BTE 417 Test 2 Sample Questions

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

if a project team goes from 3 people to 6 people how many more communication channels are there

12

pv=100k ev=60k what is spi of project

60

Which of the following is not advice for closing projects or phases? A. You don't need to celebrate completing a project, especially if it did not go well. B. You should capture lessons learned as soon as possible, not just at the end of a project C. You should include tasks in the WBS for project closing D. You should assign resources to specific project closing tasks

A. You don't need to celebrate completing a project, especially if it did not go well

Answering questions such as, "What will you do differently on the next project based on your experience working on this project?" is part of a __________. A. lessons-learned report B. customer acceptance/project completion form C. written notice of contract closure D. transition plan

A. lessons-learned report

What is the most common reason for closing or terminating a project? A. addition B. integration C. extinction D. starvation

B. integration

A __________ is another name for a project close-out meeting. A. celebration B. post project C. final review D. post mortem

D. post mortem

Assume you have collected the following data for your project. Its budget is $75,000 and it is expected to last four months. After two months, you have calculated the following information about the project. PV = $45,000 EV = $38,500 AC = $37,000 Calculate the SPI and CPI. Good news or Bad?

SPI = EV/PV = $38,500/45,000 = .86 CPI = EV/AC = $38,500/37,000 = 1.04 SPI < 1 ~ behind schedule CPI > 1 ~ under budget

all are examples of signifiant project risk except

all are significant potential project risks (financial, technical, commercial)

Given the following information, determine the EV of your project. AC = $120,000 PV = $125,000 CV = -$10,000 a. $130,000 b. $110,000 c. $90,000 d. $120,000

b Justification: The formula to calculate CV is EV - AC, so when given both CV and AC, you can use this formula as a basis for solving for EV. CV = EV - AC EV = CV + AC EV = -$10,000 + $120,000 EV = $110,000

most preferred conflict handling mode

confrontation

the ____ should include requirements for formal acceptance and closure of contracts

contract itself

which is not an example of team development strategy

creating a WBS for the project

which of the following is not an example of a soft skill

financial analysis

if the (cpi) is less than 100%, the (eac) is going to be ___ than the (bac)

higher

the knowledge area not involved in monitoring and controlling

human resource management

what is the most common reason for closing or terminating a project

integration

a ____ chart is a histogram that can help you identify and prioritize problem areas

pareto

what two dimensions should you use when evaluating project risks

probability and impact

_____ is defined as the degree to which a set of inherent characteristics fulfill requirements

quality

____ included all of the activities related to satisfying relevant quality standards for projects

quality assurance

a RACI chart is a type of

responsibility assignment matrix

these issues cause more conflict than others on projects

schedule issues

buyers develop a ____ of top 3 to 5 suppliers to reduce work involved in selecting a source

short list

a ____ describes when and how people will be added to and taken off of a project

staffing management plan

type of plan the helps create a smooth turnover of the the project into normal operations

transition plan

____ are unplanned responses to risk events

workarounds