An activity's normal time and cost are 10 and $120, respectively. Its estimated crash time and cost are 7 and $180, respectively. What is this activity's crash cost per time unit?

$60 / 3 = 20

Which of the following projects would be least benefited if additional resources were added?

Developing new software

Compressing activities on a project with a sensitive project network will:

Increase risk of delaying the project and reduce scheduling flexibility.

Which of the following is NOT one of the more commonly used options for cutting project costs? Reduce project scope Have owner take more responsibility Move the completion date further out Brainstorm cost savings options Outsource project activities

Move the completion date further out

When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors? The inherent risk associated with the activity How crashing will impact the morale and motivation of the individuals working on that activity Resource availability after crashing that activity The level of difficulty involved in completing the activity When during the project the activity will occur

The level of difficulty involved in completing the activity

Erin has just learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?

identify the critical path

As a project is crashed and project duration is reduced, direct costs typically

increase

The less steep the cost slope of an activity, the

less it costs to shorten one time period

When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of

reduce project scope

Reducing project duration involves crashing all activities to their crash point. can only be done when resources are not constrained. is always more expensive. tends to increase network sensitivity. should be considered for all projects.

tends to increase network sensitivity

When reducing project duration, the duration for a project that is optimal is at the point where

total project costs are the lowest

When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option? Establish a core project team Fast-tracking Reduce project scope Compromise quality Use critical-chain project management

Establish a core project team

When crashing a schedule, this may set in when a least-cost method is used.

Fatigue and resentment

When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?

Find the activity with the lowest crash cost

When the project team is salaried, which of the following is the preferred choice for accelerating project completion?

Schedule overtime


Ensembles d'études connexes

Chapter 09: Maternal and Fetal Nutrition

View Set

DYGI Questions Chapter 9 Part 2: The Endocrine System

View Set

Chapter-11: Tactical Ventilatioin

View Set

Chapter 4: Validity and Test Development

View Set

Animal Development Quiz #2 Questions

View Set