not necessary to the Scrum method, because Scrum implies that team members work as a self-directed group. Answers: a. Gantt chart b. team charter c. velocity estimate d. product backlog

team charter

Reporting performance, where project stakeholders can identify any necessary changes that may be required to keep the project on track, is a common part of which process? Answers: a. executing b. monitoring and controlling c. closing d. planning

monitoring and controlling

An organizational process assets update is the output of which closing process? Answers: a. project time management b. project quality management c. project integration management d. project procurement management

project integration management

Which activity is a part of the Scrum planning process? Answers: a. Creating sprint backlog b. Demonstrating the product during a sprint review meeting c. Determining how many sprints will compose each release d. Completing tasks each day during sprints

Creating sprint backlog

Which processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements? Answers: a. executing b. planning c. monitoring and controlling d. initiating

executing

What is often the most difficult and unappreciated process in project management? Answers: a. monitoring and controlling b. initiating c. planning d. executing

planning

The kick-off meeting is always held before the business case and project charter are completed. Answers: True False

False


Kaugnay na mga set ng pag-aaral

Introduction to Computer Science

View Set

Translation (Requires Codon Chart)

View Set

PSY-Chapter 9: Extinction of Conditioned Behavior

View Set

Enzymes Workbook Pages IB by Mahin Acharya

View Set

13:Reproduction [The Endocrine System]

View Set