OM 303 - Module 3

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

Program evaluation and review technique (PERT)

A project management technique that employs three time estimates for each activity.

Critical path method (CPM)

A project management technique that uses only one time factor per activity.

The critical path for the network activities shown below is ________ with duration ________. - A-C; 12 - A-D-E; 19 - B-E; 13 - A-B-C-D-E; 29 - None of these

A-D-E; 19

Optimistic time

The "best" activity completion time that could be obtained in a PERT network.

Pessimistic time

The "worst" activity time that could be expected in a PERT network.

critical path

The computed longest time path(s) through a network.

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete? - 0.1587 - near zero - 0.0126 - 0.8413 - 2.14

0.1587

Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline? - 0.0401 - 0.4599 - 0.8056 - 0.9599 - near 1.0000, or almost certain

0.9599

A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to nearest day)? - 807 - 631 - 689 - 1009 - 833

807

Work Breakdown Structure (WBS)

A hierarchical description of a project into more and more detailed components.

Activity-on-arrow (AOA)

A network diagram in which arrows designate activities.

Activity-on-node (AON)

A network diagram in which nodes designate activities.

Critical path analysis

A process that helps determine a project schedule.

Forward pass

A process that identifies all the early times.

Dummy activity

An activity having no time that is inserted into a network to maintain the logic of the network.

Backward pass

An activity that finds all the late start and late finish times.

Project Organization

An organization formed to ensure that programs (projects) receive the proper management and attention.

A project organization works best for an organization when the project resides in only one of its functional areas. - True - False

False

Slack time

Free time for an activity. Also referred to as free float or free slack.

Agile projects

Ill-defined projects requiring collaboration and constant feedback to adjust to project unknowns.

A project manager is interested in crashing a project with variable activity times. Which of the following tools should he/she employ? - Gantt Chart - PERT, CPM, or a Gantt chart are fine. - PERT - CPM - either PERT or CPM

PERT

GANTT charts

Planning charts used to schedule resources and allocate time.

Waterfall projects

Projects that progress smoothly in a step-by-step manner until completed.

Crashing

Shortening activity time in a network to reduce time on the critical path so total completion time is reduced.

A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8. - The critical path is A-B-C, duration 15. - The critical path is A-B-C, duration 13.5 - The network has no critical path. - The critical path is A-C, duration 12. - The critical path cannot be determined without knowing PERT expected activity times.

The critical path is A-B-C, duration 15.

Most likely time

The most probably time to complete an activity in a PERT network.

In project management, crashing an activity must consider the impact on all paths in the network. - True - False

True

A project organization that becomes permanent is often referred to as a: - standard organization. - normal organization. - matrix organization. - fixed project organization. - permanent project organization.

matrix organization


Ensembles d'études connexes

Ch 1: The Sciences of Anatomy and Physiology BIO 67A

View Set

Types of Life Insurance Policies

View Set

Business Foundation Chapter 2 review

View Set

PHL 255 Non-Western Philosophy Exam 1

View Set

Chapter 14 & 15 Somatic and Autonomic Nervous Systems

View Set