PI c5

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

19. Which of the following is recommended for the creation of a good WBS? a. Any WBS item should be the responsibility of all the people working on it. c. Each WBS item should be created assuming that the requirements are inflexible. b. A unit of work should appear at only one place in the WBS. d. The work content of a WBS item is independent of the WBS items below it.

B

21. A unit of work should appear at only one place in the WBS.

T

3. _____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them. a. Collecting requirements c. Controlling scope b. Defining scope d. Validating scope

A

9. A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed. a. requirements traceability matrix c. state transition table b. Gantt chart d. entity-attribute-value model

A

4. _____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved. a. Creating scope c. Controlling scope b. Defining scope d. Validating scope

B

7. The ______ documents how project needs will be analyzed, documented, and managed. a. requirements traceability matrix c. WBS b. requirements management plan d. project scope statement

B

15. The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail. a. analogy c. top-down b. bottom-up d. mind mapping

C

10. A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. a. project charter c. project scope statement b. business case d. work breakdown structure

D

14. A work package represents one component of the product that the project aims to deliver.

F

15. A work package must always represent less than 80 hours of work.

F

7. Project scope statements must include the project boundaries, constraints, and assumptions.

F

8. The scope of a project is clear and specific from the start.

F


Ensembles d'études connexes

Ch. 26- FL Laws and Rules Pertinent to Life and Health Insurance

View Set

PrepU ch 22. Nursing Management of the Postpartum Woman at Risk

View Set

ACCT 430 - Chapter 4 - International Financial Reporting Standards: Part 1

View Set

NUR 105; critical thinking questions for Fluid and Electrolytes and ABGs

View Set

INFORMATION SYSTEMS (Module 2 Unit 3)

View Set

Wildlife Policy and Administration Exam 1

View Set

Chapter 19: Assessing Thorax and Lungs

View Set

DECA - Advertising 100 test Study Guide

View Set

Federalism in the Constitution Assignment

View Set