Ch 3 Quiz
Which process group normally requires the most resources and time.
Executing
Initiating involves developing a project charter, which is part of the project ________ management knowledge area.
Integration
What type of report do project teams create to reflect on what went right and what went wrong with the project?
Lessons-learned report
________ involves measuring progress toward project objectives and taking corrective actions.
Monitoring and controling
What methodology was developed in the U.K. , defines 45 separate subprocesses, and organizes these into eight process group.
PRINCE2
A work breakdown structure, project schedule, and cost estimates are outputs of the _________ process.
Planning
A ________ is a series of actions directed toward a particular result.
Process
Which of the following outputs is often completed before initiating a project?
business case
Many people use ________ to have a standard format for preparing various project management documents.
templates