(midterm) not the best practice that can help in avoiding scope problems on IT project A. use off the shelf software and hardware whenever possible B. don't involve too many users in scope management

B. don't involve too many users in scope management

PDM uses all of the following except (exam) A leads and lags B lags and leads C dummy activities D Finish to start relationship E finish to finish relationship

C dummy activities

26. _____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them. a. Collecting requirements b. Defining scope c. Controlling scope d. Validating scope

a. Collecting requirements

47. _____ refers to the process of developing a working replica of the system or some aspect of the system. a. Prototyping b. Variance c. Decomposition d. Use case modeling

a. Prototyping

45. _____ involves formal acceptance of the completed project scope by the stakeholders. a. Scope validation b. Scope planning c. Scope control d. Scope baseline

a. Scope validation

29. Creating the WBS is a subprocess associated with the _____ process in project scope management. a. planning b. monitoring and controlling c. closing d. executing

a. planning

32. A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed. a. requirements traceability matrix b. Gantt chart c. state transition table d. entity-attribute-value model

a. requirements traceability matrix

44. Scope creep refers to: a. the tendency for project scope to keep getting bigger and bigger. b. subdividing project deliverables into smaller pieces. c. the approved project scope statement and its associated WBS. d. a task at the lowest level of the WBS.

a. the tendency for project scope to keep getting bigger and bigger.

43. Which of the following is recommended for the creation of a good WBS? a. Any WBS item should be the responsibility of all the people working on it. b. A unit of work should appear at only one place in the WBS. c. Each WBS item should be created assuming that the requirements are inflexible. d. The work content of a WBS item is independent of the WBS items below it.

b. A unit of work should appear at only one place in the WBS.

27. _____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved. a. Creating scope b. Defining scope c. Controlling scope d. Validating scope

b. Defining scope

49. _____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems. a. Prototyping b. JAD c. RAD d. Use case modeling

b. JAD

46. _____ refers to the difference between planned and actual performance. a. Decomposition b. Variance c. Scope validation d. Scope creep

b. Variance

31. Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____. a. variance b. benchmarking c. prototyping d. decomposition

b. benchmarking

41. In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS. a. analogy b. bottom-up c. top-down d. mind mapping

b. bottom-up

30. The ______ documents how project needs will be analyzed, documented, and managed. a. requirements traceability matrix b. requirements management plan c. WBS d. project scope statement

b. requirements management plan

36. The _____ should list and describe all of the deliverables required for the project. a. project charter b. scope statement c. WBS d. Gantt chart

b. scope statement

34. The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces. a. conglomeration b. accumulation c. decomposition d. catalyzation

c. decomposition

42. Mind mapping can be used for developing WBSs using a. the analogy approach only b. the bottom-up or analogy approach c. the top-down or bottom-up approach d. any approach

c. the top-down or bottom-up approach

38. The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail. a. analogy b. bottom-up c. top-down d. mind mapping

c. top-down

39. The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items. a. analogy b. bottom-up c. top-down d. mind mapping

c. top-down

48. _____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them. a. Prototyping b. JAD c. RAD d. Use case modeling

d. Use case modeling

28. _____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables. a. Creating scope b. Defining scope c. Controlling scope d. Validating scope

d. Validating scope

37. In the _____approach for constructing a WBS, you use a similar project's WBS as a starting point. a. top-down b. bottom-up c. mind-mapping d. analogy

d. analogy

40. The _____ technique for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks. a. analogy b. bottom-up c. top-down d. mind mapping

d. mind mapping

25. Scope refers to: a. each level of work that is outlined in a work breakdown structure. b. the end product created as part of a project that is delivered to the client. c. tasks that are decomposed into smaller tasks in a work breakdown structure. d. the work involved in creating the products and the processes used to create them.

d. the work involved in creating the products and the processes used to create them.

33. A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. a. project charter b. business case c. project scope statement d. work breakdown structure

d. work breakdown structure

35. A(n) ____ is a task at the lowest level of the WBS. a. variance b. objective c. deliverable d. work package

d. work package


Ensembles d'études connexes

Chapter 15: Medical Expense Insurance

View Set

COSC1301_ReviewQuestions_PowerPoint_1-3 Office 2019

View Set

CommonLit (HOW RESILIENCE WORKS) Assessment Answers (Not Activity)

View Set

Med Surg Ch 46 Gastric & Duodenal Disorders

View Set

Giddens Chapter 13 Intracranial Regulation

View Set

Network+ Guide to networks, 8e Midterm Test

View Set