BTE 417 Test 2 Sample Questions
if a project team goes from 3 people to 6 people how many more communication channels are there
12
pv=100k ev=60k what is spi of project
60
Which of the following is not advice for closing projects or phases? A. You don't need to celebrate completing a project, especially if it did not go well. B. You should capture lessons learned as soon as possible, not just at the end of a project C. You should include tasks in the WBS for project closing D. You should assign resources to specific project closing tasks
A. You don't need to celebrate completing a project, especially if it did not go well
Answering questions such as, "What will you do differently on the next project based on your experience working on this project?" is part of a __________. A. lessons-learned report B. customer acceptance/project completion form C. written notice of contract closure D. transition plan
A. lessons-learned report
What is the most common reason for closing or terminating a project? A. addition B. integration C. extinction D. starvation
B. integration
A __________ is another name for a project close-out meeting. A. celebration B. post project C. final review D. post mortem
D. post mortem
Assume you have collected the following data for your project. Its budget is $75,000 and it is expected to last four months. After two months, you have calculated the following information about the project. PV = $45,000 EV = $38,500 AC = $37,000 Calculate the SPI and CPI. Good news or Bad?
SPI = EV/PV = $38,500/45,000 = .86 CPI = EV/AC = $38,500/37,000 = 1.04 SPI < 1 ~ behind schedule CPI > 1 ~ under budget
all are examples of signifiant project risk except
all are significant potential project risks (financial, technical, commercial)
Given the following information, determine the EV of your project. AC = $120,000 PV = $125,000 CV = -$10,000 a. $130,000 b. $110,000 c. $90,000 d. $120,000
b Justification: The formula to calculate CV is EV - AC, so when given both CV and AC, you can use this formula as a basis for solving for EV. CV = EV - AC EV = CV + AC EV = -$10,000 + $120,000 EV = $110,000
most preferred conflict handling mode
confrontation
the ____ should include requirements for formal acceptance and closure of contracts
contract itself
which is not an example of team development strategy
creating a WBS for the project
which of the following is not an example of a soft skill
financial analysis
if the (cpi) is less than 100%, the (eac) is going to be ___ than the (bac)
higher
the knowledge area not involved in monitoring and controlling
human resource management
what is the most common reason for closing or terminating a project
integration
a ____ chart is a histogram that can help you identify and prioritize problem areas
pareto
what two dimensions should you use when evaluating project risks
probability and impact
_____ is defined as the degree to which a set of inherent characteristics fulfill requirements
quality
____ included all of the activities related to satisfying relevant quality standards for projects
quality assurance
a RACI chart is a type of
responsibility assignment matrix
these issues cause more conflict than others on projects
schedule issues
buyers develop a ____ of top 3 to 5 suppliers to reduce work involved in selecting a source
short list
a ____ describes when and how people will be added to and taken off of a project
staffing management plan
type of plan the helps create a smooth turnover of the the project into normal operations
transition plan
____ are unplanned responses to risk events
workarounds